Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
779 (OG) |
170667-Construction & Black Topping of Road from Barara Mera Khel Hamedi Road Hassan Khel to Khujari (3.9 Km) Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 47.065 | 0 | 47.064 | 44.711 | 21.179 | 0 | 0 | 0.001 | 100% |
- December - 2018 |
Tender floated on 24/10/2018. Summary under process. |
No Image |
PK-73, Bannu | |||||||||||||||||||
779 (OG) |
170667-Construction & Black Topping of Road from Barara Mera Khel Hamedi Road Hassan Khel to Khujari (3.9 Km) Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 47.065 | 0 | 47.064 | 44.711 | 21.179 | 0 | 0 | 0.001 | 100% |
- November - 2018 |
Tender floated on 24/10/2018.
Summary under process. |
No Image |
PK-73, Bannu | |||||||||||||||||||
779 (OG) |
170667-Construction & Black Topping of Road from Barara Mera Khel Hamedi Road Hassan Khel to Khujari (3.9 Km) Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 47.065 | 0 | 47.064 | 44.711 | 21.179 | 0 | 0 | 0.001 | 100% |
- November - 2018 |
Tender floated on 24/10/2018.
Summary under process. |
No Image |
PK-73, Bannu | |||||||||||||||||||
779 (OG) |
170667-Construction & Black Topping of Road from Barara Mera Khel Hamedi Road Hassan Khel to Khujari (3.9 Km) Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 47.065 | 0 | 47.064 | 41.871 | 41.871 | 0 | 0 | 0.001 | 100% |
- April - 2019 |
Re-tendered. Site disputed. Revised PC-I/DCE under preparation based on CMD. |
No Image |
PK-73, Bannu | |||||||||||||||||||
779 (OG) |
170667-Construction & Black Topping of Road from Barara Mera Khel Hamedi Road Hassan Khel to Khujari (3.9 Km) Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 47.065 | 0 | 47.064 | 44.7108 | 44.7113 | 0 | 0 | 0.001 | 100% |
- March - 2019 |
Re-tendered. Site disputed. Revised PC-I/DCE under preparation based on CMD |
No Image |
PK-73, Bannu | |||||||||||||||||||
779 (OG) |
170667-Construction & Black Topping of Road from Barara Mera Khel Hamedi Road Hassan Khel to Khujari (3.9 Km) Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 47.065 | 0 | 47.064 | 44.7108 | 44.7113 | 0 | 0 | 0.001 | 100% |
- March - 2019 |
Re-tendered. Site disputed. Revised PC-I/DCE under preparation based on CMD |
No Image |
PK-73, Bannu | |||||||||||||||||||
779 (OG) |
170667-Construction & Black Topping of Road from Barara Mera Khel Hamedi Road Hassan Khel to Khujari (3.9 Km) Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 47.065 | 0 | 47.064 | 44.7108 | 44.7113 | 0 | 0 | 0.001 | 100% |
- February - 2019 |
Re- Tendered. Site disputed. |
No Image |
PK-73, Bannu | |||||||||||||||||||
779 (OG) |
170667-Construction & Black Topping of Road from Barara Mera Khel Hamedi Road Hassan Khel to Khujari (3.9 Km) Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 47.065 | 0 | 47.064 | 44.711 | 21.179 | 0 | 0 | 0.001 | 100% |
- January - 2019 |
Re- Tendered. Site disputed. |
No Image |
PK-73, Bannu | |||||||||||||||||||
779 (OG) |
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 103.114 | 20.751 | 20.751 | 20.751 | 10.376 | 113.49 | 26.135 | 83% |
76% September - 2018 |
Length 5 Km - 4 Km BT completed. Work order issued for new work 3 Km. Work in progress on the revsied scope of work. |
No Image |
Dir Upper (5 Km) | |||||||||||||||||||
779 (OG) |
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 103.114 | 20.751 | 20.751 | 10.376 | 0 | 103.114 | 26.135 | 83% |
69% July - 2018 |
Length 5 Km - 4 Km BT completed. Work order issued for new work 3 Km. Cannot be completed because of the work in progress on the revsied scope of work. |
No Image |
Dir Upper (5 Km) | |||||||||||||||||||
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Nowshera |
20-08-15 | 30-06-18 | - | 22-01-15 | - | 28 | 16.477 | 0 | 0 | 0 | 0 | 16.477 | 11.523 | - |
59% December - 2017 |
Work completed on reduced scope (4 components). |
No Image |
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Nowshera |
20-08-15 | 30-06-18 | - | 22-01-15 | - | 28 | 16.477 | 0 | 0 | 0 | 0 | 16.477 | 11.523 | - |
59% September - 2017 |
Work completed on reduced scope. |
No Image |
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Nowshera |
20-08-15 | 30-06-18 | - | 22-01-15 | - | 28 | 16.477 | 0 | 0 | 0 | 0 | 16.477 | 11.523 | - |
59% August - 2017 |
Work completed on reduced scope. |
No Image |
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Nowshera |
20-08-15 | 30-06-18 | - | 22-01-15 | - | 28 | 16.477 | 0 | 0 | 0 | 0 | 16.477 | 11.523 | - |
59% July - 2017 |
Work completed except building involved reconsruction for which PC-II approved. |
No Image |
779 (New) |
200200-F/S for Construction of Childern & Maternity Hospital, Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 15 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
PC-II submitted to Health deptt for Rs. 15 M |
No Image |
779 (New) |
200200-F/S for Construction of Childern & Maternity Hospital, Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 15 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
PC-II submitted to Health deptt for Rs. 15 M |
No Image |
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28 | 16.477 | 0 | 0 | 0 | 0 | 16.477 | 11.523 | - |
59% November - 2017 |
Work completed on reduced scope. |
No Image |
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28 | 16.477 | 0 | 0 | 0 | 0 | 16.477 | 11.523 | - |
59% October - 2017 |
Work completed on reduced scope. |
No Image |
779 (New) |
200200-F/S for Construction of Childern & Maternity Hospital, Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 15 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
PC-II submitted to Health deptt for Rs. 15 M |
No Image |
779 (New) |
200200-F/S for Construction of Childern & Maternity Hospital, Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 15 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
PC-II submitted to Health deptt for Rs. 15 M |
No Image |
779 (New) |
200200-F/S for Construction of Childern & Maternity Hospital, Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 15 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
PC-II submitted to Health deptt for Rs. 15 M |
No Image |
779 (New) |
200200-F/S for Construction of Childern & Maternity Hospital, Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 15 | 0 | 1 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28 | 16.477 | 0 | 0 | 0 | 0 | 16.477 | 11.523 | - |
59% June - 2018 |
Work completed on reduced scope (4 components). |
No Image |
GCT Nowshera PK-14 | |||||||||||||||||||
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28 | 16.477 | 0 | 0 | 0 | 0 | 16.477 | 11.523 | - |
59% May - 2018 |
Work completed on reduced scope (4 components). |
No Image |
GCT Nowshera PK-14 | |||||||||||||||||||
779 (New) |
200200-F/S for Construction of Childern & Maternity Hospital, Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 15 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
May - 2021 |
PC-II approved for Rs. 25 M. RFP called. Proposals Submitted to DST |
No Image | |
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28 | 16.477 | 0 | 0 | 0 | 0 | 16.477 | 11.523 | - |
59% April - 2018 |
Work completed on reduced scope (4 components). |
No Image |
GCT Nowshera PK-14 | |||||||||||||||||||
779 (New) |
200200-F/S for Construction of Childern & Maternity Hospital, Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 15 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
April - 2021 |
PC-II approved for Rs. 25 M. RFP called. Proposals Submitted to DST |
No Image | |
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28 | 16.477 | 0 | 0 | 0 | 0 | 16.477 | 11.523 | - |
59% March - 2018 |
Work completed on reduced scope (4 components). |
No Image |
GCT Nowshera PK-14 | |||||||||||||||||||
779 (New) |
200200-F/S for Construction of Childern & Maternity Hospital, Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 15 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
March - 2021 |
No Image | ||
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28 | 16.477 | 0 | 0 | 0 | 0 | 16.477 | 11.523 | - |
59% February - 2018 |
Work completed on reduced scope (4 components). |
No Image |
GCT Nowshera PK-14 | |||||||||||||||||||
779 (New) |
200200-F/S for Construction of Childern & Maternity Hospital, Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 15 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
February - 2021 |
No Image | ||
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 28 | 16.477 | 0 | 0 | 0 | 0 | 16.477 | 11.523 | - |
59% January - 2018 |
Work completed on reduced scope (4 components). |
No Image |
779 (New) |
200200-F/S for Construction of Childern & Maternity Hospital, Nowshera |
Nowshera |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 15 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
January - 2021 |
No Image | ||
779 (OG) |
140938-F/S, Design & Improvement/BT of Internal 16 Km Road at Kheshgi Bala and Payan, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 849.997 | 694.953 | 40.559 | 23.559 | 23.559 | 23.558219 | 718.511219 | 114.485 | 87% |
85% December - 2019 |
Original scope completed (16 Km). 1st Revised scope - work in progress. 2nd revised scope (46 Km) - WBM in progress. |
No Image |
Nowshera | |||||||||||||||||||
779 (OG) |
140938-F/S, Design & Improvement/BT of Internal 16 Km Road at Kheshgi Bala and Payan, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 849.997 | 694.953 | 40.559 | 23.419 | 3.28 | 3.28 | 698.233 | 114.485 | 87% |
82% November - 2019 |
Original scope completed (16 Km). 1st Revised scope - work in progress. 2nd revised scope (46 Km) - WBM in progress. |
No Image |
Nowshera | |||||||||||||||||||
779 (OG) |
140938-F/S, Design & Improvement/BT of Internal 16 Km Road at Kheshgi Bala and Payan, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 849.997 | 694.953 | 40.559 | 30.419 | 0.14 | 0 | 694.953 | 114.485 | 87% |
82% October - 2019 |
Original scope completed (16 Km). 1st Revised scope - work in progress. 2nd revised scope (46 Km) - WBM in progress. |
No Image |
Nowshera | |||||||||||||||||||
779 (OG) |
140938-F/S, Design & Improvement/BT of Internal 16 Km Road at Kheshgi Bala and Payan, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 849.997 | 694.953 | 40.559 | 30.419 | 0 | 0 | 694.953 | 114.485 | 87% |
82% September - 2019 |
Original scope completed (16 Km). 1st Revised scope - work in progress. 2nd revised scope (46 Km) - WBM in progress. |
No Image |
Nowshera | |||||||||||||||||||
779 (OG) |
140938-F/S, Design & Improvement/BT of Internal 16 Km Road at Kheshgi Bala and Payan, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 849.997 | 694.953 | 40.559 | 40.559 | 10.14 | 10.14 | 705.093 | 114.485 | 87% |
83% August - 2019 |
Original scope completed (16 Km). 1st Revised scope - work in progress. 2nd revised scope (46 Km) - WBM in progress. |
No Image |
Nowshera | |||||||||||||||||||
779 (OG) |
140938-F/S, Design & Improvement/BT of Internal 16 Km Road at Kheshgi Bala and Payan, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 849.997 | 694.953 | 40.559 | 53.559 | 53.559 | 53.083 | 748.036 | 114.485 | 87% |
88% May - 2020 |
Original scope completed (16 Km). 1st Revised scope - work in progress. 2nd revised scope (46 Km) - WBM in progress. |
No Image |
Nowshera | |||||||||||||||||||
779 (OG) |
140938-F/S, Design & Improvement/BT of Internal 16 Km Road at Kheshgi Bala and Payan, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 849.997 | 694.953 | 40.559 | 53.559 | 53.559 | 23.558 | 718.511 | 114.485 | 87% |
85% April - 2020 |
Original scope completed (16 Km). 1st Revised scope - work in progress. 2nd revised scope (46 Km) - WBM in progress. |
No Image |
Nowshera | |||||||||||||||||||
779 (OG) |
140938-F/S, Design & Improvement/BT of Internal 16 Km Road at Kheshgi Bala and Payan, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 849.997 | 694.953 | 40.559 | 53.559 | 53.559 | 23.558 | 718.511 | 114.485 | 87% |
85% March - 2020 |
Original scope completed (16 Km). 1st Revised scope - work in progress. 2nd revised scope (46 Km) - WBM in progress. |
No Image |
Nowshera | |||||||||||||||||||
779 (OG) |
140938-F/S, Design & Improvement/BT of Internal 16 Km Road at Kheshgi Bala and Payan, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 849.997 | 694.953 | 40.559 | 53.559 | 53.559 | 23.558 | 718.511 | 114.485 | 87% |
85% February - 2020 |
Original scope completed (16 Km). 1st Revised scope - work in progress. 2nd revised scope (46 Km) - WBM in progress. |
No Image |
Nowshera | |||||||||||||||||||
779 (OG) |
140938-F/S, Design & Improvement/BT of Internal 16 Km Road at Kheshgi Bala and Payan, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 849.997 | 694.953 | 40.559 | 23.559 | 23.559 | 23.558219 | 718.511219 | 114.485 | 87% |
85% January - 2020 |
Original scope completed (16 Km). 1st Revised scope - work in progress. 2nd revised scope (46 Km) - WBM in progress. |
No Image |
Nowshera | |||||||||||||||||||
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Peshawar BD-2 |
15-10-15 | 30-06-18 | - | 22-01-15 | - | 29.889 | 24.834 | 5.2 | 5.2 | 0 | 0 | 24.834 | 0 | 100% |
83% December - 2017 |
(Repair work) - admin block, academic block 95 % .Completed Rs.5.200 m released in FY 2015-16 could not be punched, however, reflected in ADP. |
No Image |
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 29.889 | 24.834 | 5.2 | 5.2 | 0 | 0 | 24.834 | 0 | 100% |
83% November - 2017 |
(Repair work) - admin block, academic block in progress. Rs.5.200 m released in FY 2015-16 could not be punched, however, reflected in ADP. |
No Image |
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 29.889 | 24.834 | 5.2 | 5.2 | 0 | 0 | 24.834 | 0 | 100% |
83% October - 2017 |
(Repair work) - admin block, academic block in progress. Rs.5.2 m released in FY 2015-16 could not be punched, however, reflected in ADP. |
No Image |
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Peshawar BD-2 |
15-10-15 | 30-06-18 | - | 22-01-15 | - | 29.889 | 24.834 | 5.2 | 5.2 | 0 | 0 | 24.834 | 0 | 100% |
83% September - 2017 |
(Repair work) - admin block, academic block in progress. Rs.5.2 m released in FY 2015-16 could not be punched, however, reflected in ADP. |
No Image |
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Peshawar BD-2 |
15-10-15 | 30-06-18 | - | 22-01-15 | - | 29.889 | 24.834 | 5.2 | 5.2 | 0 | 0 | 24.834 | 0 | 100% |
83% August - 2017 |
(Repair work) - admin block, academic block in progress. Rs.5.2 m released in FY 2015-16 could not be punched, however, reflected in ADP. |
No Image |
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Peshawar BD-2 |
15-10-15 | 30-06-18 | - | 22-01-15 | - | 29.889 | 24.834 | 0 | 0 | 0 | 0 | 24.834 | 5.055 | - |
83% July - 2017 |
(Repair work) - admin block, academic block in progress. Rs.5.2 m released in FY 2015-16 could not be punched, however, reflected in ADP. |
No Image |
779 (OG) |
150573-Rehabilitation of Infrastructure Facilities at GTVC (Boys) Gul Bahar Peshawar and GCT Nowshera. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 29.889 | 24.834 | 1.956 | 1.956 | 1.956 | 1.956 | 26.79 | 3.099 | 90% |
90% June - 2018 |
(Repair work) - admin block, academic block 95% completed. Rs.5.200 m released in FY 2015-16 could not be punched, however, reflected in ADP. |
No Image |
GTVC Gulbahar PK-02, Peshawar | |||||||||||||||||||
Pages : 1 2 |