Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, January - 2019, February - 2020, February - 2021, February - 2018, February - 2019, March - 2020, March - 2021, March - 2018, March - 2019, April - 2020, April - 2021, April - 2018, April - 2019, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, July - 2018, August - 2020, August - 2017, August - 2019, September - 2020, September - 2017, September - 2018, September - 2019, October - 2020, October - 2017, October - 2019, November - 2019, November - 2017, November - 2018, December - 2020, December - 2017, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
793
(OG)
70190-Establishment of Bannu Medical College, Bannu. (Phase-II)
Bannu
30-11--1 30-11--1 - 30-11--1 - 917.317 827.429 40 40 20 16.641 844.07 49.888 95% 92%
December - 2020
Academic/admin block, cafetaria, library, mosque In progress.
No Image
Bannu
793
(OG)
70190-Establishment of Bannu Medical College, Bannu. (Phase-II)
Bannu
30-11--1 30-11--1 - 30-11--1 - 917.317 827.429 40 40 20 16.641 844.07 49.888 95% 92%
December - 2020
Academic/admin block, cafetaria, library, mosque In progress.
No Image
Bannu
793
(OG)
70190-Establishment of Bannu Medical College, Bannu. (Phase-II)
Bannu
30-11--1 30-11--1 - 30-11--1 - 917.317 827.429 80 80 20 13 840.429 9.888 99% 92%
October - 2020
Academic/admin block, cafetaria, library, mosque In progress.
No Image
Bannu
793
(OG)
70190-Establishment of Bannu Medical College, Bannu. (Phase-II)
Bannu
30-11--1 30-11--1 - 30-11--1 - 917.317 827.429 80 80 20 13 840.429 9.888 99% 92%
September - 2020
Academic/admin block, cafetaria, library, mosque In progress.
No Image
Bannu
793
(OG)
70190-Establishment of Bannu Medical College, Bannu. (Phase-II)
Bannu
30-11--1 30-11--1 - 30-11--1 - 917.317 827.429 80 80 20 7.4 834.829 9.888 99% 91%
August - 2020
Academic/admin block, cafetaria, library, mosque In progress.
No Image
Bannu
793
(OG)
70190-Establishment of Bannu Medical College, Bannu. (Phase-II)
Bannu
30-11--1 30-11--1 - 30-11--1 - 917.317 827.429 80 0 0 0 827.429 9.888 99% 90%
July - 2020
Academic/admin block, cafetaria, library, mosque i
No Image
Bannu
793
(OG)
70190-Establishment of Bannu Medical College, Bannu. (Phase-II)
Bannu
30-11--1 30-11--1 - 30-11--1 - 917.317 810.014 80 70 70 60 870.014 27.303 97% 95%
May - 2021
01-Unit 1. Academic/admin block, cafetaria, library, mosque In progress. 2. Admin Block-I Completed, Block-II & III 75 %
No Image
Scope of work:
 
Package-I
  • Academic Block, A,B&C BCL
  • Admin Block I,II & III Chaman
  • Cafeteria Chaman
  • Library Chaman
Package-II
  • Mosque
  • Police Post
  • Maintencance Staff Housing
  • Sub Stataion
  • Ground & O.H.T
  • Watch Tower
  • Roads & walk Ways
  • Compound wall
793
(OG)
70190-Establishment of Bannu Medical College, Bannu. (Phase-II)
Bannu
30-11--1 30-11--1 - 30-11--1 - 917.317 810.014 80 60 60 60 870.014 27.303 97% 95%
April - 2021
Academic/admin block, cafetaria, library, mosque In progress.
No Image
Bannu
793
(OG)
70190-Establishment of Bannu Medical College, Bannu. (Phase-II)
Bannu
30-11--1 30-11--1 - 30-11--1 - 917.317 810.014 80 60 60 60 870.014 27.303 97% 95%
March - 2021
Academic/admin block, cafetaria, library, mosque In progress.
No Image
Bannu
793
(OG)
70190-Establishment of Bannu Medical College, Bannu. (Phase-II)
Bannu
30-11--1 30-11--1 - 30-11--1 - 917.317 810.014 80 60 60 60 870.014 27.303 97% 95%
February - 2021
Academic/admin block, cafetaria, library, mosque In progress.
No Image
Bannu
793
(OG)
70190-Establishment of Bannu Medical College, Bannu. (Phase-II)
Bannu
30-11--1 30-11--1 - 30-11--1 - 917.317 827.429 80 70 70 28.753 856.182 9.888 99% 93%
January - 2021
Academic/admin block, cafetaria, library, mosque In progress.
No Image
Bannu
793
(OG)
150824-Construction / rehabilitation / widening / completion of incomplete Molkoh road, Boni bridge to Boni Bazar via Bazar to Government Guest House in Tehsil Mastuj District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 125.302 37.787 10 10 5 5 42.787 77.515 38% 34%
September - 2018
3 units - 1 completed, 2 in progress.
No Image
1) Construction of incomplete Mulkow road
2) Boni Bridge to Boni Bazar Chowk
3) Boni Bazar Chowk to Govt Rest House road
793
(OG)
150824-Construction / rehabilitation / widening / completion of incomplete Molkoh road, Boni bridge to Boni Bazar via Bazar to Government Guest House in Tehsil Mastuj District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 125.302 37.787 10 10 5 0 37.787 77.515 38% 30%
July - 2018
3 units - 1 completed, 2 in progress.
No Image
1) Construction of incomplete Mulkow road
2) Boni Bridge to Boni Bazar Chowk
3) Boni Bazar Chowk to Govt Rest House road
793
(OG)
140308-F/S and Construction of Judicial Complex, DI.Khan.
D.I.Khan
04-04-16 - - 03-09-15 - 976 205.09 20 50 50 50 255.09 750.91 23% 26%
December - 2017
GF/FF - roof laid. 2nd floor roofing in progress.
No Image
793
(OG)
140308-F/S and Construction of Judicial Complex, DI.Khan.
D.I.Khan
04-04-16 - - 03-09-15 - 976 205.09 20 50 50 20 225.09 750.91 23% 23%
September - 2017
GF/FF - roof laid. 2nd floor roofing in progress.
No Image
793
(OG)
140308-F/S and Construction of Judicial Complex, DI.Khan.
D.I.Khan
04-04-16 - - 03-09-15 - 976 205.09 20 20 20 0 205.09 750.91 23% 21%
August - 2017
GF - basement completed, FF in progress.
No Image
793
(OG)
140308-F/S and Construction of Judicial Complex, DI.Khan.
D.I.Khan
04-04-16 - - 03-09-15 - 976 205.09 20 20 0 0 205.09 750.91 23% 21%
July - 2017
GF - basement completed, FF in progress.
No Image
793
(OG)
140308-F/S and Construction of Judicial Complex, DI.Khan.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 976 205.09 20 50 50 48.664 253.754 750.91 23% 26%
November - 2017
GF/FF - roof laid. 2nd floor roofing in progress.
No Image
793
(OG)
140308-F/S and Construction of Judicial Complex, DI.Khan.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 976 205.09 20 50 50 50 255.09 750.91 23% 26%
October - 2017
GF/FF - roof laid. 2nd floor roofing in progress.
No Image
793
(OG)
140308-F/S and Construction of Judicial Complex, DI.Khan.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 976 205.09 20 90 90 90 295.09 750.91 23% 30%
June - 2018
Main building - plastering in progress.
No Image
DI.Khan
793
(OG)
140308-F/S and Construction of Judicial Complex, DI.Khan.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 976 205.09 20 90 90 87.596 292.686 750.91 23% 30%
May - 2018
Main building - plastering in progress. Demand Rs.60 m.
No Image
DI.Khan
793
(OG)
140308-F/S and Construction of Judicial Complex, DI.Khan.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 976 205.09 20 80 80 80 285.09 750.91 23% 29%
April - 2018
Main building - plastering in progress. Demand Rs.60 m.
No Image
DI.Khan
793
(OG)
140308-F/S and Construction of Judicial Complex, DI.Khan.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 976 205.09 20 80 80 80 285.09 750.91 23% 29%
March - 2018
Main building - plastering in progress. Demand Rs. 60 m.
No Image
DI.Khan
793
(OG)
140308-F/S and Construction of Judicial Complex, DI.Khan.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 976 205.09 20 80 80 80 285.09 750.91 23% 29%
February - 2018
Main building - plastering in progress. Demand Rs. 30 m
ADP's Images
DI.Khan
793
(OG)
140308-F/S and Construction of Judicial Complex, DI.Khan.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 976 205.09 20 80 80 80 285.09 750.91 23% 29%
January - 2018
Main building - plastering in progress.
No Image
793
(OG)
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 150 64.433 10 13.784 11.62 11.621 76.054 75.567 50% 51%
December - 2018
4 units - 1.5 Km BT completed. WBM in progress.
No Image
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km  - 12 ft)
793
(OG)
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 150 64.433 10 9.784 7.62 7.62 72.053 75.567 50% 48%
November - 2018
4 units - 1.5 Km BT completed. WBM in progress.
No Image
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km  - 12 ft)
793
(OG)
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 150 64.433 10 9.784 7.62 7.62 72.053 75.567 50% 48%
November - 2018
4 units - 1.5 Km BT completed. WBM in progress.
No Image
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km  - 12 ft)
793
(OG)
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 150 64.433 10 13.7836 13.2421 13.242 77.675 75.567 50% 52%
April - 2019
4 units - 5.5 Km BT completed. WBM in progress. Demand Rs.20 m.
No Image
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km  - 12 ft)
793
(OG)
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 150 64.433 10 13.7836 13.2421 13.242 77.675 75.567 50% 52%
March - 2019
4 units - 5.5 Km BT completed. WBM in progress. Demand Rs.20 m.
No Image
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km  - 12 ft)
793
(OG)
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 150 64.433 10 13.7836 13.2421 13.242 77.675 75.567 50% 52%
March - 2019
4 units - 5.5 Km BT completed. WBM in progress. Demand Rs.20 m.
No Image
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km  - 12 ft)
793
(OG)
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 150 64.433 10 13.7836 13.2421 12.702 77.135 75.567 50% 51%
February - 2019
4 units - 5.5 Km BT completed. WBM in progress. Demand Rs.20 m.
No Image
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km  - 12 ft)
793
(OG)
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 - 150 64.433 10 13.784 12.701 11.524 75.957 75.567 50% 51%
January - 2019
4 units - 5.5 Km BT completed. WBM in progress. Demand Rs. 20 M
No Image
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km  - 12 ft)
793
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 75 25 25 25 20.756827 95.756827 50 67% 64%
December - 2019
7 Km - 7 km asphalt completed.
No Image
Nowshera
793
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 75 25 25 12.5 12.5 87.5 50 67% 58%
November - 2019
7 Km - 4 km asphalt completed.
No Image
Nowshera
793
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 75 25 25 6.25 6.25 81.25 50 67% 54%
October - 2019
7 Km - 4 km asphalt completed.
No Image
Nowshera
793
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 75 25 25 6.25 6.25 81.25 50 67% 54%
September - 2019
7 Km - 4 km asphalt completed.
No Image
Nowshera
793
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 75 25 25 6.25 6.25 81.25 50 67% 54%
August - 2019
7 Km - 4 km asphalt completed.
No Image
Nowshera
793
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 75 25 25 25 25 100 50 67% 67%
May - 2020
7 Km - 7 km asphalt completed.
No Image
Nowshera
793
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 75 25 25 25 25 100 50 67% 67%
April - 2020
7 Km - 7 km asphalt completed.
No Image
Nowshera
793
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 75 25 25 25 25 100 50 67% 67%
March - 2020
7 Km - 7 km asphalt completed.
No Image
Nowshera
793
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 75 25 25 25 25 100 50 67% 67%
February - 2020
7 Km - 7 km asphalt completed.
No Image
Nowshera
793
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 75 25 25 25 25 100 50 67% 67%
January - 2020
7 Km - 7 km asphalt completed.
No Image
Nowshera