Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
- | - | - | 28-01-15 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- December - 2017 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
- | - | - | 28-01-15 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- September - 2017 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
- | - | - | 28-01-15 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- August - 2017 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
- | - | - | 28-01-15 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- July - 2017 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- November - 2017 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- October - 2017 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- June - 2018 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- May - 2018 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- April - 2018 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- March - 2018 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- February - 2018 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.186 | 0 | 0 | 0 | 0 | 0 | 0 | 27.186 | - |
- January - 2018 |
Work order issued. Land not available. |
No Image |
1) SDC Havelian | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
- | - | - | 28-01-15 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- December - 2017 |
Site not yet H/O. |
No Image |
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
- | - | - | 28-01-15 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- September - 2017 |
Site not yet H/O. |
No Image |
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
- | - | - | 28-01-15 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- August - 2017 |
Site not yet H/O. |
No Image |
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
- | - | - | 28-01-15 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- July - 2017 |
Site not yet H/O. |
No Image |
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- November - 2017 |
Site not yet H/O. |
No Image |
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- October - 2017 |
Site not yet H/O. |
No Image |
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- June - 2018 |
Site not yet H/O. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- May - 2018 |
Site not yet H/O. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- April - 2018 |
Site not yet H/O. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- March - 2018 |
Site not yet H/O. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- February - 2018 |
Site not yet H/O. |
No Image |
Service Delivery Center, Bannu | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.677 | 0 | 0 | 0 | 0 | 0 | 0 | 36.677 | - |
- January - 2018 |
Site not yet H/O. |
No Image |
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
- | - | - | 28-01-15 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
PC-I/DCE for Rs.42.696 m for Tehsil Battagram and Rs.31.231 m for Tehsil Allai submitted to DC Battagram on 13/11/2017. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
- | - | - | 28-01-15 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
PC-I/DCE for Rs.78.743 m on MRS 2015 submitted to SPO BOR on 03/09/2015. Allai -approved on 26/01/2016. AA awaited. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
- | - | - | 28-01-15 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
PC-I/DCE for Rs.78.743 m on MRS 2015 submitted to SPO BOR on 03/09/2015. Allai -approved on 26/01/2016. AA awaited. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
- | - | - | 28-01-15 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
PC-I/DCE for Rs.78.743 m on MRS 2015 submitted to SPO BOR on 03/09/2015. Allai -approved on 26/01/2016. AA awaited. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
64 (OG) |
150289-Construction of 100 Nos Patwar Khanas in Khyber Pakhtunkhwa (Phase-II). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2018 |
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.286 m on MRS-2017 submitted to DC on 26/03/2018. |
No Image |
1) Tikri Mera
2) Shamlai | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
PC-I/DCE for Rs.42.696 m for Tehsil Battagram and Rs.31.231 m for Tehsil Allai submitted to DC Battagram on 13/11/2017. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
64 (OG) |
150289-Construction of 100 Nos Patwar Khanas in Khyber Pakhtunkhwa (Phase-II). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.286 m on MRS-2017 submitted to DC on 26/03/2018. |
No Image |
1) Tikri Mera
2) Shamlai | |||||||||||||||||||
64 (OG) |
150289-Construction of 100 Nos Patwar Khanas in Khyber Pakhtunkhwa (Phase-II). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.286 m on MRS-2017 submitted to DC on 26/03/2018. |
No Image |
1) Tikri Mera
2) Shamlai | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
PC-I/DCE for Rs.78.743 m on MRS 2015 submitted to SPO BOR on 03/09/2015. Allai -approved on 26/01/2016. AA awaited. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- June - 2018 |
PC-I/DCE for Rs.42.696 m for Tehsil Battagram and Rs.31.231 m for Tehsil Allai submitted to DC Battagram on 13/11/2017. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2018 |
PC-I/DCE for Rs.42.696 m for Tehsil Battagram and Rs.31.231 m for Tehsil Allai submitted to DC Battagram on 13/11/2017. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2018 |
PC-I/DCE for Rs.42.696 m for Tehsil Battagram and Rs.31.231 m for Tehsil Allai submitted to DC Battagram on 13/11/2017. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
64 (OG) |
150289-Construction of 100 Nos Patwar Khanas in Khyber Pakhtunkhwa (Phase-II). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2019 |
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.286 m on MRS-2017 submitted to DC on 26/03/2018. |
No Image |
1) Tikri Mera
2) Shamlai | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2018 |
PC-I/DCE for Rs.42.696 m for Tehsil Battagram and Rs.31.231 m for Tehsil Allai submitted to DC Battagram on 13/11/2017. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
64 (OG) |
150289-Construction of 100 Nos Patwar Khanas in Khyber Pakhtunkhwa (Phase-II). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.286 m on MRS-2017 submitted to DC on 26/03/2018. |
No Image |
1) Tikri Mera
2) Shamlai | |||||||||||||||||||
64 (OG) |
150289-Construction of 100 Nos Patwar Khanas in Khyber Pakhtunkhwa (Phase-II). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2019 |
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.286 m on MRS-2017 submitted to DC on 26/03/2018. |
No Image |
1) Tikri Mera
2) Shamlai | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2018 |
PC-I/DCE for Rs.42.696 m for Tehsil Battagram and Rs.31.231 m for Tehsil Allai submitted to DC Battagram on 13/11/2017. |
No Image |
1) Tehsil Battagram PK-59
2) Tehsil Allai PK-60 | |||||||||||||||||||
64 (OG) |
150289-Construction of 100 Nos Patwar Khanas in Khyber Pakhtunkhwa (Phase-II). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2019 |
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.286 m on MRS-2017 submitted to DC on 26/03/2018. |
No Image |
1) Tikri Mera
2) Shamlai | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2018 |
PC-I/DCE for Rs.42.696 m for Tehsil Battagram and Rs.31.231 m for Tehsil Allai submitted to DC Battagram on 13/11/2017. |
No Image |
1) Tehsil Battagram PK-59 2) Tehsil Allai PK-60 | |||||||||||||||||||
64 (OG) |
150289-Construction of 100 Nos Patwar Khanas in Khyber Pakhtunkhwa (Phase-II). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2019 |
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.286 m on MRS-2017 submitted to DC on 26/03/2018. |
No Image |
1) Tikri Mera
2) Shamlai | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
25-06-16 | - | - | 28-01-15 | - | 71.759 | 35.44 | 9 | 9 | 9 | 6.7 | 42.14 | 27.319 | 62% |
59% December - 2017 |
3 units - (a) Khadukhail - finishing in progress. (b) Gagra - roof level. (c) Mandar - lintel level. |
No Image |
1) Tehsil Daggar PK-79
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
25-06-16 | - | - | 28-01-15 | - | 71.759 | 35.44 | 9 | 9 | 9 | 1.104 | 36.544 | 27.319 | 62% |
51% September - 2017 |
3 units - (a) Khadukhail - finishing in progress. (b) Gagra - roof level. (c) Mandar - lintel level. |
No Image |
1) Tehsil Daggar PK-79
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
25-06-16 | - | - | 28-01-15 | - | 71.759 | 35.44 | 9 | 9 | 9 | 1.104 | 36.544 | 27.319 | 62% |
51% August - 2017 |
3 units - (a) Khadukhail - finishing in progress. (b) Gagra - roof level. (c) Mandar - lintel level. |
No Image |
1) Tehsil Daggar PK-79
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
- | - | - | 28-01-15 | - | 71.759 | 35.44 | 9 | 9 | 9 | 0 | 35.44 | 27.319 | 62% |
49% July - 2017 |
3 units - (a) Khadukhail - finishing in progress. (b) Gagra - roof level. (c) Mandar - lintel level. |
No Image |
1) Tehsil Daggar PK-79
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 35.44 | 9 | 9 | 9 | 4.173 | 39.613 | 27.319 | 62% |
55% November - 2017 |
3 units - (a) Khadukhail - finishing in progress. (b) Gagra - roof level. (c) Mandar - lintel level. |
No Image |
1) Tehsil Daggar PK-79
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
64 (OG) |
140586-Establishment of Service Delivery Centres in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 71.759 | 35.44 | 9 | 9 | 9 | 1.104 | 36.544 | 27.319 | 62% |
51% October - 2017 |
3 units - (a) Khadukhail - finishing in progress. (b) Gagra - roof level. (c) Mandar - lintel level. |
No Image |
1) Tehsil Daggar PK-79
2) Tehsil Gagra PK-78
3) Tehsil Mandnr PK-77 | |||||||||||||||||||
Pages : 1 2 3 4 5 6 |