Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
14-05-13 | 30-06-18 | - | 29-01-13 | - | 20 | 23.9 | 0 | 0 | 0 | 0 | 23.9 | 0 | - |
100% December - 2017 |
Completed & H/O. |
No Image |
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
14-05-13 | 30-06-18 | - | 29-01-13 | - | 20 | 23.9 | 0 | 0 | 0 | 0 | 23.9 | 0 | - |
100% September - 2017 |
Completed & H/O. |
No Image |
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
14-05-13 | 30-06-18 | - | 29-01-13 | - | 20 | 23.9 | 0 | 0 | 0 | 0 | 23.9 | 0 | - |
100% August - 2017 |
Completed & H/O. |
No Image |
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
14-05-13 | 30-06-18 | - | 29-01-13 | - | 20 | 23.9 | 0 | 0 | 0 | 0 | 23.9 | 0 | - |
100% July - 2017 |
Completed & H/O. |
No Image |
81 (New) |
180619-Construction/reconstruction of Government Accomodations at District Headquarter, Bannu |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- December - 2018 |
No Image | |
Bannu | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 23.9 | 0 | 0 | 0 | 0 | 23.9 | 0 | - |
100% November - 2017 |
Completed & H/O. |
No Image |
81 (New) |
180619-Construction/reconstruction of Government Accomodations at District Headquarter, Bannu |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
No Image | |
Bannu | |||||||||||||||||||
81 (New) |
180619-Construction/reconstruction of Government Accomodations at District Headquarter, Bannu |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 10 | 10 | 0 | 0 | 0 | 0 | - |
- November - 2018 |
No Image | |
Bannu | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 23.9 | 0 | 0 | 0 | 0 | 23.9 | 0 | - |
100% October - 2017 |
Completed & H/O. |
No Image |
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.1 | 22.9 | 0 | 0 | 0 | 0 | 22.9 | 0.2 | - |
99% June - 2018 |
Completed & H/O. |
No Image |
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018 | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.1 | 22.9 | 0 | 0 | 0 | 0 | 22.9 | 0.2 | - |
99% May - 2018 |
Completed & H/O. |
No Image |
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018 | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.1 | 22.9 | 0 | 0 | 0 | 0 | 22.9 | 0.2 | - |
99% April - 2018 |
Completed & H/O. |
No Image |
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018 | |||||||||||||||||||
81 (New) |
180619-Construction/reconstruction of Government Accomodations at District Headquarter, Bannu |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.35 | 0 | 10 | 10 | 0 | 0 | 0 | 69.35 | 13% |
- April - 2019 |
Work started. Demand Allocation |
No Image |
Bannu | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 23.1 | 22.9 | 0 | 0 | 0 | 0 | 22.9 | 0.2 | - |
99% March - 2018 |
Completed & H/O. |
No Image |
PHED office Bannu ? AA Rs.23.100 m dated 15/03/2018 | |||||||||||||||||||
81 (New) |
180619-Construction/reconstruction of Government Accomodations at District Headquarter, Bannu |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.35 | 0 | 10 | 10 | 0 | 0 | 0 | 69.35 | 13% |
- March - 2019 |
Tender floated on 03/04/2019. |
No Image |
Bannu | |||||||||||||||||||
81 (New) |
180619-Construction/reconstruction of Government Accomodations at District Headquarter, Bannu |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.35 | 0 | 10 | 10 | 0 | 0 | 0 | 69.35 | 13% |
- March - 2019 |
Tender floated on 03/04/2019. |
No Image |
Bannu | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 22.9 | 0 | 0 | 0 | 0 | 22.9 | 0 | - |
100% February - 2018 |
Completed & H/O. |
No Image |
Bannu | |||||||||||||||||||
81 (New) |
180619-Construction/reconstruction of Government Accomodations at District Headquarter, Bannu |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.35 | 0 | 10 | 10 | 0 | 0 | 0 | 69.35 | 13% |
- February - 2019 |
Technical evaluation under process. |
No Image |
Bannu | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 23.9 | 0 | 0 | 0 | 0 | 23.9 | 0 | - |
100% January - 2018 |
Completed & H/O. |
No Image |
81 (New) |
180619-Construction/reconstruction of Government Accomodations at District Headquarter, Bannu |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 79.35 | 0 | 10 | 10 | 0 | 0 | 0 | 69.35 | 13% |
- January - 2019 |
Approved. |
No Image |
Bannu | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.1 | 24.1 | 0 | 0 | 0 | 0 | 24.1 | 0 | - |
100% June - 2018 |
Completed & H/O. |
No Image |
PHED Office Chitral | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.1 | 24.1 | 0 | 0 | 0 | 0 | 24.1 | 0 | - |
100% May - 2018 |
Completed & H/O. |
No Image |
PHED Office Chitral | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.1 | 24.1 | 0 | 0 | 0 | 0 | 24.1 | 0 | - |
100% April - 2018 |
Completed & H/O. |
No Image |
PHED Office Chitral | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.1 | 24.1 | 0 | 0 | 0 | 0 | 24.1 | 0 | - |
100% March - 2018 |
Complted and H/O |
No Image |
PHED Office Chitral | |||||||||||||||||||
81 (OG) |
170168-Reconstruction of Damaged DC's Main Office/ Tehsil Building Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 228.246 | 6.25 | 14.31 | 14.31 | 3.578 | 0.31 | 6.56 | 207.686 | 9% |
3% December - 2019 |
Site not yet handed by the client Dept. |
No Image |
Mansehra | |||||||||||||||||||
81 (OG) |
170168-Reconstruction of Damaged DC's Main Office/ Tehsil Building Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 228.246 | 6.25 | 14.31 | 14.31 | 3.578 | 0 | 6.25 | 207.686 | 9% |
3% November - 2019 |
Site not yet handed by the client Deptt? |
No Image |
Mansehra | |||||||||||||||||||
81 (OG) |
170168-Reconstruction of Damaged DC's Main Office/ Tehsil Building Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 228.246 | 6.25 | 14.31 | 14.31 | 3.578 | 0 | 6.25 | 207.686 | 9% |
3% October - 2019 |
Demarcation of land under process. Constractor nominated. |
No Image |
Mansehra | |||||||||||||||||||
81 (OG) |
170168-Reconstruction of Damaged DC's Main Office/ Tehsil Building Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 228.246 | 6.25 | 14.31 | 14.31 | 3.578 | 0 | 6.25 | 207.686 | 9% |
3% September - 2019 |
Land payment involved of Rs.60 m. Demarcation of land under process. Constractor nominated. |
No Image |
Mansehra | |||||||||||||||||||
81 (OG) |
170168-Reconstruction of Damaged DC's Main Office/ Tehsil Building Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 228.246 | 6.25 | 14.31 | 14.31 | 3.578 | 0 | 6.25 | 207.686 | 9% |
3% August - 2019 |
Land payment involved of Rs.60 m. Demarcation of land under process. Constractor nominated. |
No Image |
Mansehra | |||||||||||||||||||
81 (OG) |
170168-Reconstruction of Damaged DC's Main Office/ Tehsil Building Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 228.246 | 6.25 | 14.31 | 14.31 | 7.31 | 6.246 | 12.496 | 207.686 | 9% |
5% May - 2020 |
Site handed by the client Dept. Developmental work started. |
No Image |
Mansehra | |||||||||||||||||||
81 (OG) |
170168-Reconstruction of Damaged DC's Main Office/ Tehsil Building Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 228.246 | 6.25 | 14.31 | 14.31 | 3.578 | 0.31 | 6.56 | 207.686 | 9% |
3% April - 2020 |
Site handed by the client Dept. Developmental work started. |
No Image |
Mansehra | |||||||||||||||||||
81 (OG) |
170168-Reconstruction of Damaged DC's Main Office/ Tehsil Building Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 228.246 | 6.25 | 14.31 | 14.31 | 3.578 | 0.31 | 6.56 | 207.686 | 9% |
3% March - 2020 |
Site handed by the client Dept. Developmental work started. |
No Image |
Mansehra | |||||||||||||||||||
81 (OG) |
170168-Reconstruction of Damaged DC's Main Office/ Tehsil Building Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 228.246 | 6.25 | 14.31 | 14.31 | 3.578 | 0.31 | 6.56 | 207.686 | 9% |
3% February - 2020 |
Site handed by the client Dept. Developmental work started. |
No Image |
Mansehra | |||||||||||||||||||
81 (OG) |
170168-Reconstruction of Damaged DC's Main Office/ Tehsil Building Mansehra |
Mansehra |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 228.246 | 6.25 | 14.31 | 14.31 | 3.578 | 0.31 | 6.56 | 207.686 | 9% |
3% January - 2020 |
Site not yet handed by the client Dept. |
No Image |
Mansehra | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Mardan |
- | 30-06-18 | - | 29-01-13 | - | 45.592 | 46.308 | 0 | 0 | 0 | 0 | 46.308 | 0 | - |
100% December - 2017 |
PHED office - finishing in progress. Highway Division - GF, FF, mosque finishing in progress. Revised PC-I/DCE for Rs.29.696 submitted to P&D. |
No Image |
1) Office Highway Division Mardan
2) PHED office Mardan | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Mardan |
- | 30-06-18 | - | 29-01-13 | - | 45.592 | 46.308 | 0 | 0 | 0 | 0 | 46.308 | 0 | - |
100% September - 2017 |
PHED - GF roof laid, column in progress. Office HD - finishing in progress. Revised PC-I/DCE submitted for approval. |
No Image |
1) Office Highway Division Mardan
2) PHED office Mardan | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Mardan |
- | 30-06-18 | - | 29-01-13 | - | 45.592 | 46.308 | 0 | 0 | 0 | 0 | 46.308 | 0 | - |
100% August - 2017 |
PHED - GF roof laid, column in progress. Office HD - finishing in progress. Revised PC-I/DCE submitted for approval. |
No Image |
1) Office Highway Division Mardan
2) PHED office Mardan | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Mardan |
- | 30-06-18 | - | 29-01-13 | - | 45.592 | 46.308 | 0 | 0 | 0 | 0 | 46.308 | 0 | - |
100% July - 2017 |
PHED - GF roof laid, column in progress. Office HD - finishing in progress. Revised PC-I/DCE submitted for approval. |
No Image |
1) Office Highway Division Mardan
2) PHED office Mardan | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45.592 | 46.308 | 0 | 0 | 0 | 0 | 46.308 | 0 | - |
100% November - 2017 |
PHED office - finishing in progress. Highway Division - GF, FF, mosque finishing in progress. Revised PC-I/DCE for Rs.29.696 submitted to P&D. |
No Image |
1) Office Highway Division Mardan
2) PHED office Mardan | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45.592 | 46.308 | 0 | 0 | 0 | 0 | 46.308 | 0 | - |
100% October - 2017 |
PHED office - finishing in progress. Highway Division - GF, FF, mosque finishing in progress. Revised PC-I/DCE for Rs.29.696 approved. AA Awaited |
No Image |
1) Office Highway Division Mardan
2) PHED office Mardan | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.805 | 46.308 | 0 | 0 | 0 | 0 | 46.308 | 12.497 | - |
79% June - 2018 |
Finishing in progress. |
No Image |
1) C&W Circle and Highway Division Mardan ? AA Rs.32.508 m dated 15/03/2018
2) PHED office Mardan ? AA Rs.26.297 m dated 15/03/2018 | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.805 | 46.308 | 0 | 0 | 0 | 0 | 46.308 | 12.497 | - |
79% May - 2018 |
PHED office - finishing in progress. Highway Division - GF/FF/mosque finishing in progress. |
No Image |
1) C&W Circle and Highway Division Mardan ? AA Rs.32.508 m dated 15/03/2018
2) PHED office Mardan ? AA Rs.26.297 m dated 15/03/2018 | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.805 | 46.308 | 0 | 0 | 0 | 0 | 46.308 | 12.497 | - |
79% April - 2018 |
PHED office - finishing in progress. Highway Division - GF/FF/mosque finishing in progress. |
No Image |
1) C&W Circle and Highway Division Mardan ? AA Rs.32.508 m dated 15/03/2018
2) PHED office Mardan ? AA Rs.26.297 m dated 15/03/2018 | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 58.805 | 46.308 | 0 | 0 | 0 | 0 | 46.308 | 12.497 | - |
79% March - 2018 |
PHED office - finishing in progress. Highway Division - GF/FF/mosque finishing in progress. |
No Image |
1) C&W Circle and Highway Division Mardan ? AA Rs.32.508 m dated 15/03/2018
2) PHED office Mardan ? AA Rs.26.297 m dated 15/03/2018 | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45.592 | 46.308 | 0 | 0 | 0 | 0 | 46.308 | 0 | - |
100% February - 2018 |
PHED office - finishing in progress. Highway Division - GF, FF, mosque finishing in progress. Revised PC-I/DCE for Rs.29.019 approved in DDWP. AA awaited. |
No Image |
1) Office Highway Division Mardan
2) PHED office Mardan | |||||||||||||||||||
81 (OG) |
120750-F/S and Construction of PHED and C&W Offices and Residences Complex at Mardan, Bannu and Chitral. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45.592 | 46.308 | 0 | 0 | 0 | 0 | 46.308 | 0 | - |
100% January - 2018 |
PHED office - finishing in progress. Highway Division - GF, FF, mosque finishing in progress. Revised PC-I/DCE for Rs.26.297 approved in DDWP. AA awaited. |
No Image |
1) Office Highway Division Mardan 2) PHED office Mardan | |||||||||||||||||||
81 (OG) |
191078-010085-Opening of 3 CVCs, 11 CVDs and 9 AICs and Upgradation of 4 CVDs to CVH Status in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 191.033 | 177.033 | 0 | 0 | 0 | 0 | 177.033 | 0 | - |
- December - 2020 |
No Image | |
81 (OG) |
191078-010085-Opening of 3 CVCs, 11 CVDs and 9 AICs and Upgradation of 4 CVDs to CVH Status in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 191.033 | 177.033 | 0 | 0 | 0 | 0 | 177.033 | 0 | - |
- December - 2020 |
No Image | |
81 (OG) |
191078-010085-Opening of 3 CVCs, 11 CVDs and 9 AICs and Upgradation of 4 CVDs to CVH Status in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 191.033 | 177.033 | 0 | 0 | 0 | 0 | 177.033 | 0 | - |
- October - 2020 |
No Image | |
81 (OG) |
191078-010085-Opening of 3 CVCs, 11 CVDs and 9 AICs and Upgradation of 4 CVDs to CVH Status in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 191.033 | 177.033 | 0 | 0 | 0 | 0 | 177.033 | 0 | - |
- September - 2020 |
No Image | |
Pages : 1 2 |