Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 20 | - |
- December - 2019 |
Revenue |
No Image |
Purchase of furniture and equipment for Judicial Complex Bannu | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 20 | - |
- November - 2019 |
Revenue |
No Image |
Purchase of furniture and equipment for Judicial Complex Bannu | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 20 | - |
- October - 2019 |
Revenue |
No Image |
Purchase of furniture and equipment for Judicial Complex Bannu | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 20 | - |
- September - 2019 |
Approved. |
No Image |
Purchase of furniture and equipment for Judicial Complex Bannu | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 20 | - |
- August - 2019 |
Approved. |
No Image |
Purchase of furniture and equipment for Judicial Complex Bannu | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 20 | - |
- May - 2020 |
Revenue |
No Image |
Purchase of furniture and equipment for Judicial Complex Bannu | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 20 | - |
- April - 2020 |
Revenue |
No Image |
Purchase of furniture and equipment for Judicial Complex Bannu | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 20 | - |
- March - 2020 |
Revenue |
No Image |
Purchase of furniture and equipment for Judicial Complex Bannu | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 20 | - |
- February - 2020 |
Revenue |
No Image |
Purchase of furniture and equipment for Judicial Complex Bannu | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 20 | - |
- January - 2020 |
Revenue |
No Image |
Purchase of furniture and equipment for Judicial Complex Bannu | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 1 | 3 | 3 | 3 | 0.537 | 1.537 | 0 | 100% |
38% December - 2019 |
Bar room - roof level. Litigant shed - DPC level. |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 1 | 3 | 3 | 3 | 0 | 1 | 0 | 100% |
25% November - 2019 |
Bar room - roof level. Litigant shed - DPC level. |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 1 | 3 | 3 | 3 | 0 | 1 | 0 | 100% |
25% October - 2019 |
Bar room - roof level. Litigant shed - DPC level. |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 1 | 0 | 0 | 0 | 0 | 1 | 3 | - |
25% September - 2019 |
Bar room - roof level. Litigant shed - DPC level. |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 1 | 0 | 0 | 0 | 0 | 1 | 3 | - |
25% August - 2019 |
Bar room - roof level. Litigant shed - DPC level. |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 1 | 3 | 3 | 3 | 2.416 | 3.416 | 0 | 100% |
85% May - 2020 |
Bar room - roof level. Litigant shed - DPC level. |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 1 | 3 | 3 | 3 | 1.894 | 2.894 | 0 | 100% |
72% April - 2020 |
Bar room - roof level. Litigant shed - DPC level. |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 1 | 3 | 3 | 3 | 1.894 | 2.894 | 0 | 100% |
72% March - 2020 |
Bar room - roof level. Litigant shed - DPC level. |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 1 | 3 | 3 | 3 | 1.894 | 2.894 | 0 | 100% |
72% February - 2020 |
Bar room - roof level. Litigant shed - DPC level. |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 4 | 1 | 3 | 3 | 3 | 1.894 | 2.894 | 0 | 100% |
72% January - 2020 |
Bar room - roof level. Litigant shed - DPC level. |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.903 | 23.431 | 4.25 | 4.25 | 4.25 | 4.25 | 27.681 | 1.222 | 96% |
96% December - 2019 |
Completed. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda. | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.903 | 23.431 | 4.25 | 4.25 | 4.25 | 4.25 | 27.681 | 1.222 | 96% |
96% November - 2019 |
Completed. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda. | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.903 | 23.431 | 4.25 | 4.25 | 4.25 | 1.25 | 24.681 | 1.222 | 96% |
85% October - 2019 |
Completed. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.903 | 23.431 | 1.25 | 1.25 | 1.25 | 1.25 | 24.681 | 4.222 | 85% |
85% September - 2019 |
Completed. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.903 | 23.431 | 0 | 0 | 0 | 0 | 23.431 | 5.472 | - |
81% August - 2019 |
Completed. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.903 | 23.431 | 4.25 | 4.25 | 4.25 | 4.25 | 27.681 | 1.222 | 96% |
96% May - 2020 |
Completed & H/O. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda. | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.903 | 23.431 | 4.25 | 4.25 | 4.25 | 4.25 | 27.681 | 1.222 | 96% |
96% April - 2020 |
Completed & H/O. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda. | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.903 | 23.431 | 4.25 | 4.25 | 4.25 | 4.25 | 27.681 | 1.222 | 96% |
96% March - 2020 |
Completed & H/O. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda. | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.903 | 23.431 | 4.25 | 4.25 | 4.25 | 4.25 | 27.681 | 1.222 | 96% |
96% February - 2020 |
Completed & H/O. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda. | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28.903 | 23.431 | 4.25 | 4.25 | 4.25 | 4.25 | 27.681 | 1.222 | 96% |
96% January - 2020 |
Completed. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda. | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.068 | 0 | 0 | 0 | 0 | 0 | 0 | 21.068 | - |
- December - 2019 |
Work order issued |
No Image |
Construction of Single Storey residential apartment at Tehsil Complex Paharpur | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.068 | 0 | 0 | 0 | 0 | 0 | 0 | 21.068 | - |
- November - 2019 |
Work order issued |
No Image |
Construction of Single Storey residential apartment at Tehsil Complex Paharpur | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.068 | 0 | 0 | 0 | 0 | 0 | 0 | 21.068 | - |
- October - 2019 |
Work order issued |
No Image |
Construction of Single Storey residential apartment at Tehsil Complex Paharpur | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.068 | 0 | 0 | 0 | 0 | 0 | 0 | 21.068 | - |
- September - 2019 |
Work order issued |
No Image |
Construction of Single Storey residential apartment at Tehsil Complex Paharpur | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.068 | 0 | 0 | 0 | 0 | 0 | 0 | 21.068 | - |
- August - 2019 |
Work order issued |
No Image |
Construction of Single Storey residential apartment at Tehsil Complex Paharpur | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.068 | 0 | 0 | 0 | 0 | 0 | 0 | 21.068 | - |
- May - 2020 |
Work order issued on 06/04/2018. |
No Image |
Construction of Single Storey residential apartment at Tehsil Complex Paharpur | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.068 | 0 | 0 | 0 | 0 | 0 | 0 | 21.068 | - |
- April - 2020 |
Work order issued on 06/04/2018. |
No Image |
Construction of Single Storey residential apartment at Tehsil Complex Paharpur | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.068 | 0 | 0 | 0 | 0 | 0 | 0 | 21.068 | - |
- March - 2020 |
Work order issued on 06/04/2018. |
No Image |
Construction of Single Storey residential apartment at Tehsil Complex Paharpur | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.068 | 0 | 0 | 0 | 0 | 0 | 0 | 21.068 | - |
- February - 2020 |
Work order issued on 06/04/2018. |
No Image |
Construction of Single Storey residential apartment at Tehsil Complex Paharpur | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 21.068 | 0 | 0 | 0 | 0 | 0 | 0 | 21.068 | - |
- January - 2020 |
Work order issued on 06/04/2018. |
No Image |
Construction of Single Storey residential apartment at Tehsil Complex Paharpur | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.219 | 4.373 | 0 | 0 | 0 | 0 | 4.373 | 5.846 | - |
43% December - 2019 |
Finishing in progress. |
No Image |
Construction of Court Rooms in Judiciary Complex at Dir Lower | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.219 | 4.373 | 0 | 0 | 0 | 0 | 4.373 | 5.846 | - |
43% November - 2019 |
Finishing in progress. Liability Rs. 3 M |
No Image |
Construction of Court Rooms in Judiciary Complex at Dir Lower | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.219 | 4.373 | 0 | 0 | 0 | 0 | 4.373 | 5.846 | - |
43% October - 2019 |
Finishing in progress. Liability Rs. 3 M |
No Image |
Construction of Court Rooms in Judiciary Complex at Dir Lower | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.219 | 4.373 | 0 | 0 | 0 | 0 | 4.373 | 5.846 | - |
43% September - 2019 |
Finishing in progress. Liability Rs. 3 M |
No Image |
Construction of Court Rooms in Judiciary Complex at Dir Lower | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.219 | 4.373 | 0 | 0 | 0 | 0 | 4.373 | 5.846 | - |
43% August - 2019 |
Finishing in progress. Liability Rs. 3 M |
No Image |
Construction of Court Rooms in Judiciary Complex at Dir Lower | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.219 | 4.373 | 0 | 0 | 0 | 0 | 4.373 | 5.846 | - |
43% May - 2020 |
Finishing in progress. |
No Image |
Construction of Court Rooms in Judiciary Complex at Dir Lower | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.219 | 4.373 | 0 | 0 | 0 | 0 | 4.373 | 5.846 | - |
43% April - 2020 |
Finishing in progress. |
No Image |
Construction of Court Rooms in Judiciary Complex at Dir Lower | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.219 | 4.373 | 0 | 0 | 0 | 0 | 4.373 | 5.846 | - |
43% March - 2020 |
Finishing in progress. |
No Image |
Construction of Court Rooms in Judiciary Complex at Dir Lower | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.219 | 4.373 | 0 | 0 | 0 | 0 | 4.373 | 5.846 | - |
43% February - 2020 |
Finishing in progress. |
No Image |
Construction of Court Rooms in Judiciary Complex at Dir Lower | |||||||||||||||||||
593 (OG) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 10.219 | 4.373 | 0 | 0 | 0 | 0 | 4.373 | 5.846 | - |
43% January - 2020 |
Finishing in progress. |
No Image |
Construction of Court Rooms in Judiciary Complex at Dir Lower | |||||||||||||||||||