Progressive Review for the month(s) of : January - 2019, February - 2019, March - 2019, April - 2019, July - 2018, September - 2018, November - 2018, December - 2018,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
609
(OG)
140987-F/S, Design and Construction of Main Daraban Road from Saggu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi District DI.Khan (i) Improvement and Black Top Road from Kirri Shamozai to Jhoke Rind PK-67 (1 Km) (ii) Construction of Bridge on Lora Nullah Daraban City PK-67.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 210.223 116.573 0.001 0.001 0.0005 0 116.573 93.649 55% 55%
September - 2018
Length 16 Km (width-12ft) - earth work completed. Sub-base 8 Km completed. Lora Bridge (length 120 ft, 4 span) - tender aproval in progress. Additional road (1 Km) - work order issued.
No Image
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works)
609
(OG)
140987-F/S, Design and Construction of Main Daraban Road from Saggu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi District DI.Khan (i) Improvement and Black Top Road from Kirri Shamozai to Jhoke Rind PK-67 (1 Km) (ii) Construction of Bridge on Lora Nullah Daraban City PK-67.
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 210.223 116.573 0.001 0.001 0.0005 0 116.573 93.649 55% 55%
July - 2018
Length 16 Km (width-12ft) - earth work completed. Sub-base 8 Km completed. Lora Bridge (length 120 ft, 4 span) - tender aproval in progress. Additional road (1 Km) - work order issued.
No Image
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works)
609
(OG)
120419-F/S for Master Panning and Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 290 10 0.001 0.001 0 0 10 279.999 3% 3%
December - 2018
Procurement stopped till possession of site. Scheme freezed by PHC.
No Image
Peshawar
609
(OG)
120419-F/S for Master Panning and Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 290 10 0.001 0.001 0 0 10 279.999 3% 3%
November - 2018
Procurement stopped till possession of site. Scheme freezed by PHC.
No Image
Peshawar
609
(OG)
120419-F/S for Master Panning and Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 290 10 0.001 0.001 0 0 10 279.999 3% 3%
November - 2018
Procurement stopped till possession of site. Scheme freezed by PHC.
No Image
Peshawar
609
(OG)
120419-F/S for Master Panning and Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 290 10 0.001 0.001 0 0 10 279.999 3% 3%
April - 2019
Procurement stopped till possession of site. Scheme freezed by PHC.
No Image
Peshawar
609
(OG)
120419-F/S for Master Panning and Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 290 10 0.001 0.001 0 0 10 279.999 3% 3%
March - 2019
Procurement stopped till possession of site. Scheme freezed by PHC.
No Image
Peshawar
609
(OG)
120419-F/S for Master Panning and Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 290 10 0.001 0.001 0 0 10 279.999 3% 3%
March - 2019
Procurement stopped till possession of site. Scheme freezed by PHC.
No Image
Peshawar
609
(OG)
120419-F/S for Master Panning and Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 290 10 0.001 0.001 0 0 10 279.999 3% 3%
February - 2019
Procurement stopped till possession of site. Scheme freezed by PHC.
No Image
Peshawar
609
(OG)
120419-F/S for Master Panning and Designing of Khyber Pakhtunkhwa Judicial Academy at Regi Model Town Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 290 10 0.001 0.001 0 0 10 279.999 3% 3%
January - 2019
Procurement stopped till possession of site. Scheme freezed by PHC.
No Image
Peshawar