Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2019, January - 2020, February - 2021, February - 2019, February - 2020, March - 2021, March - 2019, March - 2020, April - 2021, April - 2019, April - 2020, May - 2021, May - 2020, July - 2018, July - 2020, August - 2019, August - 2020, September - 2020, September - 2018, September - 2019, October - 2020, October - 2019, November - 2018, November - 2019, December - 2020, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
782
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 380.856 179.247 20 20 10 10 189.247 181.609 52% 50%
September - 2018
Length 27 Km - cutting of 27 Km completed, WB of 5 Km completed.
No Image
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km)
782
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 380.856 179.247 20 20 10 0 179.247 181.609 52% 47%
July - 2018
Length 27 Km - cutting of 27 Km completed, WB of 5 Km completed.
No Image
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km)
782
(OG)
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 390.218 278.808 25 25 25 25 303.808 86.41 78% 78%
December - 2018
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. Balance work - work order issued. Liability 20 M
No Image
Karak
782
(OG)
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 390.218 278.808 25 25 25 23.817 302.625 86.41 78% 78%
November - 2018
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. Balance work - work order issued.
No Image
Karak
782
(OG)
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 390.218 278.808 25 25 25 23.817 302.625 86.41 78% 78%
November - 2018
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. Balance work - work order issued.
No Image
Karak
782
(OG)
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 390.218 278.808 25 25 25 25 303.808 86.41 78% 78%
April - 2019
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. Liability Rs.40 m.
No Image
Karak
782
(OG)
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 390.218 278.808 25 25 25 25 303.808 86.41 78% 78%
March - 2019
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. Liability Rs.40 m.
No Image
Karak
782
(OG)
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 390.218 278.808 25 25 25 25 303.808 86.41 78% 78%
March - 2019
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. Liability Rs.40 m.
No Image
Karak
782
(OG)
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 390.218 278.808 25 25 25 25 303.808 86.41 78% 78%
February - 2019
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. Liability Rs.40 m.
No Image
Karak
782
(OG)
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km).
Karak
30-11--1 30-11--1 - 30-11--1 - 390.218 278.808 25 25 25 25 303.808 86.41 78% 78%
January - 2019
Length 4.225 Km (width 40 ft) - 3.2 Km both lane BT completed. Balance work - work order issued. Liability Rs.40 m.
No Image
Karak
782
(OG)
140992-F/S, Design and Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 146.444 30 30 30 30 176.444 23.556 88% 88%
December - 2019
Length 8.3 Km - 8.3 Km completed. Summary approved. Balance work (2.5 Km road) - WBM completed. Asphaltic wering course in progress.
No Image
Nowshera
782
(OG)
140992-F/S, Design and Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 146.444 30 30 15 15 161.444 23.556 88% 81%
November - 2019
Length 8.3 Km - 8.3 Km completed. Summary approved. Balance work (2.5 Km road) - WBM completed. Asphaltic wering course in progress.
No Image
Nowshera
782
(OG)
140992-F/S, Design and Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 146.444 30 30 7.5 7.5 153.944 23.556 88% 77%
October - 2019
Length 8.3 Km - 8.3 Km completed. Summary approved. Balance work (2.5 Km road) - WBM completed. Asphaltic wering course in progress.
No Image
Nowshera
782
(OG)
140992-F/S, Design and Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 146.444 30 30 7.5 7.5 153.944 23.556 88% 77%
September - 2019
Length 8.3 Km - 8.3 Km completed. Summary approved. Balance work (2.5 Km road) - WBM completed. Asphaltic wering course in progress.
No Image
Nowshera
782
(OG)
140992-F/S, Design and Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 146.444 30 30 7.5 0 146.444 23.556 88% 73%
August - 2019
Length 8.3 Km - 8.3 Km completed. Summary approved. Balance work (2.5 Km road) - WBM completed. Asphaltic wering course in progress.
No Image
Nowshera
782
(OG)
140992-F/S, Design and Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 146.444 30 30 30 30 176.444 23.556 88% 88%
May - 2020
Length 8.3 Km - 8.3 Km completed. Summary approved. Balance work (2.5 Km road) - WBM completed. Asphaltic wering course in progress.
No Image
Nowshera
782
(OG)
140992-F/S, Design and Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 146.444 30 30 30 30 176.444 23.556 88% 88%
April - 2020
Length 8.3 Km - 8.3 Km completed. Summary approved. Balance work (2.5 Km road) - WBM completed. Asphaltic wering course in progress.
No Image
Nowshera
782
(OG)
140992-F/S, Design and Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 146.444 30 30 30 30 176.444 23.556 88% 88%
March - 2020
Length 8.3 Km - 8.3 Km completed. Summary approved. Balance work (2.5 Km road) - WBM completed. Asphaltic wering course in progress.
No Image
Nowshera
782
(OG)
140992-F/S, Design and Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 146.444 30 30 30 30 176.444 23.556 88% 88%
February - 2020
Length 8.3 Km - 8.3 Km completed. Summary approved. Balance work (2.5 Km road) - WBM completed. Asphaltic wering course in progress.
No Image
Nowshera
782
(OG)
140992-F/S, Design and Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar Akora Khattak, Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 200 146.444 30 30 30 30 176.444 23.556 88% 88%
January - 2020
Length 8.3 Km - 8.3 Km completed. Summary approved. Balance work (2.5 Km road) - WBM completed. Asphaltic wering course in progress.
No Image
Nowshera
782
(New)
190418-Re-Construction of Barikot Hospital and Upgradation of RHC Chuprial into Category-D Hospital Swat
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 526.033 0 50 50 25 0 0 476.033 10% -
December - 2020
work order issued
No Image
782
(New)
190418-Re-Construction of Barikot Hospital and Upgradation of RHC Chuprial into Category-D Hospital Swat
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 526.033 0 50 50 25 0 0 476.033 10% -
December - 2020
work order issued
No Image
782
(New)
190418-Re-Construction of Barikot Hospital and Upgradation of RHC Chuprial into Category-D Hospital Swat
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 516 0 50 50 0 0 0 0 - -
October - 2020
approved for Rs. 516 m . AA Awaited
No Image
782
(New)
190418-Re-Construction of Barikot Hospital and Upgradation of RHC Chuprial into Category-D Hospital Swat
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 516 0 50 50 0 0 0 0 - -
September - 2020
approved for Rs. 516 m . AA Awaited
No Image
782
(New)
190418-Re-Construction of Barikot Hospital and Upgradation of RHC Chuprial into Category-D Hospital Swat
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 516 0 50 50 0 0 0 0 - -
August - 2020
PC-I submitted
No Image
782
(New)
190418-Re-Construction of Barikot Hospital and Upgradation of RHC Chuprial into Category-D Hospital Swat
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 516 0 50 0 0 0 0 0 - -
July - 2020
Consultant selected. PC-I submitted
No Image
782
(New)
190418-Re-Construction of Barikot Hospital and Upgradation of RHC Chuprial into Category-D Hospital Swat
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 526.033 0 50 95 95 30 30 476.033 10% 6%
May - 2021
Layout given
No Image
Upgradation of RHC Chuprial into Category-D Hospital Swat
782
(New)
190418-Re-Construction of Barikot Hospital and Upgradation of RHC Chuprial into Category-D Hospital Swat
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 526.033 0 50 95 95 30 30 476.033 10% 6%
April - 2021
Layout given
No Image
Upgradation of RHC Chuprial into Category-D Hospital Swat
782
(New)
190418-Re-Construction of Barikot Hospital and Upgradation of RHC Chuprial into Category-D Hospital Swat
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 526.033 0 50 95 95 30 30 476.033 10% 6%
March - 2021
Layout given
No Image
Upgradation of RHC Chuprial into Category-D Hospital Swat
782
(New)
190418-Re-Construction of Barikot Hospital and Upgradation of RHC Chuprial into Category-D Hospital Swat
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 526.033 0 50 45 45 30 30 476.033 10% 6%
February - 2021
Layout given
No Image
Upgradation of RHC Chuprial into Category-D Hospital Swat
782
(New)
190418-Re-Construction of Barikot Hospital and Upgradation of RHC Chuprial into Category-D Hospital Swat
Swat
30-11--1 30-11--1 - 30-11--1 Line Deptt 526.033 0 50 30 30 30 30 476.033 10% 6%
January - 2021
work started
No Image
Upgradation of RHC Chuprial into Category-D Hospital Swat
Pages : 1