Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- December - 2018 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- November - 2018 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- November - 2018 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- April - 2019 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- March - 2019 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- March - 2019 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- February - 2019 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- January - 2019 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- December - 2018 |
Site not yet H/O. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- November - 2018 |
Site not yet H/O. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- November - 2018 |
Site not yet H/O. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
63 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.1 | 22.9 | 0 | 0 | 0 | 0 | 22.9 | 0.2 | - |
99% September - 2018 |
Completed & H/O. |
No Image |
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018 | |||||||||||||||||||
63 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.1 | 22.9 | 0 | 0 | 0 | 0 | 22.9 | 0.2 | - |
99% July - 2018 |
Completed & H/O. |
No Image |
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- April - 2019 |
Tender under process. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- March - 2019 |
Tender under process. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- March - 2019 |
Tender under process. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- February - 2019 |
Site not yet H/O. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- January - 2019 |
Site not yet H/O. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2018 |
Approved in DDWP. AA awaited. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
PC-I/DCE for Rs.42.696 m for Tehsil Battagram and Rs.31.231 m for Tehsil Allai submitted to DC Battagram on 13/11/2017. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
PC-I/DCE for Rs.42.696 m for Tehsil Battagram and Rs.31.231 m for Tehsil Allai submitted to DC Battagram on 13/11/2017. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2019 |
Approved in DDWP. AA awaited. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
Approved in DDWP. AA awaited. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
Approved in DDWP. AA awaited. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2019 |
Approved in DDWP. AA awaited. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2019 |
Approved in DDWP. AA awaited. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 41.601 | 5.795 | 5.795 | 5.795 | 4.935 | 46.536 | 24.363 | 66% |
65% December - 2018 |
3 units - Khadukhail - completed. Gagra - plastering in progress. Mandar - plastering in progress. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 41.6 | 2 | 2 | 2 | 2 | 43.6 | 28.159 | 61% |
61% November - 2018 |
3 units - Khadukhail - completed. Gagra - plastering in progress. Mandar - plastering in progress. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 41.6 | 2 | 2 | 2 | 2 | 43.6 | 28.159 | 61% |
61% November - 2018 |
3 units - Khadukhail - completed. Gagra - plastering in progress. Mandar - plastering in progress. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 41.601 | 5.795 | 5.795 | 5.795 | 5.795 | 47.396 | 24.363 | 66% |
66% April - 2019 |
3 units - Khadukhail - completed. Gagra - plastering in progress. Mandar - plastering in progress. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 41.601 | 5.795 | 5.795 | 5.795 | 5.795 | 47.396 | 24.363 | 66% |
66% March - 2019 |
3 units - Khadukhail - completed. Gagra - plastering in progress. Mandar - plastering in progress. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 41.601 | 5.795 | 5.795 | 5.795 | 5.795 | 47.396 | 24.363 | 66% |
66% March - 2019 |
3 units - Khadukhail - completed. Gagra - plastering in progress. Mandar - plastering in progress. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 41.601 | 5.795 | 5.795 | 5.795 | 5.795 | 47.396 | 24.363 | 66% |
66% February - 2019 |
3 units - Khadukhail - completed. Gagra - plastering in progress. Mandar - plastering in progress. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 41.601 | 5.795 | 5.795 | 5.795 | 5.795 | 47.396 | 24.363 | 66% |
66% January - 2019 |
3 units - Khadukhail - completed. Gagra - plastering in progress. Mandar - plastering in progress. |
No Image |
1) Tehsil Daggar PK-79 shifted to Khadukhail
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 34.755 | 1 | 1 | 1 | 0 | 34.755 | 13.025 | 73% |
71% December - 2018 |
Charsadda - completed. Tangi - finishing in progress. Shabqadar - deferred due to higher cost of land. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 34.755 | 0 | 0 | 0 | 0 | 34.755 | 14.025 | - |
71% November - 2018 |
Charsadda - completed. Tangi - finishing in progress. Shabqadar - deferred due to higher cost of land. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 34.755 | 0 | 0 | 0 | 0 | 34.755 | 14.025 | - |
71% November - 2018 |
Charsadda - completed. Tangi - finishing in progress. Shabqadar - deferred due to higher cost of land. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 34.755 | 1 | 1 | 1 | 1 | 35.755 | 13.025 | 73% |
73% April - 2019 |
Charsadda - completed. Tangi - finishing in progress. Shabqadar - deferred due to higher cost of land. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 34.755 | 1 | 1 | 1 | 1 | 35.755 | 13.025 | 73% |
73% March - 2019 |
Charsadda - completed. Tangi - finishing in progress. Shabqadar - deferred due to higher cost of land. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 34.755 | 1 | 1 | 1 | 1 | 35.755 | 13.025 | 73% |
73% March - 2019 |
Charsadda - completed. Tangi - finishing in progress. Shabqadar - deferred due to higher cost of land. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 34.755 | 1 | 1 | 1 | 1 | 35.755 | 13.025 | 73% |
73% February - 2019 |
Charsadda - completed. Tangi - finishing in progress. Shabqadar - deferred due to higher cost of land. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.78 | 34.755 | 1 | 1 | 1 | 0 | 34.755 | 13.025 | 73% |
71% January - 2019 |
Charsadda - completed. Tangi - finishing in progress. Shabqadar - deferred due to higher cost of land. |
No Image |
1) Tehsil Charsadda
2) Tehsil Tangi
3) Tehsil Shabqadar | |||||||||||||||||||
63 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.1 | 24.1 | 0 | 0 | 0 | 0 | 24.1 | 0 | - |
100% September - 2018 |
Completed & H/O. |
No Image |
PHED Office Chitral | |||||||||||||||||||
63 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.1 | 24.1 | 0 | 0 | 0 | 0 | 24.1 | 0 | - |
100% July - 2018 |
Completed & H/O. |
No Image |
PHED Office Chitral | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.788 | 45.814 | 2 | 2 | 2 | 0.067 | 45.881 | 9.974 | 83% |
79% December - 2018 |
Completed (3 units). |
No Image |
1) Tehsil Paharpur
2) Tehsil Daraban
3) Tehsil Paroa | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.788 | 45.814 | 2 | 2 | 2 | 0.067 | 45.881 | 9.974 | 83% |
79% November - 2018 |
Completed (3 units). |
No Image |
1) Tehsil Paharpur
2) Tehsil Daraban
3) Tehsil Paroa | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.788 | 45.814 | 2 | 2 | 2 | 0.067 | 45.881 | 9.974 | 83% |
79% November - 2018 |
Completed (3 units). |
No Image |
1) Tehsil Paharpur
2) Tehsil Daraban
3) Tehsil Paroa | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.788 | 45.813 | 2 | 2 | 2 | 2 | 47.813 | 9.975 | 83% |
83% April - 2019 |
Completed (3 units). Liability Rs.1.583 m. |
No Image |
1) Tehsil Paharpur
2) Tehsil Daraban
3) Tehsil Paroa | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.788 | 45.813 | 2 | 2 | 2 | 1.249 | 47.062 | 9.975 | 83% |
81% March - 2019 |
Completed (3 units). Liability Rs.1.583 m. |
No Image |
1) Tehsil Paharpur
2) Tehsil Daraban
3) Tehsil Paroa | |||||||||||||||||||
63 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 57.788 | 45.813 | 2 | 2 | 2 | 1.249 | 47.062 | 9.975 | 83% |
81% March - 2019 |
Completed (3 units). Liability Rs.1.583 m. |
No Image |
1) Tehsil Paharpur
2) Tehsil Daraban
3) Tehsil Paroa | |||||||||||||||||||