Progressive Review for the month(s) of : January - 2021, January - 2019, February - 2021, February - 2019, March - 2021, March - 2019, April - 2021, April - 2019, May - 2021, July - 2020, July - 2018, August - 2020, September - 2020, September - 2018, October - 2020, November - 2018, December - 2020, December - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
51
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 37.85 20.3 0 0 0 0 20.3 17.55 - 54%
September - 2018
GF - flooring completed. FF - finishing stage.
No Image
Bannu (construction of new mohafiz khana/record rooms)
51
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 37.85 20.3 0 0 0 0 20.3 17.55 - 54%
July - 2018
GF - flooring completed. FF - finishing stage.
No Image
Bannu (construction of new mohafiz khana/record rooms)
51
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 36.281 28.023 0 0 0 0 28.023 8.258 - 77%
September - 2018
Completed & H/O.
No Image
Construction of Mohafiz Khana / Record Room in District Charsadda
51
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 36.281 28.023 0 0 0 0 28.023 8.258 - 77%
July - 2018
Completed & H/O.
No Image
Construction of Mohafiz Khana / Record Room in District Charsadda
51
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Chitral
30-11--1 30-11--1 - 30-11--1 - 52.566 19 0 0 0 0 19 33.566 - 36%
September - 2018
GF - finishing in progres. FF - roof trusses in progress.
No Image
Muhafiz Khana, Chitral
51
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Chitral
30-11--1 30-11--1 - 30-11--1 - 52.566 19 0 0 0 0 19 33.566 - 36%
July - 2018
GF - finishing in progres. FF - roof trusses in progress.
No Image
Muhafiz Khana, Chitral
51
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Hangu
30-11--1 30-11--1 - 30-11--1 - 38.26 29.615 0 0 0 0 29.615 8.645 - 77%
September - 2018
Finishing in progress.
No Image
District Hangu
51
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Hangu
30-11--1 30-11--1 - 30-11--1 - 38.26 29.615 0 0 0 0 29.615 8.645 - 77%
July - 2018
Finishing in progress.
No Image
District Hangu
51
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Karak
30-11--1 30-11--1 - 30-11--1 - 34.989 22.772 1 1 1 0 22.772 11.217 68% 65%
September - 2018
Main building - flooring in progress. Pressure Pump, ground reservoir tank completed. CW 95% completed.
No Image
Karak
51
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Karak
30-11--1 30-11--1 - 30-11--1 - 34.989 22.772 0 0 0 0 22.772 12.217 - 65%
July - 2018
Main building - flooring in progress. Pressure Pump, ground reservoir tank completed. CW 95% completed.
No Image
Karak
51
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 36.702 27.7 0 0 0 0 27.7 9.002 - 75%
September - 2018
Main building - in progress. CW 95% work completed.
No Image
Mohafiz Khana / Record Room in District Lakki Marwat PK-76
51
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 36.702 27.7 0 0 0 0 27.7 9.002 - 75%
July - 2018
Main building - in progress. CW 95% work completed.
No Image
Mohafiz Khana / Record Room in District Lakki Marwat PK-76
51
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 460.844 132.837 28.737 28.737 18.736 18.736 151.573 299.27 35% 33%
December - 2018
Academic block - basement roof laid. Block-B - basement roofing in progress. Block-C - basement columns in progress.
No Image
Akora Khattak Nowshera
51
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 460.844 132.837 28.737 28.737 18.736 18.548 151.385 299.27 35% 33%
November - 2018
Academic block - basement roof laid. Block-B - basement roofing in progress. Block-C - basement columns in progress.
No Image
Akora Khattak Nowshera
51
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 460.844 132.837 28.737 28.737 18.736 18.548 151.385 299.27 35% 33%
November - 2018
Academic block - basement roof laid. Block-B - basement roofing in progress. Block-C - basement columns in progress.
No Image
Akora Khattak Nowshera
51
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 460.844 132.837 28.737 48.736 48.736 39.585 172.422 299.27 35% 37%
April - 2019
Academic block - basement roof laid. Block-B - basement roofing in progress. Block-C - basement columns in progress.
No Image
Akora Khattak Nowshera
51
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 460.844 132.837 28.737 48.736 48.736 39.585 172.422 299.27 35% 37%
March - 2019
Academic block - basement roof laid. Block-B - basement roofing in progress. Block-C - basement columns in progress.
No Image
Akora Khattak Nowshera
51
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 460.844 132.837 28.737 48.736 48.736 39.585 172.422 299.27 35% 37%
March - 2019
Academic block - basement roof laid. Block-B - basement roofing in progress. Block-C - basement columns in progress.
No Image
Akora Khattak Nowshera
51
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 460.844 132.837 28.737 28.737 18.736 18.736 151.573 299.27 35% 33%
February - 2019
Academic block - basement roof laid. Block-B - basement roofing in progress. Block-C - basement columns in progress.
No Image
Akora Khattak Nowshera
51
(OG)
160607-Construction and rehabilitation of Darul Uloom Haqannia, Akora Khattak.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 460.844 132.837 28.737 28.737 18.736 18.736 151.573 299.27 35% 33%
January - 2019
Academic block - basement roof laid. Block-B - basement roofing in progress. Block-C - basement columns in progress.
No Image
Akora Khattak Nowshera
51
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 50.166 31.172 0 0 0 0 31.172 18.994 - 62%
September - 2018
RW 70% completed. FF - roof laid, 2nd floor roof laid.
No Image
PK-05, Peshawar
51
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 50.166 31.172 0 0 0 0 31.172 18.994 - 62%
July - 2018
RW 70% completed. FF - roof laid, 2nd floor roof laid.
No Image
PK-05, Peshawar
51
(OG)
191107-190332 - Provision for purchase of earth moving machinery for Land Reclamation in Merged Areas. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 500 0 0 0 0 0 0 0 - -
December - 2020
No Image
51
(OG)
191107-190332 - Provision for purchase of earth moving machinery for Land Reclamation in Merged Areas. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 500 0 0 0 0 0 0 0 - -
December - 2020
No Image
51
(OG)
191107-190332 - Provision for purchase of earth moving machinery for Land Reclamation in Merged Areas. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 500 0 0 0 0 0 0 0 - -
October - 2020
No Image
51
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Provincial
30-11--1 30-11--1 - 30-11--1 - 285.843 75 10 10 0 0 75 0 - -
September - 2018
PC-I/DCE submitted.
No Image
51
(OG)
191107-190332 - Provision for purchase of earth moving machinery for Land Reclamation in Merged Areas. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 500 0 0 0 0 0 0 0 - -
September - 2020
No Image
51
(OG)
191107-190332 - Provision for purchase of earth moving machinery for Land Reclamation in Merged Areas. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 500 0 0 0 0 0 0 0 - -
August - 2020
No Image
51
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Provincial
30-11--1 30-11--1 - 30-11--1 - 285.843 75 10 10 0 0 75 0 - -
July - 2018
PC-I/DCE submitted.
No Image
51
(OG)
191107-190332 - Provision for purchase of earth moving machinery for Land Reclamation in Merged Areas. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 500 0 0 0 0 0 0 0 - -
July - 2020
No Image
51
(OG)
191107-190332 - Provision for purchase of earth moving machinery for Land Reclamation in Merged Areas. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 500 0 0 0 0 0 0 0 - -
May - 2021
No Image
51
(OG)
191107-190332 - Provision for purchase of earth moving machinery for Land Reclamation in Merged Areas. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 500 0 0 0 0 0 0 0 - -
April - 2021
No Image
51
(OG)
191107-190332 - Provision for purchase of earth moving machinery for Land Reclamation in Merged Areas. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 500 0 0 0 0 0 0 0 - -
March - 2021
No Image
51
(OG)
191107-190332 - Provision for purchase of earth moving machinery for Land Reclamation in Merged Areas. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 500 0 0 0 0 0 0 0 - -
February - 2021
No Image
51
(OG)
191107-190332 - Provision for purchase of earth moving machinery for Land Reclamation in Merged Areas. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 500 0 0 0 0 0 0 0 - -
January - 2021
No Image