Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2020, February - 2019, February - 2020, March - 2019, March - 2020, April - 2019, April - 2020, May - 2020, July - 2018, August - 2019, September - 2018, September - 2019, October - 2019, November - 2018, November - 2019, December - 2018, December - 2019,

Showing Page Number : 1 of 2

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Battagram
30-11--1 30-11--1 - 30-11--1 - 3.56 0 2.5 2.5 2.5 2.5 2.5 1.06 70% 70%
December - 2019
50% work completed.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Battagram
30-11--1 30-11--1 - 30-11--1 - 3.56 0 2.5 2.5 2.5 0.836 0.836 1.06 70% 23%
November - 2019
50% work completed.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Battagram
30-11--1 30-11--1 - 30-11--1 - 3.56 0 2.5 2.5 2.5 0 0 1.06 70% -
October - 2019
Work strated.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Battagram
30-11--1 30-11--1 - 30-11--1 - 3.56 0 0 0 0 0 0 3.56 - -
September - 2019
Tender under process.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Battagram
30-11--1 30-11--1 - 30-11--1 - 3.56 0 0 0 0 0 0 3.56 - -
August - 2019
Tender under process.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Battagram
30-11--1 30-11--1 - 30-11--1 - 3.56 0 2.5 2.5 2.5 2.5 2.5 1.06 70% 70%
May - 2020
50% work completed.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Battagram
30-11--1 30-11--1 - 30-11--1 - 3.56 0 2.5 2.5 2.5 2.5 2.5 1.06 70% 70%
April - 2020
50% work completed.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Battagram
30-11--1 30-11--1 - 30-11--1 - 3.56 0 2.5 2.5 2.5 2.5 2.5 1.06 70% 70%
March - 2020
50% work completed.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Battagram
30-11--1 30-11--1 - 30-11--1 - 3.56 0 2.5 2.5 2.5 2.5 2.5 1.06 70% 70%
February - 2020
50% work completed.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Battagram
30-11--1 30-11--1 - 30-11--1 - 3.56 0 2.5 2.5 2.5 2.5 2.5 1.06 70% 70%
January - 2020
50% work completed.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Buner
30-11--1 30-11--1 - 30-11--1 - 5.574 0 2 2 2 0.994 0.994 3.574 36% 18%
December - 2019
Revised scope of work awaited.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Buner
30-11--1 30-11--1 - 30-11--1 - 5.574 0 0 0 0 0 0 5.574 - -
November - 2019
Revised scope of work awaited.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Buner
30-11--1 30-11--1 - 30-11--1 - 5.574 0 0 0 0 0 0 5.574 - -
October - 2019
Revised scope of work awaited.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Buner
30-11--1 30-11--1 - 30-11--1 - 5.574 0 2 2 2 0.994 0.994 3.574 36% 18%
May - 2020
Revised scope of work awaited.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Buner
30-11--1 30-11--1 - 30-11--1 - 5.574 0 2 2 2 0.994 0.994 3.574 36% 18%
April - 2020
Revised scope of work awaited.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Buner
30-11--1 30-11--1 - 30-11--1 - 5.574 0 2 2 2 0.994 0.994 3.574 36% 18%
March - 2020
Revised scope of work awaited.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Buner
30-11--1 30-11--1 - 30-11--1 - 5.574 0 2 2 2 0.994 0.994 3.574 36% 18%
February - 2020
Revised scope of work awaited.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Buner
30-11--1 30-11--1 - 30-11--1 - 5.574 0 2 2 2 0.994 0.994 3.574 36% 18%
January - 2020
Revised scope of work awaited.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2 0 1 1 1 1 1 1 50% 50%
December - 2019
Completed.
No Image
Construction of Motorcycle Shed.
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2 0 1 1 1 1 1 1 50% 50%
November - 2019
Completed.
No Image
Construction of Motorcycle Shed.
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2 0 1 1 1 1 1 1 50% 50%
October - 2019
Completed.
No Image
Construction of Motorcycle Shed.
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2 0 0 0 0 0 0 2 - -
September - 2019
Work order issued.
No Image
Construction of Motorcycle Shed.
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2 0 0 0 0 0 0 2 - -
August - 2019
Work order issued.
No Image
Construction of Motorcycle Shed.
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2 0 4.39 4.39 4.39 4.39 4.39 0 100% 100%
May - 2020
Completed.
No Image
Construction of Motorcycle Shed.
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2 0 4.39 4.39 4.39 4.39 4.39 0 100% 100%
April - 2020
Completed.
No Image
Construction of Motorcycle Shed.
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2 0 4.39 4.39 4.39 4.39 4.39 0 100% 100%
March - 2020
Completed.
No Image
Construction of Motorcycle Shed.
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2 0 4.39 4.39 4.39 4.39 4.39 0 100% 100%
February - 2020
Completed.
No Image
Construction of Motorcycle Shed.
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 2 0 1 1 1 1 1 1 50% 50%
January - 2020
Completed.
No Image
Construction of Motorcycle Shed.
595
(OG)
160479-Construction of Newspaper Market for Hawkers in all Districts.
Kohat
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
December - 2018
PC-I/DCE for Rs.6.053 m submitted to PO Information & PR on 15/03/2017.
No Image
Kohat
595
(OG)
160479-Construction of Newspaper Market for Hawkers in all Districts.
Kohat
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
November - 2018
PC-I/DCE for Rs.6.053 m submitted to PO Information & PR on 15/03/2017. Not yet approved.
No Image
Kohat
595
(OG)
160479-Construction of Newspaper Market for Hawkers in all Districts.
Kohat
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
November - 2018
PC-I/DCE for Rs.6.053 m submitted to PO Information & PR on 15/03/2017. Not yet approved.
No Image
Kohat
595
(OG)
160479-Construction of Newspaper Market for Hawkers in all Districts.
Kohat
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
April - 2019
PC-I/DCE for Rs.6.053 m submitted to PO Information & PR on 15/03/2017.
No Image
Kohat
595
(OG)
160479-Construction of Newspaper Market for Hawkers in all Districts.
Kohat
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
March - 2019
PC-I/DCE for Rs.6.053 m submitted to PO Information & PR on 15/03/2017.
No Image
Kohat
595
(OG)
160479-Construction of Newspaper Market for Hawkers in all Districts.
Kohat
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
March - 2019
PC-I/DCE for Rs.6.053 m submitted to PO Information & PR on 15/03/2017.
No Image
Kohat
595
(OG)
160479-Construction of Newspaper Market for Hawkers in all Districts.
Kohat
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
February - 2019
PC-I/DCE for Rs.6.053 m submitted to PO Information & PR on 15/03/2017.
No Image
Kohat
595
(OG)
160479-Construction of Newspaper Market for Hawkers in all Districts.
Kohat
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
January - 2019
PC-I/DCE for Rs.6.053 m submitted to PO Information & PR on 15/03/2017.
No Image
Kohat
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Kohistan
30-11--1 30-11--1 - 30-11--1 - 1.5 0 1.5 1.5 1.5 0.758 0.758 0 100% 51%
December - 2019
Boundary wall work in progress.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Kohistan
30-11--1 30-11--1 - 30-11--1 - 1.5 0 1.5 1.5 1.5 0 0 0 100% -
May - 2020
Boundary wall work in progress.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Kohistan
30-11--1 30-11--1 - 30-11--1 - 1.5 0 1.5 1.5 1.5 0 0 0 100% -
April - 2020
Boundary wall work in progress.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Kohistan
30-11--1 30-11--1 - 30-11--1 - 1.5 0 1.5 1.5 1.5 0 0 0 100% -
March - 2020
Boundary wall work in progress.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Kohistan
30-11--1 30-11--1 - 30-11--1 - 1.5 0 1.5 1.5 1.5 0 0 0 100% -
February - 2020
Boundary wall work in progress.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Kohistan
30-11--1 30-11--1 - 30-11--1 - 1.5 0 1.5 1.5 1.5 0.758 0.758 0 100% 51%
January - 2020
Boundary wall work in progress.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Malakand
30-11--1 30-11--1 - 30-11--1 - 14.222 0 0 0 0 0 0 14.222 - -
December - 2019
Work Order being issued.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Malakand
30-11--1 30-11--1 - 30-11--1 - 14.222 0 0 0 0 0 0 14.222 - -
November - 2019
Work Order being issued.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Malakand
30-11--1 30-11--1 - 30-11--1 - 14.222 0 0 0 0 0 0 14.222 - -
May - 2020
Work Order being issued.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Malakand
30-11--1 30-11--1 - 30-11--1 - 14.222 0 0 0 0 0 0 14.222 - -
April - 2020
Work Order being issued.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Malakand
30-11--1 30-11--1 - 30-11--1 - 14.222 0 0 0 0 0 0 14.222 - -
March - 2020
Work Order being issued.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Malakand
30-11--1 30-11--1 - 30-11--1 - 14.222 0 0 0 0 0 0 14.222 - -
February - 2020
Work Order being issued.
No Image
595
(OG)
180076-Additional facilities and improvement of infrastructure of existing judicial complexes
Malakand
30-11--1 30-11--1 - 30-11--1 - 14.222 0 0 0 0 0 0 14.222 - -
January - 2020
Work Order being issued.
No Image
595
(OG)
150137-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 137.445 0 2 2 0 0 0 0 - -
September - 2018
Site/scope of work not identified.
No Image
Mansehra
Pages : 1 2