Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, January - 2019, February - 2020, February - 2021, February - 2018, February - 2019, March - 2020, March - 2021, March - 2018, March - 2019, April - 2019, April - 2020, April - 2021, April - 2018, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, July - 2018, August - 2019, August - 2020, August - 2017, September - 2019, September - 2020, September - 2017, September - 2018, October - 2019, October - 2020, October - 2017, November - 2019, November - 2017, November - 2018, December - 2018, December - 2019, December - 2020, December - 2017,

Showing Page Number : 1 of 4

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
08-05-16 - - 04-12-13 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
December - 2017
Completed.
No Image
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
08-05-16 - - 04-12-13 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
September - 2017
Completed.
No Image
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
08-05-16 - - 04-12-13 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
August - 2017
Completed.
No Image
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
08-05-16 - - 04-12-13 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
July - 2017
Completed.
No Image
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
December - 2018
Completed.
No Image
Service Delivery Center in the premises of DC office Abbottabad
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
November - 2017
Completed.
No Image
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
November - 2018
Completed.
No Image
Service Delivery Center in the premises of DC office Abbottabad
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
November - 2018
Completed.
No Image
Service Delivery Center in the premises of DC office Abbottabad
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
October - 2017
Completed.
No Image
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
June - 2018
Completed.
No Image
Service Delivery Center in the premises of DC office Abbottabad
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
May - 2018
Completed.
No Image
Service Delivery Center in the premises of DC office Abbottabad
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
April - 2018
Completed.
No Image
Service Delivery Center in the premises of DC office Abbottabad
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
April - 2019
Completed.
No Image
Service Delivery Center in the premises of DC office Abbottabad
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
March - 2018
Completed.
No Image
Service Delivery Center in the premises of DC office Abbottabad
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
March - 2019
Completed.
No Image
Service Delivery Center in the premises of DC office Abbottabad
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
March - 2019
Completed.
No Image
Service Delivery Center in the premises of DC office Abbottabad
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
February - 2018
Completed.
No Image
Service Delivery Center in the premises of DC office Abbottabad
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
February - 2019
Completed.
No Image
Service Delivery Center in the premises of DC office Abbottabad
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
January - 2018
Completed.
No Image
Service Delivery Center in the premises of DC office Abbottabad
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 6.705 6.117 0 0 0 0 6.117 0.588 - 91%
January - 2019
Completed.
No Image
Service Delivery Center in the premises of DC office Abbottabad
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
20-09-17 - - 04-12-13 - 13.523 0 5 5 5 5 5 8.523 37% 37%
December - 2017
Out of 2 units, all in progress.
No Image
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
- - - 04-12-13 - 13.523 0 5 5 5 0.595 0.595 8.523 37% 4%
September - 2017
Work started.
No Image
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
- - - 04-12-13 - 13.523 0 5 5 5 0 0 8.523 37% -
August - 2017
Work order issued.
No Image
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
- - - 04-12-13 - 13.523 0 0 0 0 0 0 13.523 - -
July - 2017
Tender floated on 25/07/2017.
No Image
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
30-11--1 30-11--1 - 30-11--1 - 13.523 5 1 1 1 1 6 7.523 44% 44%
December - 2018
Out of 2 units, all in progress.
No Image
1) Domel, Bannu (computerization of land record)
2) Kakki, Bannu (computerization of land record)
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
30-11--1 30-11--1 - 30-11--1 - 13.523 0 5 5 5 4.422 4.422 8.523 37% 33%
November - 2017
Out of 2 units, 1 in progress, 1 layout given.
No Image
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
30-11--1 30-11--1 - 30-11--1 - 13.523 5 1 1 1 0 5 7.523 44% 37%
November - 2018
Out of 2 units, all in progress.
No Image
1) Domel, Bannu (computerization of land record)
2) Kakki, Bannu (computerization of land record)
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
30-11--1 30-11--1 - 30-11--1 - 13.523 5 1 1 1 0 5 7.523 44% 37%
November - 2018
Out of 2 units, all in progress.
No Image
1) Domel, Bannu (computerization of land record)
2) Kakki, Bannu (computerization of land record)
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
30-11--1 30-11--1 - 30-11--1 - 13.523 0 5 5 5 2.138 2.138 8.523 37% 16%
October - 2017
Work started.
No Image
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
30-11--1 30-11--1 - 30-11--1 - 13.523 0 5 5 5 5 5 8.523 37% 37%
June - 2018
Out of 2 units, all in progress.
No Image
1) Domel, Bannu (computerization of land record)
2) Kakki, Bannu (computerization of land record)
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
30-11--1 30-11--1 - 30-11--1 - 13.523 0 5 5 5 5 5 8.523 37% 37%
May - 2018
Out of 2 units, all in progress.
No Image
1) Domel, Bannu (computerization of land record)
2) Kakki, Bannu (computerization of land record)
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
30-11--1 30-11--1 - 30-11--1 - 13.523 0 5 5 5 5 5 8.523 37% 37%
April - 2018
Out of 2 units, all in progress.
No Image
1) Domel, Bannu (computerization of land record)
2) Kakki, Bannu (computerization of land record)
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
30-11--1 30-11--1 - 30-11--1 - 13.523 5 3 3 3 2.521 7.521 5.523 59% 56%
April - 2019
Out of 2 units, all in progress.
No Image
1) Domel, Bannu (computerization of land record)
2) Kakki, Bannu (computerization of land record)
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
30-11--1 30-11--1 - 30-11--1 - 13.523 0 5 5 5 5 5 8.523 37% 37%
March - 2018
Out of 2 units, all in progress.
No Image
1) Domel, Bannu (computerization of land record)
2) Kakki, Bannu (computerization of land record)
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
30-11--1 30-11--1 - 30-11--1 - 13.523 5 3 3 3 2.521 7.521 5.523 59% 56%
March - 2019
Out of 2 units, all in progress.
No Image
1) Domel, Bannu (computerization of land record)
2) Kakki, Bannu (computerization of land record)
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
30-11--1 30-11--1 - 30-11--1 - 13.523 5 3 3 3 2.521 7.521 5.523 59% 56%
March - 2019
Out of 2 units, all in progress.
No Image
1) Domel, Bannu (computerization of land record)
2) Kakki, Bannu (computerization of land record)
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
30-11--1 30-11--1 - 30-11--1 - 13.523 0 5 5 5 5 5 8.523 37% 37%
February - 2018
Out of 2 units, all in progress.
No Image
1) Domel, Bannu (computerization of land record)
2) Kakki, Bannu (computerization of land record)
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
30-11--1 30-11--1 - 30-11--1 - 13.523 5 2 2 2 1.691 6.691 6.523 52% 49%
February - 2019
Out of 2 units, all in progress.
No Image
1) Domel, Bannu (computerization of land record)
2) Kakki, Bannu (computerization of land record)
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
30-11--1 30-11--1 - 30-11--1 - 13.523 0 5 5 5 5 5 8.523 37% 37%
January - 2018
Out of 2 units, all in progress.
No Image
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Bannu
30-11--1 30-11--1 - 30-11--1 - 13.523 5 2 2 2 1 6 6.523 52% 44%
January - 2019
Out of 2 units, all in progress.
No Image
1) Domel, Bannu (computerization of land record)
2) Kakki, Bannu (computerization of land record)
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Buner
27-10-16 - - 04-12-13 - 7.431 4.431 1 1 1 0.112 4.543 2 73% 61%
December - 2017
Civil work in progress. Tender called on 20/04/2017 (for CCTV cameras, solar UPS, networking).
No Image
Tehsil Daggar Buner
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Buner
27-10-16 - - 04-12-13 - 7.431 4.431 1 1 1 0.112 4.543 2 73% 61%
September - 2017
Civil work in progress. Tender called on 20/04/2017 (for CCTV cameras, solar UPS, networking).
No Image
Tehsil Daggar Buner
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Buner
27-10-16 - - 04-12-13 - 7.431 4.431 1 1 1 0 4.431 2 73% 60%
August - 2017
Civil work in progress. Tender called on 20/04/2017 (for CCTV cameras, solar UPS, networking).
No Image
Tehsil Daggar Buner
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Buner
- - - 04-12-13 - 7.431 4.431 1 1 1 0 4.431 2 73% 60%
July - 2017
Civil work in progress. Tender called on 20/04/2017 (for CCTV cameras, solar UPS, networking).
No Image
Tehsil Daggar Buner
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Buner
30-11--1 30-11--1 - 30-11--1 - 7.431 4.543 0.316 0.316 0.316 0 4.543 2.572 65% 61%
December - 2018
Civil work in progress. Tender called on 20/04/2017 (for CCTV cameras, solar UPS, networking).
No Image
PK-79 Tehsil Daggar Buner
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Buner
30-11--1 30-11--1 - 30-11--1 - 7.431 4.431 1 1 1 0.112 4.543 2 73% 61%
November - 2017
Civil work in progress. Tender called on 20/04/2017 (for CCTV cameras, solar UPS, networking).
No Image
Tehsil Daggar Buner
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Buner
30-11--1 30-11--1 - 30-11--1 - 7.431 4.543 0.316 0.316 0.316 0 4.543 2.572 65% 61%
November - 2018
Civil work in progress. Tender called on 20/04/2017 (for CCTV cameras, solar UPS, networking).
No Image
PK-79 Tehsil Daggar Buner
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Buner
30-11--1 30-11--1 - 30-11--1 - 7.431 4.543 0.316 0.316 0.316 0 4.543 2.572 65% 61%
November - 2018
Civil work in progress. Tender called on 20/04/2017 (for CCTV cameras, solar UPS, networking).
No Image
PK-79 Tehsil Daggar Buner
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Buner
30-11--1 30-11--1 - 30-11--1 - 7.431 4.431 1 1 1 0.112 4.543 2 73% 61%
October - 2017
Civil work in progress. Tender called on 20/04/2017 (for CCTV cameras, solar UPS, networking).
No Image
Tehsil Daggar Buner
61
(OG)
100311-Computerization of Land Record in 18 Districts of Khyber Pakhtunkhwa (Phase-I 7 Districts).
Buner
30-11--1 30-11--1 - 30-11--1 - 7.431 4.431 0.112 0.112 0.112 0.112 4.543 2.888 61% 61%
June - 2018
Civil work in progress. Tender called on 20/04/2017 (for CCTV cameras, solar UPS, networking).
No Image
PK-79 Tehsil Daggar Buner