Progressive Review for the month(s) of : January - 2021, January - 2018, January - 2019, January - 2020, February - 2021, February - 2018, February - 2019, February - 2020, March - 2021, March - 2018, March - 2019, March - 2020, April - 2021, April - 2018, April - 2019, April - 2020, May - 2021, May - 2018, May - 2020, June - 2018, July - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2017, September - 2018, September - 2019, September - 2020, October - 2017, October - 2019, October - 2020, November - 2017, November - 2018, November - 2019, December - 2017, December - 2020, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
818
(New)
170190-Repair and extension of Judicial Lodge at Nathiagali.
Abbottabad
- - - - Line Deptt 80 0 40 40 0 0 0 0 - -
December - 2017
PC-I submitted 6 months ago. Meeting with PHC held on 14/09/2017. Not yet approved.
No Image
818
(New)
170190-Repair and extension of Judicial Lodge at Nathiagali.
Abbottabad
- - - - Line Deptt 80 0 40 40 0 0 0 0 - -
September - 2017
PC-I under preparation. Meeting with PHC held on 14/9/2017.
No Image
818
(New)
170190-Repair and extension of Judicial Lodge at Nathiagali.
Abbottabad
- - - - Line Deptt 80 0 40 40 0 0 0 0 - -
August - 2017
PC-I under preparation. Meeting with PHC held on 14/9/2017.
No Image
818
(New)
170190-Repair and extension of Judicial Lodge at Nathiagali.
Abbottabad
- - - - Line Deptt 80 0 40 40 0 0 0 0 - -
July - 2017
PC-I under preparation.
No Image
818
(New)
170190-Repair and extension of Judicial Lodge at Nathiagali.
Abbottabad
30-11--1 30-11--1 - 30-11--1 Line Deptt 80 0 40 40 0 0 0 0 - -
November - 2017
PC-I under preparation. Meeting with PHC held on 14/09/2017.
No Image
818
(New)
170190-Repair and extension of Judicial Lodge at Nathiagali.
Abbottabad
30-11--1 30-11--1 - 30-11--1 Line Deptt 80 0 40 40 0 0 0 0 - -
October - 2017
PC-I under preparation. Meeting with PHC held on 14/9/2017.
No Image
818
(OG)
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 126.5 81.12 0.001 0.001 0.0005 0 81.12 45.379 64% 64%
September - 2018
Length 5 Km - earth work 100%, structure work 100%, road work 100% completed.
No Image
PK-47, Abbottabad
818
(OG)
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 126.5 81.12 0.001 0.001 0.0005 0 81.12 45.379 64% 64%
July - 2018
Length 5 Km - earth work 100%, structure work 100%, road work 100% completed.
No Image
PK-47, Abbottabad
818
(New)
170190-Repair and extension of Judicial Lodge at Nathiagali.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 62.013 0 40 40 0 0 0 22.013 65% -
June - 2018
Approved.
No Image
Nathiagali, Abbottabad
818
(New)
170190-Repair and extension of Judicial Lodge at Nathiagali.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 62.013 0 40 40 0 0 0 22.013 65% -
May - 2018
Approved.
No Image
Nathiagali, Abbottabad
818
(New)
170190-Repair and extension of Judicial Lodge at Nathiagali.
Abbottabad
30-11--1 30-11--1 - 30-11--1 Line Deptt 80 0 40 40 0 0 0 0 - -
April - 2018
PC-I submitted 6 months ago. Meeting with PHC held on 14/09/2017. Not yet approved.
No Image
Nathiagali, Abbottabad
818
(New)
170190-Repair and extension of Judicial Lodge at Nathiagali.
Abbottabad
30-11--1 30-11--1 - 30-11--1 Line Deptt 80 0 40 40 0 0 0 0 - -
March - 2018
PC-I submitted 6 months ago. Meeting with PHC held on 14/09/2017. Not yet approved.
No Image
Nathiagali, Abbottabad
818
(New)
170190-Repair and extension of Judicial Lodge at Nathiagali.
Abbottabad
30-11--1 30-11--1 - 30-11--1 Line Deptt 80 0 40 40 0 0 0 0 - -
February - 2018
PC-I submitted 6 months ago. Meeting with PHC held on 14/09/2017. Not yet approved.
No Image
Nathiagali, Abbottabad
818
(New)
170190-Repair and extension of Judicial Lodge at Nathiagali.
Abbottabad
30-11--1 30-11--1 - 30-11--1 Line Deptt 80 0 40 40 0 0 0 0 - -
January - 2018
PC-I submitted 6 months ago. Meeting with PHC held on 14/09/2017. Not yet approved.
No Image
818
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1753.754 198 198 49.5 49.5 1803.254 482.449 80% 74%
December - 2020
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. ) HVAC and Medical Gas tendering in progres.
No Image
1) Phase-2
2) Phase-3
818
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1753.754 198 198 49.5 49.5 1803.254 482.449 80% 74%
December - 2020
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. ) HVAC and Medical Gas tendering in progres.
No Image
1) Phase-2
2) Phase-3
818
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1753.754 198 198 49.5 3.7 1757.454 482.449 80% 72%
October - 2020
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. )
No Image
1) Phase-2
2) Phase-3
818
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1753.754 198 198 49.5 3.7 1757.454 482.449 80% 72%
September - 2020
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. )
No Image
1) Phase-2
2) Phase-3
818
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1753.754 198 198 49.5 0 1753.754 482.449 80% 72%
August - 2020
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. )
No Image
1) Phase-2
2) Phase-3
818
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1753.754 198 0 0 0 1753.754 482.449 80% 72%
July - 2020
Phase-2 completed. Phase-3 (flats, hostel, finishi
No Image
1) Phase-2
2) Phase-3
818
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1753.754 198 96.2 96.2 89.699 1843.453 482.449 80% 76%
May - 2021
01-Unit Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. ) HVAC and Medical Gas tendering in progres.
No Image
1) Phase-2
2) Phase-3
 
818
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1753.754 198 91.2 91.2 89.699 1843.453 482.449 80% 76%
April - 2021
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. ) HVAC and Medical Gas tendering in progres.
No Image
1) Phase-2
2) Phase-3
818
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1753.754 198 72.2 72.2 71.909 1825.663 482.449 80% 75%
March - 2021
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. ) HVAC and Medical Gas tendering in progres.
No Image
1) Phase-2
2) Phase-3
818
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1753.754 198 72.2 72.2 71.909 1825.663 482.449 80% 75%
February - 2021
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. ) HVAC and Medical Gas tendering in progres.
No Image
1) Phase-2
2) Phase-3
818
(OG)
30001-Khalifa Gul Nawaz Medical Complex, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 2434.203 1753.754 198 117.2 117.2 67.825 1821.579 482.449 80% 75%
January - 2021
Phase-2 completed. Phase-3 (flats, hostel, finishing in progress. ) HVAC and Medical Gas tendering in progres.
No Image
1) Phase-2
2) Phase-3
818
(OG)
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II).
Malakand
30-11--1 30-11--1 - 30-11--1 - 199.917 20.5 15 15 15 10.585738 31.085738 164.417 18% 16%
December - 2019
Length 8 Km - Earth work, Structure work in progress.
No Image
Manzaray Baba to Khanoray Malakand
818
(OG)
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II).
Malakand
30-11--1 30-11--1 - 30-11--1 - 199.917 20.5 15 15 3.75 3.75 24.25 164.417 18% 12%
November - 2019
Length 8 Km - Earth work, Structure work in progress.
No Image
Manzaray Baba to Khanoray Malakand
818
(OG)
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II).
Malakand
30-11--1 30-11--1 - 30-11--1 - 199.917 20.5 15 15 3.75 3.75 24.25 164.417 18% 12%
October - 2019
Length 8 Km - Earth work, Structure work in progress.
No Image
Manzaray Baba to Khanoray Malakand
818
(OG)
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II).
Malakand
30-11--1 30-11--1 - 30-11--1 - 199.917 20.5 15 15 3.75 3.75 24.25 164.417 18% 12%
September - 2019
Length 8 Km - Earth work, Structure work in progress.
No Image
Manzaray Baba to Khanoray Malakand
818
(OG)
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II).
Malakand
30-11--1 30-11--1 - 30-11--1 - 199.917 20.5 15 15 3.75 0 20.5 164.417 18% 10%
August - 2019
Length 8 Km - work in progress. Cutting in progress.
No Image
Manzaray Baba to Khanoray Malakand
818
(OG)
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II).
Malakand
30-11--1 30-11--1 - 30-11--1 - 199.917 20.5 15 15 15 10.585738 31.085738 164.417 18% 16%
May - 2020
Length 8 Km - Earth work, Structure work in progress.
No Image
Manzaray Baba to Khanoray Malakand
818
(OG)
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II).
Malakand
30-11--1 30-11--1 - 30-11--1 - 199.917 20.5 15 15 15 10.585738 31.085738 164.417 18% 16%
April - 2020
Length 8 Km - Earth work, Structure work in progress.
No Image
Manzaray Baba to Khanoray Malakand
818
(OG)
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II).
Malakand
30-11--1 30-11--1 - 30-11--1 - 199.917 20.5 15 15 15 10.585738 31.085738 164.417 18% 16%
March - 2020
Length 8 Km - Earth work, Structure work in progress.
No Image
Manzaray Baba to Khanoray Malakand
818
(OG)
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II).
Malakand
30-11--1 30-11--1 - 30-11--1 - 199.917 20.5 15 15 15 10.585738 31.085738 164.417 18% 16%
February - 2020
Length 8 Km - Earth work, Structure work in progress.
No Image
Manzaray Baba to Khanoray Malakand
818
(OG)
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II).
Malakand
30-11--1 30-11--1 - 30-11--1 - 199.917 20.5 15 15 15 10.585738 31.085738 164.417 18% 16%
January - 2020
Length 8 Km - Earth work, Structure work in progress.
No Image
Manzaray Baba to Khanoray Malakand
818
(OG)
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 680.592 528.932 10 10 5.0005 0.1 529.032 141.66 79% 78%
December - 2018
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass.
No Image
Nowshera
818
(OG)
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 680.592 528.932 10 10 5.001 0.12 529.052 141.66 79% 78%
November - 2018
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass.
No Image
Nowshera
818
(OG)
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 680.592 528.932 10 10 5.001 0.12 529.052 141.66 79% 78%
November - 2018
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass.
No Image
Nowshera
818
(OG)
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 680.592 528.932 10 5.1 4.18 0.1 529.032 141.66 79% 78%
April - 2019
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass.
No Image
Nowshera
818
(OG)
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 680.592 528.932 10 5.1 2.6005 0.1 529.032 141.66 79% 78%
March - 2019
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass.
No Image
Nowshera
818
(OG)
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 680.592 528.932 10 5.1 2.6005 0.1 529.032 141.66 79% 78%
March - 2019
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass.
No Image
Nowshera
818
(OG)
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 680.592 528.932 10 5.1 2.6005 0.1 529.032 141.66 79% 78%
February - 2019
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass.
No Image
Nowshera
818
(OG)
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 680.592 528.932 10 10 0.1 0.1 529.032 141.66 79% 78%
January - 2019
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass.
No Image
Nowshera