Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
639 (New) |
150029-Construction of building for GGDC at Abbottabad (functional in rented building). |
Abbottabad |
- | - | - | - | Line Deptt | 175 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
No Image | |
639 (New) |
150029-Construction of building for GGDC at Abbottabad (functional in rented building). |
Abbottabad |
- | - | - | - | Line Deptt | 175 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
Site issue resolved. Pre-qualification under process. |
No Image |
639 (New) |
150029-Construction of building for GGDC at Abbottabad (functional in rented building). |
Abbottabad |
- | - | - | - | Line Deptt | 175 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
Site issue resolved. Pre-qualification under process. |
No Image |
639 (New) |
150029-Construction of building for GGDC at Abbottabad (functional in rented building). |
Abbottabad |
- | - | - | - | Line Deptt | 175 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
Site issue resolved. Pre-qualification under process. |
No Image |
639 (New) |
150029-Construction of building for GGDC at Abbottabad (functional in rented building). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 175 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
No Image | |
639 (New) |
150029-Construction of building for GGDC at Abbottabad (functional in rented building). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 175 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
No Image | |
639 (New) |
150029-Construction of building for GGDC at Abbottabad (functional in rented building). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 175 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- June - 2018 |
No Image | |
639 (New) |
150029-Construction of building for GGDC at Abbottabad (functional in rented building). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 175 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- May - 2018 |
No Image | |
639 (New) |
150029-Construction of building for GGDC at Abbottabad (functional in rented building). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 175 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- April - 2018 |
No Image | |
639 (New) |
150029-Construction of building for GGDC at Abbottabad (functional in rented building). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 175 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- March - 2018 |
No Image | |
639 (New) |
150029-Construction of building for GGDC at Abbottabad (functional in rented building). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 175 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- February - 2018 |
No Image | |
639 (New) |
150029-Construction of building for GGDC at Abbottabad (functional in rented building). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 175 | 0 | 5 | 5 | 0 | 0 | 0 | 0 | - |
- January - 2018 |
No Image | |
639 (OG) |
160604-Special Initiative Programme for District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 118.852 | 28 | 28 | 5 | 5 | 123.852 | 103.148 | 59% |
50% December - 2018 |
Roads, Janazagah, Streets in progress. School component not started as auction awaited from E&SE. |
No Image |
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22 | |||||||||||||||||||
639 (OG) |
160604-Special Initiative Programme for District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 118.852 | 28 | 28 | 5 | 5 | 123.852 | 103.148 | 59% |
50% November - 2018 |
Roads, Janazagah, Streets in progress. School component not started as auction awaited from E&SE. |
No Image |
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22 | |||||||||||||||||||
639 (OG) |
160604-Special Initiative Programme for District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 118.852 | 28 | 28 | 5 | 5 | 123.852 | 103.148 | 59% |
50% November - 2018 |
Roads, Janazagah, Streets in progress. School component not started as auction awaited from E&SE. |
No Image |
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22 | |||||||||||||||||||
639 (OG) |
160604-Special Initiative Programme for District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 118.852 | 28 | 28 | 5 | 5 | 123.852 | 103.148 | 59% |
50% April - 2019 |
Roads, Janazagah, Streets in progress. School component not started as auction awaited from E&SE. |
No Image |
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22 | |||||||||||||||||||
639 (OG) |
160604-Special Initiative Programme for District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 118.852 | 28 | 28 | 5 | 5 | 123.852 | 103.148 | 59% |
50% March - 2019 |
Roads, Janazagah, Streets in progress. School component not started as auction awaited from E&SE. |
No Image |
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22 | |||||||||||||||||||
639 (OG) |
160604-Special Initiative Programme for District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 118.852 | 28 | 28 | 5 | 5 | 123.852 | 103.148 | 59% |
50% March - 2019 |
Roads, Janazagah, Streets in progress. School component not started as auction awaited from E&SE. |
No Image |
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22 | |||||||||||||||||||
639 (OG) |
160604-Special Initiative Programme for District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 118.852 | 28 | 28 | 5 | 5 | 123.852 | 103.148 | 59% |
50% February - 2019 |
Roads, Janazagah, Streets in progress. School component not started as auction awaited from E&SE. |
No Image |
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22 | |||||||||||||||||||
639 (OG) |
160604-Special Initiative Programme for District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 118.852 | 28 | 28 | 5 | 5 | 123.852 | 103.148 | 59% |
50% January - 2019 |
Roads, Janazagah, Streets in progress. School component not started as auction awaited from E&SE. |
No Image |
1) PK-17
2) PK-18
3) PK-19
4) PK-20
5) PK-21
6) PK-22 | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% December - 2020 |
Completed & H/O |
No Image |
DI.Khan | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% December - 2020 |
Completed & H/O |
No Image |
DI.Khan | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 0 | 0 | 0 | 0 | 0 | 0 | 87.64 | - |
- October - 2020 |
Completed & H/O |
No Image |
DI.Khan | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 0 | 0 | 0 | 0 | 0 | 0 | 87.64 | - |
- September - 2020 |
Completed & H/O |
No Image |
DI.Khan | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 0 | 0 | 0 | 0 | 0 | 0 | 87.64 | - |
- July - 2020 |
Completed & H/O
Demand bill for meter paid to WA |
No Image |
DI.Khan | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% May - 2021 |
01- Unit
Completed & H/O |
No Image |
DI.Khan
Scope of work:
| |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% April - 2021 |
Completed & H/O |
No Image |
DI.Khan | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% March - 2021 |
Completed & H/O |
No Image |
DI.Khan | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% February - 2021 |
Completed & H/O |
No Image |
DI.Khan | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 71.57 | 0 | 0 | 0 | 0 | 71.57 | 16.07 | - |
82% January - 2021 |
Completed & H/O |
No Image |
DI.Khan | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
DI.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 87.64 | 0 | 0 | 0 | 0 | 0 | 0 | 87.64 | - |
- August - 2020 |
Completed & H/O |
No Image |
DI.Khan | |||||||||||||||||||
639 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha Khel Road Rehman Abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in Ucs, Sodhal, Lachi Rural, Mandori District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 249.927 | 168.89 | 27.5 | 27.5 | 13.75 | 13.75 | 182.64 | 53.537 | 79% |
73% September - 2018 |
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
639 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha Khel Road Rehman Abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in Ucs, Sodhal, Lachi Rural, Mandori District Kohat. |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 249.927 | 168.89 | 27.5 | 27.5 | 13.75 | 0 | 168.89 | 53.537 | 79% |
68% July - 2018 |
Bridge at Tarali - piles 64/80 completed, 1 pile cpa completed, girders casting in progress. Approaches 35 % completed. Road 7.29 Km - 6.5 Km asphalt completed. Cannot be complted (alternate scheme 998 will be completed). |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 32 | 7 | 7 | 7 | 7 | 39 | 58.69 | 40% |
40% December - 2020 |
Block A+B = Roof laid.
FF - Roofing in progress.
TS Submitted to SE |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 32 | 7 | 7 | 7 | 7 | 39 | 58.69 | 40% |
40% December - 2020 |
Block A+B = Roof laid.
FF - Roofing in progress.
TS Submitted to SE |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 0 | 0 | 0 | 0 | 0 | 0 | 97.69 | - |
- October - 2020 |
Block A+B = Roof laid.
FF - Roofing in progress. |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 0 | 0 | 0 | 0 | 0 | 0 | 97.69 | - |
- September - 2020 |
Block A+B = Roof laid.
FF - Roofing in progress. |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 0 | 0 | 0 | 0 | 0 | 0 | 97.69 | - |
- August - 2020 |
Block A+B = Roof laid.
FF - Roofing in progress. |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 0 | 0 | 0 | 0 | 0 | 0 | 97.69 | - |
- July - 2020 |
Block A+B = Roof laid.
FF - Roofing in progress. |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 32 | 18.024 | 18.024 | 18.024 | 14.839 | 46.839 | 47.666 | 51% |
48% May - 2021 |
Block A+B = Roof laid.
FF - Roofing in progress.
TS Submitted to SE |
No Image |
Tax Facilitation Center District Nowshera
Scope of work:
| |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 32 | 18.024 | 18.024 | 18.024 | 18.024 | 50.024 | 47.666 | 51% |
51% April - 2021 |
Block A+B = Roof laid.
FF - Roofing in progress.
TS Submitted to SE |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 32 | 18.14 | 18.14 | 18.14 | 10.514 | 42.514 | 47.55 | 51% |
44% March - 2021 |
Block A+B = Roof laid.
FF - Roofing in progress.
TS Submitted to SE |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 32 | 18.14 | 18.14 | 18.14 | 10.514 | 42.514 | 47.55 | 51% |
44% February - 2021 |
Block A+B = Roof laid.
FF - Roofing in progress.
TS Submitted to SE |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.69 | 32 | 10.514 | 10.514 | 10.514 | 10.514 | 42.514 | 55.176 | 44% |
44% January - 2021 |
Block A+B = Roof laid.
FF - Roofing in progress.
TS Submitted to SE |
No Image |
Tax Facilitation Center District Nowshera | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Peshawar MPD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 156.887 | 37 | 37 | 37 | 37 | 193.887 | 28.363 | 87% |
87% May - 2021 |
01- Unit
Finishing in progress |
No Image |
Tax Facilitation Center at Hayatabad, Peshawar
Scope of work:
| |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Peshawar MPD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 156.887 | 37 | 37 | 37 | 37 | 193.887 | 28.363 | 87% |
87% April - 2021 |
Builidng completed except Elevators |
No Image |
Tax Facilitation Center at Hayatabad, Peshawar | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 156.887 | 17 | 17 | 17 | 17 | 173.887 | 48.363 | 78% |
78% December - 2020 |
B/W & Brick work completed GF, FF tile completed. Opening of Lift LC in progress. |
No Image |
Tax Facilitation Center at Hayatabad, Peshawa | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 156.887 | 17 | 17 | 17 | 17 | 173.887 | 48.363 | 78% |
78% December - 2020 |
B/W & Brick work completed GF, FF tile completed. Opening of Lift LC in progress. |
No Image |
Tax Facilitation Center at Hayatabad, Peshawa | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 0 | 7 | 7 | 7 | 6.893 | 6.893 | 215.25 | 3% |
3% October - 2020 |
B/W & Brick work completed GF, FF tile completed. Opening of Lift LC in progress. |
No Image |
Tax Facilitation Center at Hayatabad, Peshawa | |||||||||||||||||||
639 (OG) |
100350-Establishment of Tax Facilitation Centers and Excise Offices in 06 Districts of Khyber Pakhtunkhwa |
Peshawar PBC-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 222.25 | 0 | 0 | 0 | 0 | 0 | 0 | 222.25 | - |
- September - 2020 |
B/W & Brick work completed GF, FF tile completed. Opening of Lift LC in progress. |
No Image |
Tax Facilitation Center at Hayatabad, Peshawa | |||||||||||||||||||