Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
818 (New) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
- | - | - | - | Line Deptt | 80 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
PC-I submitted 6 months ago. Meeting with PHC held on 14/09/2017. Not yet approved. |
No Image |
818 (New) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
- | - | - | - | Line Deptt | 80 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
PC-I under preparation. Meeting with PHC held on 14/9/2017. |
No Image |
818 (New) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
- | - | - | - | Line Deptt | 80 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
PC-I under preparation. Meeting with PHC held on 14/9/2017. |
No Image |
818 (New) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
- | - | - | - | Line Deptt | 80 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
PC-I under preparation. |
No Image |
818 (New) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
PC-I under preparation. Meeting with PHC held on 14/09/2017. |
No Image |
818 (New) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
PC-I under preparation. Meeting with PHC held on 14/9/2017. |
No Image |
818 (OG) |
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 126.5 | 81.12 | 0.001 | 0.001 | 0.0005 | 0 | 81.12 | 45.379 | 64% |
64% September - 2018 |
Length 5 Km - earth work 100%, structure work 100%, road work 100% completed. |
No Image |
PK-47, Abbottabad | |||||||||||||||||||
818 (OG) |
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 126.5 | 81.12 | 0.001 | 0.001 | 0.0005 | 0 | 81.12 | 45.379 | 64% |
64% July - 2018 |
Length 5 Km - earth work 100%, structure work 100%, road work 100% completed. |
No Image |
PK-47, Abbottabad | |||||||||||||||||||
818 (New) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.013 | 0 | 40 | 40 | 0 | 0 | 0 | 22.013 | 65% |
- June - 2018 |
Approved. |
No Image |
Nathiagali, Abbottabad | |||||||||||||||||||
818 (New) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.013 | 0 | 40 | 40 | 0 | 0 | 0 | 22.013 | 65% |
- May - 2018 |
Approved. |
No Image |
Nathiagali, Abbottabad | |||||||||||||||||||
818 (New) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- April - 2018 |
PC-I submitted 6 months ago. Meeting with PHC held on 14/09/2017. Not yet approved. |
No Image |
Nathiagali, Abbottabad | |||||||||||||||||||
818 (New) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- March - 2018 |
PC-I submitted 6 months ago. Meeting with PHC held on 14/09/2017. Not yet approved. |
No Image |
Nathiagali, Abbottabad | |||||||||||||||||||
818 (New) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- February - 2018 |
PC-I submitted 6 months ago. Meeting with PHC held on 14/09/2017. Not yet approved. |
No Image |
Nathiagali, Abbottabad | |||||||||||||||||||
818 (New) |
170190-Repair and extension of Judicial Lodge at Nathiagali. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 80 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | - |
- January - 2018 |
PC-I submitted 6 months ago. Meeting with PHC held on 14/09/2017. Not yet approved. |
No Image |
818 (OG) |
30001-Khalifa Gul Nawaz Medical Complex, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2434.203 | 1753.754 | 198 | 198 | 49.5 | 49.5 | 1803.254 | 482.449 | 80% |
74% December - 2020 |
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. )
HVAC and Medical Gas tendering in progres. |
No Image |
1) Phase-2
2) Phase-3 | |||||||||||||||||||
818 (OG) |
30001-Khalifa Gul Nawaz Medical Complex, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2434.203 | 1753.754 | 198 | 198 | 49.5 | 49.5 | 1803.254 | 482.449 | 80% |
74% December - 2020 |
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. )
HVAC and Medical Gas tendering in progres. |
No Image |
1) Phase-2
2) Phase-3 | |||||||||||||||||||
818 (OG) |
30001-Khalifa Gul Nawaz Medical Complex, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2434.203 | 1753.754 | 198 | 198 | 49.5 | 3.7 | 1757.454 | 482.449 | 80% |
72% October - 2020 |
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. ) |
No Image |
1) Phase-2
2) Phase-3 | |||||||||||||||||||
818 (OG) |
30001-Khalifa Gul Nawaz Medical Complex, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2434.203 | 1753.754 | 198 | 198 | 49.5 | 3.7 | 1757.454 | 482.449 | 80% |
72% September - 2020 |
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. ) |
No Image |
1) Phase-2
2) Phase-3 | |||||||||||||||||||
818 (OG) |
30001-Khalifa Gul Nawaz Medical Complex, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2434.203 | 1753.754 | 198 | 198 | 49.5 | 0 | 1753.754 | 482.449 | 80% |
72% August - 2020 |
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. ) |
No Image |
1) Phase-2
2) Phase-3 | |||||||||||||||||||
818 (OG) |
30001-Khalifa Gul Nawaz Medical Complex, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2434.203 | 1753.754 | 198 | 0 | 0 | 0 | 1753.754 | 482.449 | 80% |
72% July - 2020 |
Phase-2 completed. Phase-3 (flats, hostel, finishi |
No Image |
1) Phase-2
2) Phase-3 | |||||||||||||||||||
818 (OG) |
30001-Khalifa Gul Nawaz Medical Complex, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2434.203 | 1753.754 | 198 | 96.2 | 96.2 | 89.699 | 1843.453 | 482.449 | 80% |
76% May - 2021 |
01-Unit
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. )
HVAC and Medical Gas tendering in progres. |
No Image |
1) Phase-2
2) Phase-3
| |||||||||||||||||||
818 (OG) |
30001-Khalifa Gul Nawaz Medical Complex, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2434.203 | 1753.754 | 198 | 91.2 | 91.2 | 89.699 | 1843.453 | 482.449 | 80% |
76% April - 2021 |
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. )
HVAC and Medical Gas tendering in progres. |
No Image |
1) Phase-2
2) Phase-3 | |||||||||||||||||||
818 (OG) |
30001-Khalifa Gul Nawaz Medical Complex, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2434.203 | 1753.754 | 198 | 72.2 | 72.2 | 71.909 | 1825.663 | 482.449 | 80% |
75% March - 2021 |
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. )
HVAC and Medical Gas tendering in progres. |
No Image |
1) Phase-2
2) Phase-3 | |||||||||||||||||||
818 (OG) |
30001-Khalifa Gul Nawaz Medical Complex, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2434.203 | 1753.754 | 198 | 72.2 | 72.2 | 71.909 | 1825.663 | 482.449 | 80% |
75% February - 2021 |
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. )
HVAC and Medical Gas tendering in progres. |
No Image |
1) Phase-2
2) Phase-3 | |||||||||||||||||||
818 (OG) |
30001-Khalifa Gul Nawaz Medical Complex, Bannu. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 2434.203 | 1753.754 | 198 | 117.2 | 117.2 | 67.825 | 1821.579 | 482.449 | 80% |
75% January - 2021 |
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. )
HVAC and Medical Gas tendering in progres. |
No Image |
1) Phase-2
2) Phase-3 | |||||||||||||||||||
818 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 20.5 | 15 | 15 | 15 | 10.585738 | 31.085738 | 164.417 | 18% |
16% December - 2019 |
Length 8 Km - Earth work, Structure work in progress. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
818 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 20.5 | 15 | 15 | 3.75 | 3.75 | 24.25 | 164.417 | 18% |
12% November - 2019 |
Length 8 Km - Earth work, Structure work in progress. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
818 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 20.5 | 15 | 15 | 3.75 | 3.75 | 24.25 | 164.417 | 18% |
12% October - 2019 |
Length 8 Km - Earth work, Structure work in progress. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
818 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 20.5 | 15 | 15 | 3.75 | 3.75 | 24.25 | 164.417 | 18% |
12% September - 2019 |
Length 8 Km - Earth work, Structure work in progress. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
818 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 20.5 | 15 | 15 | 3.75 | 0 | 20.5 | 164.417 | 18% |
10% August - 2019 |
Length 8 Km - work in progress. Cutting in progress. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
818 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 20.5 | 15 | 15 | 15 | 10.585738 | 31.085738 | 164.417 | 18% |
16% May - 2020 |
Length 8 Km - Earth work, Structure work in progress. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
818 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 20.5 | 15 | 15 | 15 | 10.585738 | 31.085738 | 164.417 | 18% |
16% April - 2020 |
Length 8 Km - Earth work, Structure work in progress. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
818 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 20.5 | 15 | 15 | 15 | 10.585738 | 31.085738 | 164.417 | 18% |
16% March - 2020 |
Length 8 Km - Earth work, Structure work in progress. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
818 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 20.5 | 15 | 15 | 15 | 10.585738 | 31.085738 | 164.417 | 18% |
16% February - 2020 |
Length 8 Km - Earth work, Structure work in progress. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
818 (OG) |
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II). |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.917 | 20.5 | 15 | 15 | 15 | 10.585738 | 31.085738 | 164.417 | 18% |
16% January - 2020 |
Length 8 Km - Earth work, Structure work in progress. |
No Image |
Manzaray Baba to Khanoray Malakand | |||||||||||||||||||
818 (OG) |
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 680.592 | 528.932 | 10 | 10 | 5.0005 | 0.1 | 529.032 | 141.66 | 79% |
78% December - 2018 |
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass. |
No Image |
Nowshera | |||||||||||||||||||
818 (OG) |
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 680.592 | 528.932 | 10 | 10 | 5.001 | 0.12 | 529.052 | 141.66 | 79% |
78% November - 2018 |
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass. |
No Image |
Nowshera | |||||||||||||||||||
818 (OG) |
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 680.592 | 528.932 | 10 | 10 | 5.001 | 0.12 | 529.052 | 141.66 | 79% |
78% November - 2018 |
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass. |
No Image |
Nowshera | |||||||||||||||||||
818 (OG) |
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 680.592 | 528.932 | 10 | 5.1 | 4.18 | 0.1 | 529.032 | 141.66 | 79% |
78% April - 2019 |
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass. |
No Image |
Nowshera | |||||||||||||||||||
818 (OG) |
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 680.592 | 528.932 | 10 | 5.1 | 2.6005 | 0.1 | 529.032 | 141.66 | 79% |
78% March - 2019 |
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass. |
No Image |
Nowshera | |||||||||||||||||||
818 (OG) |
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 680.592 | 528.932 | 10 | 5.1 | 2.6005 | 0.1 | 529.032 | 141.66 | 79% |
78% March - 2019 |
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass. |
No Image |
Nowshera | |||||||||||||||||||
818 (OG) |
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 680.592 | 528.932 | 10 | 5.1 | 2.6005 | 0.1 | 529.032 | 141.66 | 79% |
78% February - 2019 |
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass. |
No Image |
Nowshera | |||||||||||||||||||
818 (OG) |
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 680.592 | 528.932 | 10 | 10 | 0.1 | 0.1 | 529.032 | 141.66 | 79% |
78% January - 2019 |
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass. |
No Image |
Nowshera | |||||||||||||||||||
Pages : 1 |