Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 1.5 | 4 | 4 | 4 | 4 | 5.5 | 21.699 | 20% |
20% December - 2019 |
Foundation in progress. BW in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 1.5 | 4 | 4 | 4 | 4 | 5.5 | 21.699 | 20% |
20% November - 2019 |
Foundation in progress. BW in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 1.5 | 4 | 4 | 4 | 1 | 2.5 | 21.699 | 20% |
9% October - 2019 |
Foundation in progress. BW in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 1.5 | 1 | 1 | 1 | 1 | 2.5 | 24.699 | 9% |
9% September - 2019 |
Foundation in progress. BW in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 1.5 | 0 | 0 | 0 | 0 | 1.5 | 25.699 | - |
6% August - 2019 |
Foundation in progress. BW in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 1.5 | 14 | 14 | 14 | 4 | 5.5 | 11.699 | 57% |
20% May - 2020 |
Foundation comleted.
Up to plinth beam in progress. Water supply O/H tank in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 1.5 | 14 | 14 | 14 | 4 | 5.5 | 11.699 | 57% |
20% April - 2020 |
Foundation comleted.
Up to plinth beam in progress. Water supply O/H tank in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 1.5 | 14 | 14 | 14 | 4 | 5.5 | 11.699 | 57% |
20% March - 2020 |
Foundation comleted.
Up to plinth beam in progress. Water supply O/H tank in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 1.5 | 14 | 14 | 14 | 4 | 5.5 | 11.699 | 57% |
20% February - 2020 |
Foundation comleted.
Up to plinth beam in progress. Water supply O/H tank in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.199 | 1.5 | 4 | 4 | 4 | 4 | 5.5 | 21.699 | 20% |
20% January - 2020 |
Foundation comleted.
Up to plinth beam in progress. Water supply O/H tank in progress. |
No Image |
Bachelor Hostel for Judicial Officers in District Buner | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 6.297 | 12 | 12 | 12 | 3.238 | 9.535 | 18.446 | 50% |
26% December - 2019 |
Raft laid, GF column in progress. |
No Image |
Dir Lower | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 6.297 | 12 | 12 | 12 | 3.238 | 9.535 | 18.446 | 50% |
26% November - 2019 |
Raft laid, GF column in progress. |
No Image |
Dir Lower | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 6.297 | 12 | 12 | 12 | 2 | 8.297 | 18.446 | 50% |
23% October - 2019 |
Raft laid, GF column in progress. |
No Image |
Dir Lower | |||||||||||||||||||
592 (OG) |
150658-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 137.445 | 0 | 2 | 2 | 0 | 0 | 0 | 0 | - |
- September - 2018 |
Site not yet identified by client deptt. |
No Image |
Dir Lower | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 6.297 | 2 | 2 | 2 | 2 | 8.297 | 28.446 | 23% |
23% September - 2019 |
Raft laid, GF column in progress. |
No Image |
Dir Lower | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 6.297 | 0 | 0 | 0 | 0 | 6.297 | 30.446 | - |
17% August - 2019 |
Raft laid, GF column in progress. |
No Image |
Dir Lower | |||||||||||||||||||
592 (OG) |
150658-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 137.445 | 0 | 2 | 2 | 0 | 0 | 0 | 0 | - |
- July - 2018 |
Site not yet identified by client deptt. |
No Image |
Dir Lower | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 6.297 | 12 | 12 | 12 | 12 | 18.297 | 18.446 | 50% |
50% May - 2020 |
GF roof laid. |
No Image |
Dir Lower | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 6.297 | 12 | 12 | 12 | 12 | 18.297 | 18.446 | 50% |
50% April - 2020 |
GF roof laid. |
No Image |
Dir Lower | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 6.297 | 12 | 12 | 12 | 12 | 18.297 | 18.446 | 50% |
50% March - 2020 |
GF roof laid. |
No Image |
Dir Lower | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 6.297 | 12 | 12 | 12 | 12 | 18.297 | 18.446 | 50% |
50% February - 2020 |
GF roof laid. |
No Image |
Dir Lower | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.743 | 6.297 | 12 | 12 | 12 | 7.502 | 13.799 | 18.446 | 50% |
38% January - 2020 |
Raft laid, GF slab form workn in progress |
No Image |
Dir Lower | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.647 | 0 | 0 | 0 | 0 | 0 | 0 | 26.647 | - |
- December - 2019 |
Technical bid approval under process. |
No Image |
Construction of Bachelor Hostel for Judicial Officers in Hangu | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.647 | 0 | 0 | 0 | 0 | 0 | 0 | 26.647 | - |
- November - 2019 |
Technical bid opening on 12/11/2019. |
No Image |
Construction of Bachelor Hostel for Judicial Officers in Hangu | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.647 | 0 | 0 | 0 | 0 | 0 | 0 | 26.647 | - |
- October - 2019 |
Technical bid opening on 12/11/2019. |
No Image |
Construction of Bachelor Hostel for Judicial Officers in Hangu | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.647 | 0 | 0 | 0 | 0 | 0 | 0 | 26.647 | - |
- May - 2020 |
Technical bid approval under process. |
No Image |
Construction of Bachelor Hostel for Judicial Officers in Hangu | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.647 | 0 | 0 | 0 | 0 | 0 | 0 | 26.647 | - |
- April - 2020 |
Technical bid approval under process. |
No Image |
Construction of Bachelor Hostel for Judicial Officers in Hangu | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.647 | 0 | 0 | 0 | 0 | 0 | 0 | 26.647 | - |
- March - 2020 |
Technical bid approval under process. |
No Image |
Construction of Bachelor Hostel for Judicial Officers in Hangu | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.647 | 0 | 0 | 0 | 0 | 0 | 0 | 26.647 | - |
- February - 2020 |
Technical bid approval under process. |
No Image |
Construction of Bachelor Hostel for Judicial Officers in Hangu | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 26.647 | 0 | 0 | 0 | 0 | 0 | 0 | 26.647 | - |
- January - 2020 |
Technical bid approval under process. |
No Image |
Construction of Bachelor Hostel for Judicial Officers in Hangu | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 5.25 | 2 | 2 | 2 | 2 | 7.25 | 21.183 | 25% |
25% December - 2019 |
Main building - column completed.
Roof slab steel fabrication in progress. |
No Image |
Karak | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 5.25 | 2 | 2 | 2 | 2 | 7.25 | 21.183 | 25% |
25% November - 2019 |
Main building - column completed.
Roof slab steel fabrication in progress. |
No Image |
Karak | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 5.25 | 2 | 2 | 2 | 0 | 5.25 | 21.183 | 25% |
18% October - 2019 |
Main building - column completed.
Roof slab steel fabrication in progress. |
No Image |
Karak | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 5.25 | 2 | 2 | 2 | 0 | 5.25 | 21.183 | 25% |
18% September - 2019 |
Main building - column completed. Roof slab steel fabrication in progress. |
No Image |
Karak | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 5.25 | 0 | 0 | 0 | 0 | 5.25 | 23.183 | - |
18% August - 2019 |
Main building - column completed. Roof slab steel fabrication in progress. |
No Image |
Karak | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 5.25 | 49.102 | 49.102 | 49.102 | 49.101 | 54.351 | 0 | 100% |
100% May - 2020 |
Main building - column completed.
Roof slab steel fabrication in progress. |
No Image |
Karak | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 5.25 | 2 | 2 | 2 | 2 | 7.25 | 21.183 | 25% |
25% April - 2020 |
Main building - column completed.
Roof slab steel fabrication in progress. |
No Image |
Karak | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 5.25 | 2 | 2 | 2 | 2 | 7.25 | 21.183 | 25% |
25% March - 2020 |
Main building - column completed.
Roof slab steel fabrication in progress. |
No Image |
Karak | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 5.25 | 2 | 2 | 2 | 2 | 7.25 | 21.183 | 25% |
25% February - 2020 |
Main building - column completed.
Roof slab steel fabrication in progress. |
No Image |
Karak | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.433 | 5.25 | 2 | 2 | 2 | 2 | 7.25 | 21.183 | 25% |
25% January - 2020 |
Main building - column completed.
Roof slab steel fabrication in progress. |
No Image |
Karak | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- December - 2019 |
Contract cancelled and tender re-invited on 26/12/2019. |
No Image |
Kohat | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- November - 2019 |
Contract cancelled and tender re-invited on 26/12/2019. |
No Image |
Kohat | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- October - 2019 |
Contract cancelled and will be re-tender after decision of site. Site changing involved. |
No Image |
Kohat | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- September - 2019 |
Contract cancelled and will be re-tender after decision of site. Site changing involved. |
No Image |
Kohat | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- August - 2019 |
Contract cancelled and will be re-tender after decision of site. Site changing involved. |
No Image |
Kohat | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- May - 2020 |
Financial bids approval under process. |
No Image |
Kohat | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- April - 2020 |
Contract cancelled and tender re-invited on 26/12/2019. |
No Image |
Kohat | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- March - 2020 |
Contract cancelled and tender re-invited on 26/12/2019. |
No Image |
Kohat | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- February - 2020 |
Contract cancelled and tender re-invited on 26/12/2019. |
No Image |
Kohat | |||||||||||||||||||
592 (OG) |
160589-Construction of Bachelor Hostel for Judicial Officers in 08 districts of Khyber Pakhtunkhwa |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.828 | 0 | 0 | 0 | 0 | 0 | 0 | 27.828 | - |
- January - 2020 |
Contract cancelled and tender re-invited on 26/12/2019. |
No Image |
Kohat | |||||||||||||||||||
Pages : 1 2 |