Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
793 (OG) |
70190-Establishment of Bannu Medical College, Bannu. (Phase-II) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 827.429 | 40 | 40 | 20 | 16.641 | 844.07 | 49.888 | 95% |
92% December - 2020 |
Academic/admin block, cafetaria, library, mosque In progress. |
No Image |
Bannu | |||||||||||||||||||
793 (OG) |
70190-Establishment of Bannu Medical College, Bannu. (Phase-II) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 827.429 | 40 | 40 | 20 | 16.641 | 844.07 | 49.888 | 95% |
92% December - 2020 |
Academic/admin block, cafetaria, library, mosque In progress. |
No Image |
Bannu | |||||||||||||||||||
793 (OG) |
70190-Establishment of Bannu Medical College, Bannu. (Phase-II) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 827.429 | 80 | 80 | 20 | 13 | 840.429 | 9.888 | 99% |
92% October - 2020 |
Academic/admin block, cafetaria, library, mosque In progress. |
No Image |
Bannu | |||||||||||||||||||
793 (OG) |
70190-Establishment of Bannu Medical College, Bannu. (Phase-II) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 827.429 | 80 | 80 | 20 | 13 | 840.429 | 9.888 | 99% |
92% September - 2020 |
Academic/admin block, cafetaria, library, mosque In progress. |
No Image |
Bannu | |||||||||||||||||||
793 (OG) |
70190-Establishment of Bannu Medical College, Bannu. (Phase-II) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 827.429 | 80 | 80 | 20 | 7.4 | 834.829 | 9.888 | 99% |
91% August - 2020 |
Academic/admin block, cafetaria, library, mosque In progress. |
No Image |
Bannu | |||||||||||||||||||
793 (OG) |
70190-Establishment of Bannu Medical College, Bannu. (Phase-II) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 827.429 | 80 | 0 | 0 | 0 | 827.429 | 9.888 | 99% |
90% July - 2020 |
Academic/admin block, cafetaria, library, mosque i |
No Image |
Bannu | |||||||||||||||||||
793 (OG) |
70190-Establishment of Bannu Medical College, Bannu. (Phase-II) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 810.014 | 80 | 70 | 70 | 60 | 870.014 | 27.303 | 97% |
95% May - 2021 |
01-Unit
1. Academic/admin block, cafetaria, library, mosque In progress.
2. Admin Block-I Completed, Block-II & III 75 % |
No Image |
Scope of work:
Package-I
Package-II
| |||||||||||||||||||
793 (OG) |
70190-Establishment of Bannu Medical College, Bannu. (Phase-II) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 810.014 | 80 | 60 | 60 | 60 | 870.014 | 27.303 | 97% |
95% April - 2021 |
Academic/admin block, cafetaria, library, mosque In progress. |
No Image |
Bannu | |||||||||||||||||||
793 (OG) |
70190-Establishment of Bannu Medical College, Bannu. (Phase-II) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 810.014 | 80 | 60 | 60 | 60 | 870.014 | 27.303 | 97% |
95% March - 2021 |
Academic/admin block, cafetaria, library, mosque In progress. |
No Image |
Bannu | |||||||||||||||||||
793 (OG) |
70190-Establishment of Bannu Medical College, Bannu. (Phase-II) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 810.014 | 80 | 60 | 60 | 60 | 870.014 | 27.303 | 97% |
95% February - 2021 |
Academic/admin block, cafetaria, library, mosque In progress. |
No Image |
Bannu | |||||||||||||||||||
793 (OG) |
70190-Establishment of Bannu Medical College, Bannu. (Phase-II) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 917.317 | 827.429 | 80 | 70 | 70 | 28.753 | 856.182 | 9.888 | 99% |
93% January - 2021 |
Academic/admin block, cafetaria, library, mosque In progress. |
No Image |
Bannu | |||||||||||||||||||
793 (OG) |
150824-Construction / rehabilitation / widening / completion of incomplete Molkoh road, Boni bridge to Boni Bazar via Bazar to Government Guest House in Tehsil Mastuj District Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 125.302 | 37.787 | 10 | 10 | 5 | 5 | 42.787 | 77.515 | 38% |
34% September - 2018 |
3 units - 1 completed, 2 in progress. |
No Image |
1) Construction of incomplete Mulkow road
2) Boni Bridge to Boni Bazar Chowk
3) Boni Bazar Chowk to Govt Rest House road | |||||||||||||||||||
793 (OG) |
150824-Construction / rehabilitation / widening / completion of incomplete Molkoh road, Boni bridge to Boni Bazar via Bazar to Government Guest House in Tehsil Mastuj District Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 125.302 | 37.787 | 10 | 10 | 5 | 0 | 37.787 | 77.515 | 38% |
30% July - 2018 |
3 units - 1 completed, 2 in progress. |
No Image |
1) Construction of incomplete Mulkow road
2) Boni Bridge to Boni Bazar Chowk
3) Boni Bazar Chowk to Govt Rest House road | |||||||||||||||||||
793 (OG) |
140308-F/S and Construction of Judicial Complex, DI.Khan. |
D.I.Khan |
04-04-16 | - | - | 03-09-15 | - | 976 | 205.09 | 20 | 50 | 50 | 50 | 255.09 | 750.91 | 23% |
26% December - 2017 |
GF/FF - roof laid. 2nd floor roofing in progress. |
No Image |
793 (OG) |
140308-F/S and Construction of Judicial Complex, DI.Khan. |
D.I.Khan |
04-04-16 | - | - | 03-09-15 | - | 976 | 205.09 | 20 | 50 | 50 | 20 | 225.09 | 750.91 | 23% |
23% September - 2017 |
GF/FF - roof laid. 2nd floor roofing in progress. |
No Image |
793 (OG) |
140308-F/S and Construction of Judicial Complex, DI.Khan. |
D.I.Khan |
04-04-16 | - | - | 03-09-15 | - | 976 | 205.09 | 20 | 20 | 20 | 0 | 205.09 | 750.91 | 23% |
21% August - 2017 |
GF - basement completed, FF in progress. |
No Image |
793 (OG) |
140308-F/S and Construction of Judicial Complex, DI.Khan. |
D.I.Khan |
04-04-16 | - | - | 03-09-15 | - | 976 | 205.09 | 20 | 20 | 0 | 0 | 205.09 | 750.91 | 23% |
21% July - 2017 |
GF - basement completed, FF in progress. |
No Image |
793 (OG) |
140308-F/S and Construction of Judicial Complex, DI.Khan. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 976 | 205.09 | 20 | 50 | 50 | 48.664 | 253.754 | 750.91 | 23% |
26% November - 2017 |
GF/FF - roof laid. 2nd floor roofing in progress. |
No Image |
793 (OG) |
140308-F/S and Construction of Judicial Complex, DI.Khan. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 976 | 205.09 | 20 | 50 | 50 | 50 | 255.09 | 750.91 | 23% |
26% October - 2017 |
GF/FF - roof laid. 2nd floor roofing in progress. |
No Image |
793 (OG) |
140308-F/S and Construction of Judicial Complex, DI.Khan. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 976 | 205.09 | 20 | 90 | 90 | 90 | 295.09 | 750.91 | 23% |
30% June - 2018 |
Main building - plastering in progress. |
No Image |
DI.Khan | |||||||||||||||||||
793 (OG) |
140308-F/S and Construction of Judicial Complex, DI.Khan. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 976 | 205.09 | 20 | 90 | 90 | 87.596 | 292.686 | 750.91 | 23% |
30% May - 2018 |
Main building - plastering in progress. Demand Rs.60 m. |
No Image |
DI.Khan | |||||||||||||||||||
793 (OG) |
140308-F/S and Construction of Judicial Complex, DI.Khan. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 976 | 205.09 | 20 | 80 | 80 | 80 | 285.09 | 750.91 | 23% |
29% April - 2018 |
Main building - plastering in progress. Demand Rs.60 m. |
No Image |
DI.Khan | |||||||||||||||||||
793 (OG) |
140308-F/S and Construction of Judicial Complex, DI.Khan. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 976 | 205.09 | 20 | 80 | 80 | 80 | 285.09 | 750.91 | 23% |
29% March - 2018 |
Main building - plastering in progress. Demand Rs. 60 m. |
No Image |
DI.Khan | |||||||||||||||||||
793 (OG) |
140308-F/S and Construction of Judicial Complex, DI.Khan. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 976 | 205.09 | 20 | 80 | 80 | 80 | 285.09 | 750.91 | 23% |
29% February - 2018 |
Main building - plastering in progress. Demand Rs. 30 m |
ADP's Images |
DI.Khan | |||||||||||||||||||
793 (OG) |
140308-F/S and Construction of Judicial Complex, DI.Khan. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 976 | 205.09 | 20 | 80 | 80 | 80 | 285.09 | 750.91 | 23% |
29% January - 2018 |
Main building - plastering in progress. |
No Image |
793 (OG) |
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 64.433 | 10 | 13.784 | 11.62 | 11.621 | 76.054 | 75.567 | 50% |
51% December - 2018 |
4 units - 1.5 Km BT completed. WBM in progress. |
No Image |
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km - 12 ft) | |||||||||||||||||||
793 (OG) |
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 64.433 | 10 | 9.784 | 7.62 | 7.62 | 72.053 | 75.567 | 50% |
48% November - 2018 |
4 units - 1.5 Km BT completed. WBM in progress. |
No Image |
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km - 12 ft) | |||||||||||||||||||
793 (OG) |
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 64.433 | 10 | 9.784 | 7.62 | 7.62 | 72.053 | 75.567 | 50% |
48% November - 2018 |
4 units - 1.5 Km BT completed. WBM in progress. |
No Image |
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km - 12 ft) | |||||||||||||||||||
793 (OG) |
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 64.433 | 10 | 13.7836 | 13.2421 | 13.242 | 77.675 | 75.567 | 50% |
52% April - 2019 |
4 units - 5.5 Km BT completed. WBM in progress. Demand Rs.20 m. |
No Image |
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km - 12 ft) | |||||||||||||||||||
793 (OG) |
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 64.433 | 10 | 13.7836 | 13.2421 | 13.242 | 77.675 | 75.567 | 50% |
52% March - 2019 |
4 units - 5.5 Km BT completed. WBM in progress. Demand Rs.20 m. |
No Image |
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km - 12 ft) | |||||||||||||||||||
793 (OG) |
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 64.433 | 10 | 13.7836 | 13.2421 | 13.242 | 77.675 | 75.567 | 50% |
52% March - 2019 |
4 units - 5.5 Km BT completed. WBM in progress. Demand Rs.20 m. |
No Image |
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km - 12 ft) | |||||||||||||||||||
793 (OG) |
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 64.433 | 10 | 13.7836 | 13.2421 | 12.702 | 77.135 | 75.567 | 50% |
51% February - 2019 |
4 units - 5.5 Km BT completed. WBM in progress. Demand Rs.20 m. |
No Image |
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km - 12 ft) | |||||||||||||||||||
793 (OG) |
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 64.433 | 10 | 13.784 | 12.701 | 11.524 | 75.957 | 75.567 | 50% |
51% January - 2019 |
4 units - 5.5 Km BT completed. WBM in progress. Demand Rs. 20 M |
No Image |
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km - 12 ft) | |||||||||||||||||||
793 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 75 | 25 | 25 | 25 | 20.756827 | 95.756827 | 50 | 67% |
64% December - 2019 |
7 Km - 7 km asphalt completed. |
No Image |
Nowshera | |||||||||||||||||||
793 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 75 | 25 | 25 | 12.5 | 12.5 | 87.5 | 50 | 67% |
58% November - 2019 |
7 Km - 4 km asphalt completed. |
No Image |
Nowshera | |||||||||||||||||||
793 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 75 | 25 | 25 | 6.25 | 6.25 | 81.25 | 50 | 67% |
54% October - 2019 |
7 Km - 4 km asphalt completed. |
No Image |
Nowshera | |||||||||||||||||||
793 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 75 | 25 | 25 | 6.25 | 6.25 | 81.25 | 50 | 67% |
54% September - 2019 |
7 Km - 4 km asphalt completed. |
No Image |
Nowshera | |||||||||||||||||||
793 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 75 | 25 | 25 | 6.25 | 6.25 | 81.25 | 50 | 67% |
54% August - 2019 |
7 Km - 4 km asphalt completed. |
No Image |
Nowshera | |||||||||||||||||||
793 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 75 | 25 | 25 | 25 | 25 | 100 | 50 | 67% |
67% May - 2020 |
7 Km - 7 km asphalt completed. |
No Image |
Nowshera | |||||||||||||||||||
793 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 75 | 25 | 25 | 25 | 25 | 100 | 50 | 67% |
67% April - 2020 |
7 Km - 7 km asphalt completed. |
No Image |
Nowshera | |||||||||||||||||||
793 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 75 | 25 | 25 | 25 | 25 | 100 | 50 | 67% |
67% March - 2020 |
7 Km - 7 km asphalt completed. |
No Image |
Nowshera | |||||||||||||||||||
793 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 75 | 25 | 25 | 25 | 25 | 100 | 50 | 67% |
67% February - 2020 |
7 Km - 7 km asphalt completed. |
No Image |
Nowshera | |||||||||||||||||||
793 (OG) |
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 75 | 25 | 25 | 25 | 25 | 100 | 50 | 67% |
67% January - 2020 |
7 Km - 7 km asphalt completed. |
No Image |
Nowshera | |||||||||||||||||||
Pages : 1 |