Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2019, January - 2021, February - 2019, February - 2021, March - 2019, March - 2021, April - 2019, April - 2021, May - 2021, July - 2018, July - 2020, August - 2020, September - 2018, September - 2020, October - 2020, November - 2018, December - 2018, December - 2020,

Showing Page Number : 1 of 4

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 27.186 0 0 0 0 0 0 27.186 - -
December - 2018
Work order issued. Land not available.
No Image
1) SDC Havelian
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 27.186 0 0 0 0 0 0 27.186 - -
November - 2018
Work order issued. Land not available.
No Image
1) SDC Havelian
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 27.186 0 0 0 0 0 0 27.186 - -
November - 2018
Work order issued. Land not available.
No Image
1) SDC Havelian
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 27.186 0 0 0 0 0 0 27.186 - -
April - 2019
Work order issued. Land not available.
No Image
1) SDC Havelian
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 27.186 0 0 0 0 0 0 27.186 - -
March - 2019
Work order issued. Land not available.
No Image
1) SDC Havelian
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 27.186 0 0 0 0 0 0 27.186 - -
March - 2019
Work order issued. Land not available.
No Image
1) SDC Havelian
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 27.186 0 0 0 0 0 0 27.186 - -
February - 2019
Work order issued. Land not available.
No Image
1) SDC Havelian
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 27.186 0 0 0 0 0 0 27.186 - -
January - 2019
Work order issued. Land not available.
No Image
1) SDC Havelian
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 36.677 0 0 0 0 0 0 36.677 - -
December - 2018
Site not yet H/O.
No Image
Service Delivery Center, Bannu
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 36.677 0 0 0 0 0 0 36.677 - -
November - 2018
Site not yet H/O.
No Image
Service Delivery Center, Bannu
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 36.677 0 0 0 0 0 0 36.677 - -
November - 2018
Site not yet H/O.
No Image
Service Delivery Center, Bannu
63
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Bannu
30-11--1 30-11--1 - 30-11--1 - 23.1 22.9 0 0 0 0 22.9 0.2 - 99%
September - 2018
Completed & H/O.
No Image
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018
63
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Bannu
30-11--1 30-11--1 - 30-11--1 - 23.1 22.9 0 0 0 0 22.9 0.2 - 99%
July - 2018
Completed & H/O.
No Image
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 36.677 0 0 0 0 0 0 36.677 - -
April - 2019
Tender under process.
No Image
Service Delivery Center, Bannu
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 36.677 0 0 0 0 0 0 36.677 - -
March - 2019
Tender under process.
No Image
Service Delivery Center, Bannu
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 36.677 0 0 0 0 0 0 36.677 - -
March - 2019
Tender under process.
No Image
Service Delivery Center, Bannu
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 36.677 0 0 0 0 0 0 36.677 - -
February - 2019
Site not yet H/O.
No Image
Service Delivery Center, Bannu
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 36.677 0 0 0 0 0 0 36.677 - -
January - 2019
Site not yet H/O.
No Image
Service Delivery Center, Bannu
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
December - 2018
Approved in DDWP. AA awaited.
No Image
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
November - 2018
PC-I/DCE for Rs.42.696 m for Tehsil Battagram and Rs.31.231 m for Tehsil Allai submitted to DC Battagram on 13/11/2017.
No Image
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
November - 2018
PC-I/DCE for Rs.42.696 m for Tehsil Battagram and Rs.31.231 m for Tehsil Allai submitted to DC Battagram on 13/11/2017.
No Image
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
April - 2019
Approved in DDWP. AA awaited.
No Image
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
March - 2019
Approved in DDWP. AA awaited.
No Image
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
March - 2019
Approved in DDWP. AA awaited.
No Image
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
February - 2019
Approved in DDWP. AA awaited.
No Image
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
January - 2019
Approved in DDWP. AA awaited.
No Image
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 71.759 41.601 5.795 5.795 5.795 4.935 46.536 24.363 66% 65%
December - 2018
3 units - Khadukhail - completed. Gagra - plastering in progress. Mandar - plastering in progress.
No Image
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 71.759 41.6 2 2 2 2 43.6 28.159 61% 61%
November - 2018
3 units - Khadukhail - completed. Gagra - plastering in progress. Mandar - plastering in progress.
No Image
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 71.759 41.6 2 2 2 2 43.6 28.159 61% 61%
November - 2018
3 units - Khadukhail - completed. Gagra - plastering in progress. Mandar - plastering in progress.
No Image
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 71.759 41.601 5.795 5.795 5.795 5.795 47.396 24.363 66% 66%
April - 2019
3 units - Khadukhail - completed. Gagra - plastering in progress. Mandar - plastering in progress.
No Image
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 71.759 41.601 5.795 5.795 5.795 5.795 47.396 24.363 66% 66%
March - 2019
3 units - Khadukhail - completed. Gagra - plastering in progress. Mandar - plastering in progress.
No Image
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 71.759 41.601 5.795 5.795 5.795 5.795 47.396 24.363 66% 66%
March - 2019
3 units - Khadukhail - completed. Gagra - plastering in progress. Mandar - plastering in progress.
No Image
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 71.759 41.601 5.795 5.795 5.795 5.795 47.396 24.363 66% 66%
February - 2019
3 units - Khadukhail - completed. Gagra - plastering in progress. Mandar - plastering in progress.
No Image
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 71.759 41.601 5.795 5.795 5.795 5.795 47.396 24.363 66% 66%
January - 2019
3 units - Khadukhail - completed. Gagra - plastering in progress. Mandar - plastering in progress.
No Image
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 48.78 34.755 1 1 1 0 34.755 13.025 73% 71%
December - 2018
Charsadda - completed. Tangi - finishing in progress. Shabqadar - deferred due to higher cost of land.
No Image
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 48.78 34.755 0 0 0 0 34.755 14.025 - 71%
November - 2018
Charsadda - completed. Tangi - finishing in progress. Shabqadar - deferred due to higher cost of land.
No Image
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 48.78 34.755 0 0 0 0 34.755 14.025 - 71%
November - 2018
Charsadda - completed. Tangi - finishing in progress. Shabqadar - deferred due to higher cost of land.
No Image
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 48.78 34.755 1 1 1 1 35.755 13.025 73% 73%
April - 2019
Charsadda - completed. Tangi - finishing in progress. Shabqadar - deferred due to higher cost of land.
No Image
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 48.78 34.755 1 1 1 1 35.755 13.025 73% 73%
March - 2019
Charsadda - completed. Tangi - finishing in progress. Shabqadar - deferred due to higher cost of land.
No Image
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 48.78 34.755 1 1 1 1 35.755 13.025 73% 73%
March - 2019
Charsadda - completed. Tangi - finishing in progress. Shabqadar - deferred due to higher cost of land.
No Image
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 48.78 34.755 1 1 1 1 35.755 13.025 73% 73%
February - 2019
Charsadda - completed. Tangi - finishing in progress. Shabqadar - deferred due to higher cost of land.
No Image
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 48.78 34.755 1 1 1 0 34.755 13.025 73% 71%
January - 2019
Charsadda - completed. Tangi - finishing in progress. Shabqadar - deferred due to higher cost of land.
No Image
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar
63
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 24.1 24.1 0 0 0 0 24.1 0 - 100%
September - 2018
Completed & H/O.
No Image
PHED Office Chitral
63
(OG)
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 24.1 24.1 0 0 0 0 24.1 0 - 100%
July - 2018
Completed & H/O.
No Image
PHED Office Chitral
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 57.788 45.814 2 2 2 0.067 45.881 9.974 83% 79%
December - 2018
Completed (3 units).
No Image
1) Tehsil Paharpur
2) Tehsil Daraban
3) Tehsil Paroa
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 57.788 45.814 2 2 2 0.067 45.881 9.974 83% 79%
November - 2018
Completed (3 units).
No Image
1) Tehsil Paharpur
2) Tehsil Daraban
3) Tehsil Paroa
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 57.788 45.814 2 2 2 0.067 45.881 9.974 83% 79%
November - 2018
Completed (3 units).
No Image
1) Tehsil Paharpur
2) Tehsil Daraban
3) Tehsil Paroa
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 57.788 45.813 2 2 2 2 47.813 9.975 83% 83%
April - 2019
Completed (3 units). Liability Rs.1.583 m.
No Image
1) Tehsil Paharpur
2) Tehsil Daraban
3) Tehsil Paroa
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 57.788 45.813 2 2 2 1.249 47.062 9.975 83% 81%
March - 2019
Completed (3 units). Liability Rs.1.583 m.
No Image
1) Tehsil Paharpur
2) Tehsil Daraban
3) Tehsil Paroa
63
(OG)
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 57.788 45.813 2 2 2 1.249 47.062 9.975 83% 81%
March - 2019
Completed (3 units). Liability Rs.1.583 m.
No Image
1) Tehsil Paharpur
2) Tehsil Daraban
3) Tehsil Paroa
Pages : 1 2 3 4