Progressive Review for the month(s) of : January - 2019, January - 2021, January - 2018, February - 2019, February - 2021, February - 2018, March - 2019, March - 2021, March - 2018, April - 2019, April - 2021, April - 2018, May - 2018, May - 2021, June - 2018, July - 2018, July - 2020, July - 2017, August - 2020, August - 2017, September - 2018, September - 2020, September - 2017, October - 2020, October - 2017, November - 2018, November - 2017, December - 2018, December - 2017,

Showing Page Number : 1 of 5

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
65
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 37.85 20.3 7.421 7.421 7.421 3.999 24.299 10.129 73% 64%
December - 2018
GF - flooring completed. FF - finishing stage.
No Image
Bannu (construction of new mohafiz khana/record rooms)
65
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 37.85 20.3 0 0 0 0 20.3 17.55 - 54%
November - 2018
GF - flooring completed. FF - finishing stage.
No Image
Bannu (construction of new mohafiz khana/record rooms)
65
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 37.85 20.3 0 0 0 0 20.3 17.55 - 54%
November - 2018
GF - flooring completed. FF - finishing stage.
No Image
Bannu (construction of new mohafiz khana/record rooms)
65
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 136.452 0 0 0 0 0 0 136.452 - -
September - 2018
Work order issued on 16/03/2018. Mutation of land/handing over of site under process.
No Image
Bannu
65
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 136.452 0 0 0 0 0 0 136.452 - -
July - 2018
Work order issued on 16/03/2018. Mutation of land/handing over of site under process.
No Image
Bannu
65
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 37.85 20.3 7.421 7.421 7.421 7.421 27.721 10.129 73% 73%
April - 2019
GF - flooring completed. FF - finishing stage.
No Image
Bannu (construction of new mohafiz khana/record rooms)
65
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 37.85 20.3 7.421 7.421 7.421 7.421 27.721 10.129 73% 73%
March - 2019
GF - flooring completed. FF - finishing stage.
No Image
Bannu (construction of new mohafiz khana/record rooms)
65
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 37.85 20.3 7.421 7.421 7.421 7.421 27.721 10.129 73% 73%
March - 2019
GF - flooring completed. FF - finishing stage.
No Image
Bannu (construction of new mohafiz khana/record rooms)
65
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 37.85 20.3 7.421 7.421 7.421 7.421 27.721 10.129 73% 73%
February - 2019
GF - flooring completed. FF - finishing stage.
No Image
Bannu (construction of new mohafiz khana/record rooms)
65
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Bannu
30-11--1 30-11--1 - 30-11--1 - 37.85 20.3 7.421 7.421 7.421 7.421 27.721 10.129 73% 73%
January - 2019
GF - flooring completed. FF - finishing stage.
No Image
Bannu (construction of new mohafiz khana/record rooms)
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Battagram
- - - 02-11-15 - 0 0 0 0 0 0 0 0 - -
December - 2017
2 Nos Patwar Khanas identified. PC-I/DCE under preparation on MRS-2017.
No Image
1) Tikri Mera
2) Shamlai
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Battagram
- - - 02-11-15 - 0 0 0 0 0 0 0 0 - -
September - 2017
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.929 m on MRS-2016 submitted to SPO BOR on 02/05/2016.
No Image
1) Tikri Mera
2) Shamlai
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Battagram
- - - 02-11-15 - 0 0 0 0 0 0 0 0 - -
August - 2017
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.929 m on MRS-2016 submitted to SPO BOR on 02/05/2016.
No Image
1) Tikri Mera
2) Shamlai
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Battagram
- - - 02-11-15 - 0 0 0 0 0 0 0 0 - -
July - 2017
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.929 m on MRS-2016 submitted to SPO BOR on 02/05/2016.
No Image
1) Tikri Mera
2) Shamlai
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
November - 2017
2 Nos Patwar Khanas identified. PC-I/DCE under preparation on MRS-2017.
No Image
1) Tikri Mera
2) Shamlai
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
October - 2017
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.929 m on MRS-2016 submitted to SPO BOR on 02/05/2016.
No Image
1) Tikri Mera
2) Shamlai
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
June - 2018
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.286 m on MRS-2017 submitted to DC on 26/03/2018.
No Image
1) Tikri Mera
2) Shamlai
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
May - 2018
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.286 m on MRS-2017 submitted to DC on 26/03/2018.
No Image
1) Tikri Mera
2) Shamlai
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
April - 2018
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.286 m on MRS-2017 submitted to DC on 26/03/2018.
No Image
1) Tikri Mera
2) Shamlai
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
March - 2018
2 Nos Patwar Khanas identified. PC-I/DCE for Rs.10.286 m on MRS-2017 submitted to DC on 26/03/2018.
No Image
1) Tikri Mera
2) Shamlai
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
February - 2018
2 Nos Patwar Khanas identified. PC-I/DCE under preparation on MRS-2017.
No Image
1) Tikri Mera
2) Shamlai
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Battagram
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
January - 2018
2 Nos Patwar Khanas identified. PC-I/DCE under preparation on MRS-2017.
No Image
1) Tikri Mera 2) Shamlai
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Buner
- - - 02-11-15 - 0 0 0 0 0 0 0 0 - -
December - 2017
Site not yet identified.
No Image
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Buner
- - - 02-11-15 - 0 0 0 0 0 0 0 0 - -
September - 2017
Site not yet identified.
No Image
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Buner
- - - 02-11-15 - 0 0 0 0 0 0 0 0 - -
August - 2017
Site not yet identified.
No Image
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Buner
- - - 02-11-15 - 0 0 0 0 0 0 0 0 - -
July - 2017
Site not yet identified.
No Image
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Buner
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
November - 2017
Site not yet identified.
No Image
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Buner
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
October - 2017
Site not yet identified.
No Image
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Buner
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
June - 2018
Site not yet identified.
No Image
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Buner
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
May - 2018
Site not yet identified.
No Image
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Buner
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
April - 2018
Site not yet identified.
No Image
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Buner
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
March - 2018
Site not yet identified.
No Image
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Buner
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
February - 2018
Site not yet identified.
No Image
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Buner
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
January - 2018
Site not yet identified.
No Image
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Charsadda
- - - 02-11-15 - 0 0 0 0 0 0 0 0 - -
December - 2017
PC-I/DCE submitted to SPO BOR on 21/03/2016.
No Image
1) Shabqadar PK-22
2) Maira Nisatta PK-17
3) Charsadda PK-17
4) Prang Safar Khel PK-17
5) Bari Band PK-20
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Charsadda
- - - 02-11-15 - 0 0 0 0 0 0 0 0 - -
September - 2017
PC-I/DCE submitted to SPO BOR on 21/03/2016.
No Image
1) Shabqadar PK-22
2) Maira Nisatta PK-17
3) Charsadda PK-17
4) Prang Safar Khel PK-17
5) Bari Band PK-20
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Charsadda
- - - 02-11-15 - 0 0 0 0 0 0 0 0 - -
August - 2017
PC-I/DCE submitted to SPO BOR on 21/03/2016.
No Image
1) Shabqadar PK-22
2) Maira Nisatta PK-17
3) Charsadda PK-17
4) Prang Safar Khel PK-17
5) Bari Band PK-20
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Charsadda
- - - 02-11-15 - 0 0 0 0 0 0 0 0 - -
July - 2017
PC-I/DCE submitted to SPO BOR on 21/03/2016.
No Image
1) Shabqadar PK-22
2) Maira Nisatta PK-17
3) Charsadda PK-17
4) Prang Safar Khel PK-17
5) Bari Band PK-20
65
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 36.281 28.023 0 0 0 0 28.023 8.258 - 77%
December - 2018
Completed & H/O.
No Image
Construction of Mohafiz Khana / Record Room in District Charsadda
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
November - 2017
PC-I/DCE submitted to SPO BOR on 21/03/2016.
No Image
1) Shabqadar PK-22
2) Maira Nisatta PK-17
3) Charsadda PK-17
4) Prang Safar Khel PK-17
5) Bari Band PK-20
65
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 36.281 28.023 0 0 0 0 28.023 8.258 - 77%
November - 2018
Completed & H/O.
No Image
Construction of Mohafiz Khana / Record Room in District Charsadda
65
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 36.281 28.023 0 0 0 0 28.023 8.258 - 77%
November - 2018
Completed & H/O.
No Image
Construction of Mohafiz Khana / Record Room in District Charsadda
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
October - 2017
PC-I/DCE submitted to SPO BOR on 21/03/2016.
No Image
1) Shabqadar PK-22
2) Maira Nisatta PK-17
3) Charsadda PK-17
4) Prang Safar Khel PK-17
5) Bari Band PK-20
65
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 103.45 0 0 0 0 0 0 103.45 - -
September - 2018
Work order issued. Land acquisition under process.
No Image
Construction of Tehsil Building Shabqaddar, District Charsadda
65
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 103.45 0 0 0 0 0 0 103.45 - -
July - 2018
Work order issued. Land acquisition under process.
No Image
Construction of Tehsil Building Shabqaddar, District Charsadda
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
June - 2018
PC-I/DCE submitted to SPO BOR on 21/03/2016.
No Image
1) Shabqadar PK-22
2) Maira Nisatta PK-17
3) Charsadda PK-17
4) Prang Safar Khel PK-17
5) Bari Band PK-20
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
May - 2018
PC-I/DCE submitted to SPO BOR on 21/03/2016.
No Image
1) Shabqadar PK-22
2) Maira Nisatta PK-17
3) Charsadda PK-17
4) Prang Safar Khel PK-17
5) Bari Band PK-20
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
April - 2018
PC-I/DCE submitted to SPO BOR on 21/03/2016.
No Image
1) Shabqadar PK-22
2) Maira Nisatta PK-17
3) Charsadda PK-17
4) Prang Safar Khel PK-17
5) Bari Band PK-20
65
(OG)
150311-Construction of new Mohafiz Khanas / Record Rooms on Need Basis.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 36.281 28.023 0 0 0 0 28.023 8.258 - 77%
April - 2019
Completed & H/O.
No Image
Construction of Mohafiz Khana / Record Room in District Charsadda
65
(OG)
150289-Construction of 100 No Patwar Khanas in Khyber Pakhtunkhwa (Phase-II).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
March - 2018
PC-I/DCE submitted to SPO BOR on 21/03/2016.
No Image
1) Shabqadar PK-22
2) Maira Nisatta PK-17
3) Charsadda PK-17
4) Prang Safar Khel PK-17
5) Bari Band PK-20