Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
585 (OG) |
140853-Balance Civil Works and Purchase of Equipment for Ayub College of Dentistry, Abbottabad. |
Abbottabad |
- | - | - | 28-01-15 | - | 447.317 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
Note submitted to ACS by Health Deptt regarding excution of works, decision awaited. |
No Image |
585 (OG) |
140853-Balance Civil Works and Purchase of Equipment for Ayub College of Dentistry, Abbottabad. |
Abbottabad |
- | - | - | 28-01-15 | - | 447.317 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
Note submitted to ACS by Health Deptt regarding excution of works, decision awaited. |
No Image |
585 (OG) |
140853-Balance Civil Works and Purchase of Equipment for Ayub College of Dentistry, Abbottabad. |
Abbottabad |
- | - | - | 28-01-15 | - | 447.317 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
Note submitted to ACS by Health Deptt regarding excution of works, decision awaited. |
No Image |
585 (OG) |
140853-Balance Civil Works and Purchase of Equipment for Ayub College of Dentistry, Abbottabad. |
Abbottabad |
- | - | - | 28-01-15 | - | 447.317 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
Note submitted to ACS by Health Deptt regarding excution of works, decision awaited. |
No Image |
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 3 | 16.75 | 16.75 | 16.75 | 16.25 | 19.25 | 261.636 | 7% |
7% December - 2019 |
Bar Room, ADJ - Finishing in progress |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
585 (OG) |
140853-Balance Civil Works and Purchase of Equipment for Ayub College of Dentistry, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 447.317 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
Note submitted to ACS by Health Deptt regarding excution of works, decision awaited. |
No Image |
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 3 | 16.75 | 16.75 | 16.75 | 16.2 | 19.2 | 261.636 | 7% |
7% November - 2019 |
Bar Room, ADJ - Finishing in progress |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
585 (OG) |
140853-Balance Civil Works and Purchase of Equipment for Ayub College of Dentistry, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 447.317 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
Note submitted to ACS by Health Deptt regarding excution of works, decision awaited. |
No Image |
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 3 | 16.75 | 16.75 | 16.75 | 16.2 | 19.2 | 261.636 | 7% |
7% October - 2019 |
Bar Room, ADJ - Finishing in progress |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 3 | 0 | 0 | 0 | 0 | 3 | 278.386 | - |
1% September - 2019 |
Bar Room, ADJ - Finishing in progress |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 3 | 0 | 0 | 0 | 0 | 3 | 278.386 | - |
1% August - 2019 |
Bar Room, ADJ - Finishing in progress |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
585 (OG) |
140853-Balance Civil Works and Purchase of Equipment for Ayub College of Dentistry, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 447.317 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- June - 2018 |
Note submitted to ACS by Health Deptt regarding excution of works, decision awaited. |
No Image |
585 (OG) |
140853-Balance Civil Works and Purchase of Equipment for Ayub College of Dentistry, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 447.317 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- May - 2018 |
Note submitted to ACS by Health Deptt regarding excution of works, decision awaited. |
No Image |
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 3 | 36.75 | 36.75 | 36.75 | 28.334 | 31.334 | 241.636 | 14% |
11% May - 2020 |
Bar Room, ADJ - Finishing in progress |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
585 (OG) |
140853-Balance Civil Works and Purchase of Equipment for Ayub College of Dentistry, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 447.317 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- April - 2018 |
Note submitted to ACS by Health Deptt regarding excution of works, decision awaited. |
No Image |
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 3 | 36.75 | 36.75 | 36.75 | 28.334 | 31.334 | 241.636 | 14% |
11% April - 2020 |
Bar Room, ADJ - Finishing in progress |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
585 (OG) |
140853-Balance Civil Works and Purchase of Equipment for Ayub College of Dentistry, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 447.317 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- March - 2018 |
Note submitted to ACS by Health Deptt regarding excution of works, decision awaited. |
No Image |
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 3 | 36.75 | 36.75 | 36.75 | 28.334 | 31.334 | 241.636 | 14% |
11% March - 2020 |
Bar Room, ADJ - Finishing in progress |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
585 (OG) |
140853-Balance Civil Works and Purchase of Equipment for Ayub College of Dentistry, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 447.317 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- February - 2018 |
Note submitted to ACS by Health Deptt regarding excution of works, decision awaited. |
No Image |
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 3 | 36.75 | 36.75 | 36.75 | 28.334 | 31.334 | 241.636 | 14% |
11% February - 2020 |
Bar Room, ADJ - Finishing in progress |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
585 (OG) |
140853-Balance Civil Works and Purchase of Equipment for Ayub College of Dentistry, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 447.317 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- January - 2018 |
Note submitted to ACS by Health Deptt regarding excution of works, decision awaited. |
No Image |
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 281.386 | 3 | 16.75 | 16.75 | 16.75 | 16.75 | 19.75 | 261.636 | 7% |
7% January - 2020 |
Bar Room, ADJ - Finishing in progress |
No Image |
Construction of Residenctial requirments for Judicial Officer, Abbottabad | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 6.3 | 0 | 0 | 0 | 0 | 6.3 | 96.982 | - |
6% August - 2019 |
Focal person (XEN Abbottabad). Work order issued on 05/09/2017. Supervising consultant just selected.
Bachelor Hostel - Work started. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 50 | 14.5 | 14.5 | 14.5 | 12.478 | 62.478 | 38.782 | 62% |
60% December - 2019 |
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 50 | 2 | 2 | 2 | 2 | 52 | 51.282 | 50% |
50% November - 2019 |
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 50 | 14.75 | 14.75 | 14.75 | 2.25 | 52.25 | 38.532 | 63% |
51% October - 2019 |
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 6.3 | 0 | 0 | 0 | 0 | 6.3 | 96.982 | - |
6% September - 2019 |
Focal person (XEN Abbottabad). Work order issued on 05/09/2017. Supervising consultant just selected.
Bachelor Hostel - Work started. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 50 | 14.5 | 14.5 | 14.5 | 14.5 | 64.5 | 38.782 | 62% |
62% May - 2020 |
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 50 | 14.5 | 14.5 | 14.5 | 12.478 | 62.478 | 38.782 | 62% |
60% April - 2020 |
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 50 | 14.5 | 14.5 | 14.5 | 12.478 | 62.478 | 38.782 | 62% |
60% March - 2020 |
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 50 | 14.5 | 14.5 | 14.5 | 12.478 | 62.478 | 38.782 | 62% |
60% February - 2020 |
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 103.282 | 50 | 14.5 | 14.5 | 14.5 | 12.478 | 62.478 | 38.782 | 62% |
60% January - 2020 |
Bachelor hostel - completed. FF in progress. |
No Image |
Construction of residences for Judicial Officers in Chitral | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- December - 2019 |
Scheme dropped. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- November - 2019 |
Scheme dropped. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- October - 2019 |
Scheme dropped. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- September - 2019 |
Land acquisition under process. Scheme dropped. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- August - 2019 |
Land acquisition under process. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- May - 2020 |
Scheme dropped. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- April - 2020 |
Scheme dropped. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- March - 2020 |
Scheme dropped. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- February - 2020 |
Scheme dropped. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.286 | 0 | 0 | 0 | 0 | 0 | 0 | 449.286 | - |
- January - 2020 |
Scheme dropped. |
No Image |
Construction of Tehsil Judicial Complex Parova, DI.Khan | |||||||||||||||||||
585 (OG) |
170287-Establishment of Emergency Rescue Service ( Rescue - 1122) in District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 277 | 0 | 2 | 2 | 0 | 0 | 0 | 0 | - |
- September - 2018 |
Site/scope of work not identified. |
No Image |
Hangu | |||||||||||||||||||
585 (OG) |
170287-Establishment of Emergency Rescue Service ( Rescue - 1122) in District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 277 | 0 | 2 | 2 | 0 | 0 | 0 | 0 | - |
- July - 2018 |
Site/scope of work not identified. |
No Image |
Hangu | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 13.124 | 18.5 | 18.5 | 18.5 | 14.364 | 27.488 | 62.48 | 34% |
29% December - 2019 |
2 Nos bungalow - SS in progress. |
No Image |
Residences and allied facilities for Judicial Officer / support staff in Haripur | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 13.124 | 18.5 | 18.5 | 18.5 | 6 | 19.124 | 62.48 | 34% |
20% November - 2019 |
2 Nos bungalow - SS in progress. |
No Image |
Residences and allied facilities for Judicial Officer / support staff in Haripur | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 13.124 | 18.5 | 18.5 | 18.5 | 6 | 19.124 | 62.48 | 34% |
20% October - 2019 |
2 Nos bungalow - SS in progress. |
No Image |
Residences and allied facilities for Judicial Officer / support staff in Haripur | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 13.124 | 6 | 6 | 6 | 4.31 | 17.434 | 74.98 | 20% |
19% September - 2019 |
2 Nos bungalow - SS in progress. |
No Image |
Residences and allied facilities for Judicial Officer / support staff in Haripur | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 13.124 | 0 | 0 | 0 | 0 | 13.124 | 80.98 | - |
14% August - 2019 |
2 Nos bungalow - SS in progress. |
No Image |
Residences and allied facilities for Judicial Officer / support staff in Haripur | |||||||||||||||||||
585 (OG) |
130446-F/S for Assessment of Residential Requirements, Master Planning & Designing of Judicial Complexes in Selected Districts of Khyber Pakhtunkhwa |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 94.104 | 13.124 | 18.5 | 18.5 | 18.5 | 14.364 | 27.488 | 62.48 | 34% |
29% May - 2020 |
2 Nos bungalow - SS in progress. |
No Image |
Residences and allied facilities for Judicial Officer / support staff in Haripur | |||||||||||||||||||