Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
62 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 176.844 | 177.894 | 0 | 0 | 0 | 0 | 177.894 | 0 | - |
100% September - 2018 |
Main building, basement, residential building in finishing stage. Developmental work in progress. 2nd Revised PC-I/DCE for Rs.624.685 m submitted to SOB on 16/05/2018. |
No Image |
Domel, District Bannu | |||||||||||||||||||
62 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 176.844 | 177.894 | 0 | 0 | 0 | 0 | 177.894 | 0 | - |
100% July - 2018 |
Main building, basement, residential building in finishing stage. Developmental work in progress. 2nd Revised PC-I/DCE for Rs.624.685 m submitted to SOB on 16/05/2018. |
No Image |
Domel, District Bannu | |||||||||||||||||||
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
Site identification/Scope of work awaited. |
No Image |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
Site identification/Scope of work awaited. |
No Image |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
Site identification/Scope of work awaited. |
No Image |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
Site identification/Scope of work awaited. |
No Image |
62 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.858 | 206.421 | 0 | 0 | 0 | 0 | 206.421 | 0.437 | - |
100% September - 2018 |
Completed & H/O. |
No Image |
Katlang, Mardan | |||||||||||||||||||
62 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.858 | 206.421 | 0 | 0 | 0 | 0 | 206.421 | 0.437 | - |
100% July - 2018 |
Completed & H/O. |
No Image |
Katlang, Mardan | |||||||||||||||||||
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
DCE sent for Rs. 5.141 (M) to SO Dev: Auquaf Hajj & Minority Affairs. |
No Image |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
DCE sent for Rs. 5.141 (M) to SO Dev: Auquaf Hajj & Minority Affairs. |
No Image |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
DCE sent for Rs. 5.141 (M) to SO Dev: Auquaf Hajj & Minority Affairs. |
No Image |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
DCE sent for Rs. 5.141 (M) to SO Dev: Auquaf Hajj & Minority Affairs. |
No Image |
62 (OG) |
191037-180512 - Training center in Tribal District Mohmand. (Phase II, Fish Hatchery Component). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.137 | 2.9 | 5 | 5 | 2 | 2 | 4.9 | 46.237 | 15% |
9% December - 2020 |
1- 03-Nos ponds completed.
Exevation of 03-Nos completed.
Layout out given. =1
Completed =1
Remaining work in progress. |
No Image |
62 (OG) |
191037-180512 - Training center in Tribal District Mohmand. (Phase II, Fish Hatchery Component). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.137 | 2.9 | 5 | 5 | 2 | 2 | 4.9 | 46.237 | 15% |
9% December - 2020 |
1- 03-Nos ponds completed.
Exevation of 03-Nos completed.
Layout out given. =1
Completed =1
Remaining work in progress. |
No Image |
62 (OG) |
191037-180512 - Training center in Tribal District Mohmand. (Phase II, Fish Hatchery Component). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.137 | 2.9 | 5 | 5 | 2 | 2 | 4.9 | 46.237 | 15% |
9% October - 2020 |
1- 03-Nos ponds completed.
Exevation of 03-Nos completed.
Layout out given. =1
Completed =1
Remaining work in progress. |
No Image |
62 (OG) |
191037-180512 - Training center in Tribal District Mohmand. (Phase II, Fish Hatchery Component). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.137 | 2.9 | 5 | 5 | 2 | 0 | 2.9 | 46.237 | 15% |
5% September - 2020 |
1- 03-Nos ponds completed.
Exevation of 03-Nos completed.
Layout out given. =1
Completed =1
Remaining work in progress. |
No Image |
62 (OG) |
191037-180512 - Training center in Tribal District Mohmand. (Phase II, Fish Hatchery Component). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.137 | 2.9 | 5 | 5 | 2 | 0 | 2.9 | 46.237 | 15% |
5% August - 2020 |
Tube well completed. Remaining work in progress. |
No Image |
62 (OG) |
191037-180512 - Training center in Tribal District Mohmand. (Phase II, Fish Hatchery Component). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.137 | 3 | 5 | 5 | 5 | 2 | 5 | 46.137 | 15% |
9% May - 2021 |
01- Unit
1- 03-Nos ponds completed.
Exevation of 03-Nos completed.
Layout out given. =1
Completed =1
Remaining work in progress. |
No Image |
Mohmand
Scope of work:
| |||||||||||||||||||
62 (OG) |
191037-180512 - Training center in Tribal District Mohmand. (Phase II, Fish Hatchery Component). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.137 | 3 | 5 | 5 | 5 | 2 | 5 | 46.137 | 15% |
9% April - 2021 |
1- 03-Nos ponds completed.
Exevation of 03-Nos completed.
Layout out given. =1
Completed =1
Remaining work in progress. |
No Image |
Mohmand | |||||||||||||||||||
62 (OG) |
191037-180512 - Training center in Tribal District Mohmand. (Phase II, Fish Hatchery Component). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.137 | 3 | 5 | 3.826 | 3.826 | 2 | 5 | 46.137 | 15% |
9% March - 2021 |
1- 03-Nos ponds completed.
Exevation of 03-Nos completed.
Layout out given. =1
Completed =1
Remaining work in progress. |
No Image |
Mohmand | |||||||||||||||||||
62 (OG) |
191037-180512 - Training center in Tribal District Mohmand. (Phase II, Fish Hatchery Component). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.137 | 3 | 5 | 3.826 | 3.826 | 2 | 5 | 46.137 | 15% |
9% February - 2021 |
1- 03-Nos ponds completed.
Exevation of 03-Nos completed.
Layout out given. =1
Completed =1
Remaining work in progress. |
No Image |
Mohmand | |||||||||||||||||||
62 (OG) |
191037-180512 - Training center in Tribal District Mohmand. (Phase II, Fish Hatchery Component). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 54.137 | 2.9 | 5 | 5 | 2 | 2 | 4.9 | 46.237 | 15% |
9% January - 2021 |
1- 03-Nos ponds completed.
Exevation of 03-Nos completed.
Layout out given. =1
Completed =1
Remaining work in progress. |
No Image |
Mohmand | |||||||||||||||||||
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 15 | 15 | 0 | 0 | 0 | 0 | - |
- December - 2019 |
No Image | |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 15 | 15 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
No Image | |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 15 | 15 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
No Image | |
62 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 624.685 | 542.431 | 0.001 | 0.001 | 0 | 0 | 542.431 | 0 | - |
- September - 2018 |
Mardan: Completed & H/O.
Swabi: Main building FF, judicial lockup, cafetaria in progress. Occupied by FWO. Work has been stopped.
Bannu: Main building, basement, residential building in finishing stage. Developmental work in progress. |
No Image |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 15 | 15 | 0 | 0 | 0 | 0 | - |
- September - 2019 |
No Image | |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 100 | 0 | 15 | 15 | 0 | 0 | 0 | 0 | - |
- August - 2019 |
No Image | |
62 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 624.685 | 542.431 | 0.001 | 0.001 | 0 | 0 | 542.431 | 0 | - |
- July - 2018 |
Mardan: Completed & H/O.
Swabi: Main building FF, judicial lockup, cafetaria in progress. Occupied by FWO. Work has been stopped.
Bannu: Main building, basement, residential building in finishing stage. Developmental work in progress. |
No Image |
62 (OG) |
191037-180512 - Training center in Tribal District Mohmand. (Phase II, Fish Hatchery Component). [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 85.643 | 2.9 | 5 | 0 | 0 | 0 | 2.9 | 0 |
July - 2020 |
No Image | ||
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2020 |
No Image | |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2020 |
No Image | |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2020 |
No Image | |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2020 |
No Image | |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2020 |
No Image | |
62 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.09 | 166.134 | 0 | 0 | 0 | 0 | 166.134 | 39.956 | - |
81% September - 2018 |
Main building FF, judicial lockup, cafetaria in progress. Occupied by FWO. Work has been stopped. |
No Image |
Tehsil building Rajjar Swabi | |||||||||||||||||||
62 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.09 | 166.134 | 0 | 0 | 0 | 0 | 166.134 | 39.956 | - |
81% July - 2018 |
Main building FF, judicial lockup, cafetaria in progress. Occupied by FWO. Work has been stopped. |
No Image |
Tehsil building Rajjar Swabi | |||||||||||||||||||
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 8 | 0 | 4 | 4 | 2.012 | 2.012 | 2.012 | 4 | 50% |
25% May - 2020 |
Layout given. |
No Image |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 8 | 0 | 0 | 0 | 0.912 | 0 | 0 | 8 | - |
- April - 2020 |
Work order issued. |
No Image |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 8 | 0 | 0 | 0 | 0.912 | 0 | 0 | 8 | - |
- March - 2020 |
Work order issued. |
No Image |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 8 | 0 | 0 | 0 | 0.912 | 0 | 0 | 8 | - |
- February - 2020 |
Work order issued. |
No Image |
62 (New) |
190075-Construction & Reconstruction of Masajids, Darul Ulooms & Deeni Madaris in Khyber Pakhtunkhwa. |
Swat |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 8 | 0 | 0 | 0 | 0 | 0 | 0 | 8 | - |
- January - 2020 |
Tender called on 06/06/2020. |
No Image |