Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 176.844 | 177.894 | 0 | 0 | 0 | 0 | 177.894 | 0 | - |
100% December - 2018 |
Main building, basement, residential building in finishing stage. Developmental work in progress. 2nd Revised PC-I/DCE for Rs.624.685 m submitted to SOB on 16/05/2018. |
No Image |
Domel, District Bannu | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 176.844 | 177.894 | 0 | 0 | 0 | 0 | 177.894 | 0 | - |
100% November - 2018 |
Main building, basement, residential building in finishing stage. Developmental work in progress. 2nd Revised PC-I/DCE for Rs.624.685 m submitted to SOB on 16/05/2018. |
No Image |
Domel, District Bannu | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 176.844 | 177.894 | 0 | 0 | 0 | 0 | 177.894 | 0 | - |
100% November - 2018 |
Main building, basement, residential building in finishing stage. Developmental work in progress. 2nd Revised PC-I/DCE for Rs.624.685 m submitted to SOB on 16/05/2018. |
No Image |
Domel, District Bannu | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 194.728 | 177.894 | 16.771 | 16.771 | 16.771 | 10.965 | 188.859 | 0.063 | 100% |
97% April - 2019 |
Completed. (financially + Physically ) |
No Image |
Domel, District Bannu | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 194.728 | 177.894 | 13.971 | 13.971 | 13.971 | 10.965 | 188.859 | 2.863 | 99% |
97% March - 2019 |
Main building, basement, residential building in finishing stage. Developmental work in progress. Rs. 2.9 m Required fopr completion |
No Image |
Domel, District Bannu | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 194.728 | 177.894 | 13.971 | 13.971 | 13.971 | 10.965 | 188.859 | 2.863 | 99% |
97% March - 2019 |
Main building, basement, residential building in finishing stage. Developmental work in progress. Rs. 2.9 m Required fopr completion |
No Image |
Domel, District Bannu | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 194.728 | 177.894 | 3.971 | 3.971 | 3.971 | 3.771 | 181.665 | 12.863 | 93% |
93% February - 2019 |
Main building, basement, residential building in finishing stage. Developmental work in progress. |
No Image |
Domel, District Bannu | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 194.728 | 177.894 | 3.971 | 3.971 | 3.971 | 3.971 | 181.865 | 12.863 | 93% |
93% January - 2019 |
Main building, basement, residential building in finishing stage. Developmental work in progress. |
No Image |
Domel, District Bannu | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.858 | 206.421 | 0 | 0 | 0 | 0 | 206.421 | 0.437 | - |
100% December - 2018 |
Completed & H/O. |
No Image |
Katlang, Mardan | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.858 | 206.421 | 0 | 0 | 0 | 0 | 206.421 | 0.437 | - |
100% November - 2018 |
Completed & H/O. |
No Image |
Katlang, Mardan | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.858 | 206.421 | 0 | 0 | 0 | 0 | 206.421 | 0.437 | - |
100% November - 2018 |
Completed & H/O. |
No Image |
Katlang, Mardan | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.858 | 206.421 | 0 | 0 | 0 | 0 | 206.421 | 0.437 | - |
100% April - 2019 |
Completed & H/O. |
No Image |
Katlang, Mardan | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.858 | 206.421 | 0 | 0 | 0 | 0 | 206.421 | 0.437 | - |
100% March - 2019 |
Completed & H/O. |
No Image |
Katlang, Mardan | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.858 | 206.421 | 0 | 0 | 0 | 0 | 206.421 | 0.437 | - |
100% March - 2019 |
Completed & H/O. |
No Image |
Katlang, Mardan | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.858 | 206.421 | 0 | 0 | 0 | 0 | 206.421 | 0.437 | - |
100% February - 2019 |
Completed & H/O. |
No Image |
Katlang, Mardan | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.858 | 206.421 | 0 | 0 | 0 | 0 | 206.421 | 0.437 | - |
100% January - 2019 |
Completed & H/O. |
No Image |
Katlang, Mardan | |||||||||||||||||||
76 (OG) |
191101-170442- Provision of Vety health facilities in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.184 | 8 | 5 | 5 | 2.5 | 2.5 | 10.5 | 28.184 | 32% |
25% December - 2020 |
9 - Units
1- completed.
4 units in finishing stage.
4 units work in progress. |
No Image |
76 (OG) |
191101-170442- Provision of Vety health facilities in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.184 | 8 | 5 | 5 | 2.5 | 2.5 | 10.5 | 28.184 | 32% |
25% December - 2020 |
9 - Units
1- completed.
4 units in finishing stage.
4 units work in progress. |
No Image |
76 (OG) |
191101-170442- Provision of Vety health facilities in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.184 | 8 | 5 | 5 | 2.5 | 2.5 | 10.5 | 28.184 | 32% |
25% October - 2020 |
9 - Units
1- completed.
4 units in finishing stage.
4 units work in progress. |
No Image |
76 (OG) |
191101-170442- Provision of Vety health facilities in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.184 | 8 | 5 | 5 | 2.5 | 2.5 | 10.5 | 28.184 | 32% |
25% September - 2020 |
9 - Units
1- completed.
4 units in finishing stage.
4 units work in progress. |
No Image |
76 (OG) |
191101-170442- Provision of Vety health facilities in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.184 | 8 | 5 | 5 | 0 | 0 | 8 | 28.184 | 32% |
19% August - 2020 |
9 - Units
1- completed.
4 units in finishing stage.
4 units work in progress. |
No Image |
76 (OG) |
191101-170442- Provision of Vety health facilities in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.184 | 8 | 5 | 5 | 5 | 5 | 13 | 28.184 | 32% |
32% May - 2021 |
10 - Units
1- completed.
4 units in finishing stage.
4 units work in progress.
01 Unit tender floated on 23.02.21 |
No Image |
1 CVD Ladnay Mady Khel Garyum? Rs: 4.798 M
2 CVD Shakhi Mar Razmak? Rs: 4.798 M
3 CVD Narmi Khel Balay Khel Shawal? Rs: 4.798 M
4 CVD Warmar Khel Madi Khel? Rs: 4.416 M
5 CVD Laka Asad Khel Dossali? Rs: 4.334 M
6 New Abadi Chag Doog? Rs: 4.416 M
7 CVD Olam Kabul Khel Shawa Garyum? Rs: 4.416 M
8 CVD Datta Khel Village Spinwam? Rs: 4.334 M
9 CVD Jalir Khushai.?. Rs: 4.334 M
10 CVD Palaseen Kot Laky Assad Khel? Rs: 4.7.900 M
| |||||||||||||||||||
76 (OG) |
191101-170442- Provision of Vety health facilities in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.184 | 8 | 5 | 5 | 5 | 5 | 13 | 28.184 | 32% |
32% April - 2021 |
10 - Units
1- completed.
4 units in finishing stage.
4 units work in progress.
01 Unit tender floated on 23.02.21 |
No Image |
1 CVD Ladnay Mady Khel Garyum? Rs: 4.798 M
2 CVD Shakhi Mar Razmak? Rs: 4.798 M
3 CVD Narmi Khel Balay Khel Shawal? Rs: 4.798 M
4 CVD Warmar Khel Madi Khel? Rs: 4.416 M
5 CVD Laka Asad Khel Dossali? Rs: 4.334 M
6 New Abadi Chag Doog? Rs: 4.416 M
7 CVD Olam Kabul Khel Shawa Garyum? Rs: 4.416 M
8 CVD Datta Khel Village Spinwam? Rs: 4.334 M
9 CVD Jalir Khushai.?. Rs: 4.334 M
10 CVD Palaseen Kot Laky Assad Khel? Rs: 4.7.900 M
| |||||||||||||||||||
76 (OG) |
191101-170442- Provision of Vety health facilities in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.184 | 8 | 5 | 5 | 5 | 5 | 13 | 28.184 | 32% |
32% March - 2021 |
10 - Units
1- completed.
4 units in finishing stage.
4 units work in progress.
01 Unit tender floated on 23.02.21 |
No Image |
1 CVD Ladnay Mady Khel Garyum? Rs: 4.798 M
2 CVD Shakhi Mar Razmak? Rs: 4.798 M
3 CVD Narmi Khel Balay Khel Shawal? Rs: 4.798 M
4 CVD Warmar Khel Madi Khel? Rs: 4.416 M
5 CVD Laka Asad Khel Dossali? Rs: 4.334 M
6 New Abadi Chag Doog? Rs: 4.416 M
7 CVD Olam Kabul Khel Shawa Garyum? Rs: 4.416 M
8 CVD Datta Khel Village Spinwam? Rs: 4.334 M
9 CVD Jalir Khushai.?. Rs: 4.334 M
10 CVD Palaseen Kot Laky Assad Khel? Rs: 4.7.900 M
| |||||||||||||||||||
76 (OG) |
191101-170442- Provision of Vety health facilities in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.184 | 8 | 5 | 5 | 5 | 5 | 13 | 28.184 | 32% |
32% February - 2021 |
10 - Units
1- completed.
4 units in finishing stage.
4 units work in progress.
01 Unit tender floated on 23.02.21 |
No Image |
1 CVD Ladnay Mady Khel Garyum? Rs: 4.798 M
2 CVD Shakhi Mar Razmak? Rs: 4.798 M
3 CVD Narmi Khel Balay Khel Shawal? Rs: 4.798 M
4 CVD Warmar Khel Madi Khel? Rs: 4.416 M
5 CVD Laka Asad Khel Dossali? Rs: 4.334 M
6 New Abadi Chag Doog? Rs: 4.416 M
7 CVD Olam Kabul Khel Shawa Garyum? Rs: 4.416 M
8 CVD Datta Khel Village Spinwam? Rs: 4.334 M
9 CVD Jalir Khushai.?. Rs: 4.334 M
10 CVD Palaseen Kot Laky Assad Khel? Rs: 4.7.900 M
| |||||||||||||||||||
76 (OG) |
191101-170442- Provision of Vety health facilities in District North Waziristan. [MA] |
North Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.184 | 8 | 5 | 5 | 5 | 2.5 | 10.5 | 28.184 | 32% |
25% January - 2021 |
10 - Units
1- completed.
4 units in finishing stage.
4 units work in progress.
01 Unit tender floated on 23.02.21 |
No Image |
1 CVD Ladnay Mady Khel Garyum? Rs: 4.798 M
2 CVD Shakhi Mar Razmak? Rs: 4.798 M
3 CVD Narmi Khel Balay Khel Shawal? Rs: 4.798 M
4 CVD Warmar Khel Madi Khel? Rs: 4.416 M
5 CVD Laka Asad Khel Dossali? Rs: 4.334 M
6 New Abadi Chag Doog? Rs: 4.416 M
7 CVD Olam Kabul Khel Shawa Garyum? Rs: 4.416 M
8 CVD Datta Khel Village Spinwam? Rs: 4.334 M
9 CVD Jalir Khushai.?. Rs: 4.334 M
10 CVD Palaseen Kot Laky Assad Khel? Rs: 4.7.900 M
| |||||||||||||||||||
76 (OG) |
191101-170442- Provision of Vety health facilities in District North Waziristan. [MA] |
North Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 41.184 | 8 | 5 | 0 | 0 | 0 | 8 | 28.184 | 32% |
19% July - 2020 |
9 - Units
1- completed.
4 units in finishing stage.
4 units work in progress. |
No Image |
76 (OG) |
90444-Creation of CSR/MRS Cell in C&W Department. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 67.44 | 37.03 | 10 | 10 | 5 | 0 | 37.03 | 20.41 | 70% |
55% September - 2018 |
LOA issued to Techno Legal Consultants on 14/03/2018. |
No Image |
CSR/MRS Cell | |||||||||||||||||||
76 (OG) |
90444-Creation of CSR/MRS Cell in C&W Department. |
Peshawar |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 67.44 | 37.03 | 10 | 10 | 5 | 0 | 37.03 | 20.41 | 70% |
55% July - 2018 |
LOA issued to Techno Legal Consultants on 14/03/2018. |
No Image |
CSR/MRS Cell | |||||||||||||||||||
76 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 139.435 | 20 | 15 | 15 | 0 | 139.435 | 40.816 | 80% |
70% December - 2019 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Pre-qualification cancelled. Re-called on 12/03/2019. Revised PC-I/DCE submitted to P&D on MRS 2019. |
No Image |
Peshawar (Lab Equipments 7 Nos / Main Lab civil work) | |||||||||||||||||||
76 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 139.435 | 20 | 15 | 0 | 0 | 139.435 | 40.816 | 80% |
70% November - 2019 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Pre-qualification cancelled. Re-called on 12/03/2019. Revised PC-I/DCE submitted to P&D on MRS 2019. |
No Image |
Peshawar (Lab Equipments 7 Nos / Main Lab civil work) | |||||||||||||||||||
76 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 139.435 | 20 | 20 | 5 | 0 | 139.435 | 40.816 | 80% |
70% October - 2019 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Pre-qualification cancelled. Re-called on 12/03/2019. Revised PC-I/DCE submitted to P&D on MRS 2019. |
No Image |
Peshawar (Lab Equipments 7 Nos / Main Lab civil work) | |||||||||||||||||||
76 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 139.435 | 20 | 20 | 5 | 0 | 139.435 | 40.816 | 80% |
70% September - 2019 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Pre-qualification cancelled. Re-called on 12/03/2019. Revised PC-I/DCE under preparartion in MRS 2019 |
No Image |
Peshawar (Lab Equipments 7 Nos / Main Lab civil work) | |||||||||||||||||||
76 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 139.435 | 20 | 20 | 5 | 0 | 139.435 | 40.816 | 80% |
70% August - 2019 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Pre-qualification cancelled. Re-called on 12/03/2019. Revised PC-I/DCE submitted on 14/05/2019 for Rs.283.203 m. |
No Image |
Peshawar (Lab Equipments 7 Nos / Main Lab civil work) | |||||||||||||||||||
76 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 139.435 | 20 | 0 | 0 | 0 | 139.435 | 40.816 | 80% |
70% May - 2020 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Pre-qualification cancelled. Re-called on 12/03/2019. Revised PC-I/DCE submitted to P&D on MRS 2019. |
No Image |
Peshawar (Lab Equipments 7 Nos / Main Lab civil work) | |||||||||||||||||||
76 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 139.435 | 20 | 0 | 0 | 0 | 139.435 | 40.816 | 80% |
70% April - 2020 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Pre-qualification cancelled. Re-called on 12/03/2019. Revised PC-I/DCE submitted to P&D on MRS 2019. |
No Image |
Peshawar (Lab Equipments 7 Nos / Main Lab civil work) | |||||||||||||||||||
76 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 139.435 | 20 | 0 | 0 | 0 | 139.435 | 40.816 | 80% |
70% March - 2020 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Pre-qualification cancelled. Re-called on 12/03/2019. Revised PC-I/DCE submitted to P&D on MRS 2019. |
No Image |
Peshawar (Lab Equipments 7 Nos / Main Lab civil work) | |||||||||||||||||||
76 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 139.435 | 20 | 0 | 0 | 0 | 139.435 | 40.816 | 80% |
70% February - 2020 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Pre-qualification cancelled. Re-called on 12/03/2019. Revised PC-I/DCE submitted to P&D on MRS 2019. |
No Image |
Peshawar (Lab Equipments 7 Nos / Main Lab civil work) | |||||||||||||||||||
76 (OG) |
120779-Strengthening and Capacity Building of Material Testing Labs for C&W Department, Peshawar |
Peshawar PBC-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200.251 | 139.435 | 20 | 15 | 0 | 0 | 139.435 | 40.816 | 80% |
70% January - 2020 |
8 Nos vehicles, 7 lab equipments procured. Civil work in main lab completed. Pre-qualification cancelled. Re-called on 12/03/2019. Revised PC-I/DCE submitted to P&D on MRS 2019. |
No Image |
Peshawar (Lab Equipments 7 Nos / Main Lab civil work) | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 589.792 | 542.431 | 33.675 | 33.675 | 16.838 | 0 | 542.431 | 0 | - |
- December - 2018 |
Mardan: Completed & H/O.
Swabi: Main building FF, judicial lockup, cafetaria in progress. Occupied by FWO. Work has been stopped.
Bannu: Main building, basement, residential building in finishing stage. Developmental work in progress. |
No Image |
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 589.792 | 542.431 | 33.675 | 33.675 | 16.838 | 0 | 542.431 | 0 | - |
- November - 2018 |
Mardan: Completed & H/O.
Swabi: Main building FF, judicial lockup, cafetaria in progress. Occupied by FWO. Work has been stopped.
Bannu: Main building, basement, residential building in finishing stage. Developmental work in progress. |
No Image |
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 589.792 | 542.431 | 33.675 | 33.675 | 16.838 | 0 | 542.431 | 0 | - |
- November - 2018 |
Mardan: Completed & H/O.
Swabi: Main building FF, judicial lockup, cafetaria in progress. Occupied by FWO. Work has been stopped.
Bannu: Main building, basement, residential building in finishing stage. Developmental work in progress. |
No Image |
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 589.792 | 542.431 | 33.675 | 24.808 | 24.808 | 0 | 542.431 | 0 | - |
- April - 2019 |
Mardan: Completed & H/O.
Swabi: Main building FF, judicial lockup, cafetaria in progress. Cannopt be completd due to revision.
Bannu: Main building, basement, residential building in finishing stage. Developmental work in progress. |
No Image |
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 589.792 | 542.431 | 33.675 | 24.808 | 24.808 | 0 | 542.431 | 0 | - |
- March - 2019 |
Mardan: Completed & H/O.
Swabi: Main building FF, judicial lockup, cafetaria in progress. Cannopt be completd due to revision.
Bannu: Main building, basement, residential building in finishing stage. Developmental work in progress. |
No Image |
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 589.792 | 542.431 | 33.675 | 24.808 | 24.808 | 0 | 542.431 | 0 | - |
- March - 2019 |
Mardan: Completed & H/O.
Swabi: Main building FF, judicial lockup, cafetaria in progress. Cannopt be completd due to revision.
Bannu: Main building, basement, residential building in finishing stage. Developmental work in progress. |
No Image |
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 589.792 | 542.431 | 33.675 | 24.808 | 24.808 | 0 | 542.431 | 0 | - |
- February - 2019 |
Mardan: Completed & H/O.
Swabi: Main building FF, judicial lockup, cafetaria in progress. Cannopt be completd due to revision.
Bannu: Main building, basement, residential building in finishing stage. Developmental work in progress. |
No Image |
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 589.792 | 542.431 | 33.675 | 33.675 | 16.838 | 0 | 542.431 | 0 | - |
- January - 2019 |
Mardan: Completed & H/O.
Swabi: Main building FF, judicial lockup, cafetaria in progress. Occupied by FWO. Work has been stopped.
Bannu: Main building, basement, residential building in finishing stage. Developmental work in progress. |
No Image |
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.09 | 166.134 | 0 | 0 | 0 | 0 | 166.134 | 39.956 | - |
81% December - 2018 |
Main building FF, judicial lockup, cafetaria in progress. Occupied by FWO. Work has been stopped. |
No Image |
Tehsil building Rajjar Swabi | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.09 | 166.134 | 0 | 0 | 0 | 0 | 166.134 | 39.956 | - |
81% November - 2018 |
Main building FF, judicial lockup, cafetaria in progress. Occupied by FWO. Work has been stopped. |
No Image |
Tehsil building Rajjar Swabi | |||||||||||||||||||
76 (OG) |
100393-Construction of Tehsil Buildings for Rajjar Swabi, Katlang Mardan and Domel Bannu. |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.09 | 166.134 | 0 | 0 | 0 | 0 | 166.134 | 39.956 | - |
81% November - 2018 |
Main building FF, judicial lockup, cafetaria in progress. Occupied by FWO. Work has been stopped. |
No Image |
Tehsil building Rajjar Swabi | |||||||||||||||||||