Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
823 (OG) |
140884-F/S, design and Construction of (a) Arro Kas Summa to Lora via Banwari (b) Improvement / Widening & BT of Tajwal to Bagan Road (c) Garhi ? Chanali road via Seri, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180.78 | 70.485 | 0.001 | 4 | 4 | 4 | 74.485 | 110.294 | 39% |
41% September - 2018 |
Length 8 Km - out of 3 units, all in progress. |
No Image |
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48 | |||||||||||||||||||
823 (OG) |
140884-F/S, design and Construction of (a) Arro Kas Summa to Lora via Banwari (b) Improvement / Widening & BT of Tajwal to Bagan Road (c) Garhi ? Chanali road via Seri, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 180.78 | 70.485 | 0.001 | 0.001 | 0.0005 | 0 | 70.485 | 110.294 | 39% |
39% July - 2018 |
Length 8 Km - out of 3 units, all in progress. |
No Image |
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48 | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Battagram |
- | - | - | - | Line Deptt | 4 | 0 | 0 | 0 | 0 | 0 | 0 | 4 | - |
- December - 2017 |
Tender called on 15/01/2018. |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai, Battagram | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 4 | 0 | 0 | 0 | 0 | 0 | 0 | 4 | - |
- June - 2018 |
Work started. |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai, Battagram | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 4 | 0 | 0 | 0 | 0 | 0 | 0 | 4 | - |
- May - 2018 |
Work started. |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai, Battagram | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 4 | 0 | 0 | 0 | 0 | 0 | 0 | 4 | - |
- April - 2018 |
Work started. |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai, Battagram | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 4 | 0 | 0 | 0 | 0 | 0 | 0 | 4 | - |
- March - 2018 |
Tender opened on 01/02/2018, submiited for approval. Stay order issued, hearing date on 04/04/2018. |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai, Battagram | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 4 | 0 | 0 | 0 | 0 | 0 | 0 | 4 | - |
- February - 2018 |
Tender opened on 01/02/2018, submiited for approval. Stay order issued, hearing date on 14/03/2018. |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai, Battagram | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 4 | 0 | 0 | 0 | 0 | 0 | 0 | 4 | - |
- January - 2018 |
Tender opened on 1/2/2018. Submiited for approval ( Stay order iisued ) |
No Image |
Construction of Bar Room and Litigant Sheds at Judicial Complex Allai, Battagram | |||||||||||||||||||
823 (OG) |
150846-Construction of road a) Dokda to Jawari to Korsar via poland b) Construction of Multi Span box culverts at village sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 77.06 | 30 | 28.725 | 28.725 | 15 | 92.06 | 122.94 | 47% |
40% December - 2019 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued. Snow bound area. |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
823 (OG) |
150846-Construction of road a) Dokda to Jawari to Korsar via poland b) Construction of Multi Span box culverts at village sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 77.06 | 30 | 30 | 7.5 | 7.5 | 84.56 | 122.94 | 47% |
37% November - 2019 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued. |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
823 (OG) |
150846-Construction of road a) Dokda to Jawari to Korsar via poland b) Construction of Multi Span box culverts at village sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 77.06 | 30 | 30 | 7.5 | 7.5 | 84.56 | 122.94 | 47% |
37% October - 2019 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued. |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
823 (OG) |
150846-Construction of road a) Dokda to Jawari to Korsar via poland b) Construction of Multi Span box culverts at village sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 77.06 | 30 | 30 | 7.5 | 7.5 | 84.56 | 122.94 | 47% |
37% September - 2019 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued. |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
823 (OG) |
150846-Construction of road a) Dokda to Jawari to Korsar via poland b) Construction of Multi Span box culverts at village sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 77.06 | 30 | 30 | 7.5 | 0 | 77.06 | 122.94 | 47% |
34% August - 2019 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued. |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
823 (OG) |
150846-Construction of road a) Dokda to Jawari to Korsar via poland b) Construction of Multi Span box culverts at village sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 77.06 | 30 | 28.725 | 28.725 | 28.725 | 105.785 | 122.94 | 47% |
46% May - 2020 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued.
Snow bound area. |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
823 (OG) |
150846-Construction of road a) Dokda to Jawari to Korsar via poland b) Construction of Multi Span box culverts at village sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 77.06 | 30 | 28.725 | 28.725 | 28.725 | 105.785 | 122.94 | 47% |
46% April - 2020 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued.
Snow bound area. |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
823 (OG) |
150846-Construction of road a) Dokda to Jawari to Korsar via poland b) Construction of Multi Span box culverts at village sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 77.06 | 30 | 28.725 | 28.725 | 28.725 | 105.785 | 122.94 | 47% |
46% March - 2020 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued.
Snow bound area. |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
823 (OG) |
150846-Construction of road a) Dokda to Jawari to Korsar via poland b) Construction of Multi Span box culverts at village sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 77.06 | 30 | 28.725 | 28.725 | 28.725 | 105.785 | 122.94 | 47% |
46% February - 2020 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued.
Snow bound area. |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
823 (OG) |
150846-Construction of road a) Dokda to Jawari to Korsar via poland b) Construction of Multi Span box culverts at village sultanwas and Ghazi Khanai, District Buner. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230 | 77.06 | 30 | 28.725 | 28.725 | 20 | 97.06 | 122.94 | 47% |
42% January - 2020 |
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box culverts at Sultanwas and Ghazi Khani PK-79 - work order issued.
Snow bound area. |
No Image |
1) Construction of road from Dokada to Korsar via Poland (10 Km)
2) Construction of Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Charsadda |
- | - | - | - | Line Deptt | 28.903 | 0 | 0 | 0 | 0 | 0 | 0 | 28.903 | - |
- December - 2017 |
Tender approval under process. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 28.903 | 0 | 19.431 | 19.431 | 19.431 | 19.431 | 19.431 | 9.472 | 67% |
67% June - 2018 |
Completed. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 28.903 | 0 | 18.188 | 18.188 | 18.188 | 18.188 | 18.188 | 10.715 | 63% |
63% May - 2018 |
Completed. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 28.903 | 0 | 18.188 | 18.188 | 18.188 | 18.188 | 18.188 | 10.715 | 63% |
63% April - 2018 |
Completed. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 28.903 | 0 | 10 | 10 | 10 | 10 | 10 | 18.903 | 35% |
35% March - 2018 |
Completed. Balance funds demanded. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 28.903 | 0 | 10 | 10 | 10 | 10 | 10 | 18.903 | 35% |
35% February - 2018 |
Finishing in progress. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 28.903 | 0 | 10 | 10 | 10 | 10 | 10 | 18.903 | 35% |
35% January - 2018 |
Roof laid. |
No Image |
Construction of Lawyer Shed in newly constructed Judicial Complex at Charsadda | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 21.068 | 0 | 0 | 0 | 0 | 0 | 0 | 21.068 | - |
- June - 2018 |
Work order issued. |
No Image |
Honourable Judges Apartments Single Storey at Paharpur | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 21.068 | 0 | 0 | 0 | 0 | 0 | 0 | 21.068 | - |
- May - 2018 |
Work order issued. |
No Image |
Honourable Judges Apartments Single Storey at Paharpur | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 21.068 | 0 | 0 | 0 | 0 | 0 | 0 | 21.068 | - |
- April - 2018 |
Work order issued. |
No Image |
Honourable Judges Apartments Single Storey at Paharpur | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 21.068 | 0 | 0 | 0 | 0 | 0 | 0 | 21.068 | - |
- March - 2018 |
Work order issued. |
No Image |
Honourable Judges Apartments Single Storey at Paharpur | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 21.068 | 0 | 0 | 0 | 0 | 0 | 0 | 21.068 | - |
- February - 2018 |
Tendering approval in progress. |
No Image |
Honourable Judges Apartments Single Storey at Paharpur | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 21.068 | 0 | 0 | 0 | 0 | 0 | 0 | 21.068 | - |
- January - 2018 |
Tendering opening on 20/2/2018. |
No Image |
Honourable Judges Apartments Single Storey at Paharpur | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Dir Lower |
- | - | - | - | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
Tender floated on 16/01/2018. |
No Image |
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 10.219 | 0 | 2.873 | 2.873 | 2.873 | 0.873 | 0.873 | 7.346 | 28% |
9% June - 2018 |
Structure work completed. Flooring in progress. |
No Image |
Construction of Court Rooms in Judiciary Complex at Dir Lower (civil work) | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 10.219 | 0 | 0 | 0 | 0 | 0 | 0 | 10.219 | - |
- May - 2018 |
Work in progress. |
No Image |
Construction of Court Rooms in Judiciary Complex at Dir Lower (civil work) | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 10.219 | 0 | 0 | 0 | 0 | 0 | 0 | 10.219 | - |
- April - 2018 |
Work in progress. |
No Image |
Construction of Court Rooms in Judiciary Complex at Dir Lower (civil work) | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 10.219 | 0 | 0 | 0 | 0 | 0 | 0 | 10.219 | - |
- March - 2018 |
Work started. |
No Image |
Construction of Court Rooms in Judiciary Complex at Dir Lower (civil work) | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 10.219 | 0 | 0 | 0 | 0 | 0 | 0 | 10.219 | - |
- February - 2018 |
Work started. |
No Image |
Construction of Court Rooms in Judiciary Complex at Dir Lower (civil work) | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 10.219 | 0 | 0 | 0 | 0 | 0 | 0 | 10.219 | - |
- January - 2018 |
Work started. |
No Image |
Construction of Court Rooms in Judiciary Complex at Dir Lower (civil work) | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 11.64 | 0 | 0 | 0 | 0 | 0 | 0 | 11.64 | - |
- June - 2018 |
Work started. |
No Image |
1) Judicial Complex Takht Nasrati Karak (raising of BW, installation of CCTV cameras/construction of security/sentry posts
2) Tehsil Banda Daud Shah Karak (construction of lawyers shed/offices and bathroom at court building | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 11.64 | 0 | 0 | 0 | 0 | 0 | 0 | 11.64 | - |
- May - 2018 |
Work started. Demand Rs.5 m. |
No Image |
1) Judicial Complex Takht Nasrati Karak (raising of BW, installation of CCTV cameras/construction of security/sentry posts
2) Tehsil Banda Daud Shah Karak (construction of lawyers shed/offices and bathroom at court building | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 11.64 | 0 | 0 | 0 | 0 | 0 | 0 | 11.64 | - |
- April - 2018 |
Work started. Demand Rs.5 m. |
No Image |
1) Judicial Complex Takht Nasrati Karak (raising of BW, installation of CCTV cameras/construction of security/sentry posts
2) Tehsil Banda Daud Shah Karak (construction of lawyers shed/offices and bathroom at court building | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 11.64 | 0 | 0 | 0 | 0 | 0 | 0 | 11.64 | - |
- March - 2018 |
Work Started Demand Rs. 5 M |
No Image |
1) Judicial Complex Takht Nasrati Karak (raising of BW, installation of CCTV cameras/construction of security/sentry posts
2) Tehsil Banda Daud Shah Karak (construction of lawyers shed/offices and bathroom at court building | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 11.64 | 0 | 0 | 0 | 0 | 0 | 0 | 11.64 | - |
- February - 2018 |
Tender under process. |
No Image |
1) Judicial Complex Takht Nasrati Karak (raising of BW, installation of CCTV cameras/construction of security/sentry posts
2) Tehsil Banda Daud Shah Karak (construction of lawyers shed/offices and bathroom at court building | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3.443 | 0 | 0 | 0 | 0 | 0 | 0 | 3.443 | - |
- June - 2018 |
Work order issued. |
No Image |
Construction of Mosque in Judicial Colony Nowshera road Mardan | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3.443 | 0 | 0 | 0 | 0 | 0 | 0 | 3.443 | - |
- May - 2018 |
Work order issued. |
No Image |
Construction of Mosque in Judicial Colony Nowshera road Mardan | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3.443 | 0 | 0 | 0 | 0 | 0 | 0 | 3.443 | - |
- April - 2018 |
Work order issued. |
No Image |
Construction of Mosque in Judicial Colony Nowshera road Mardan | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3.443 | 0 | 0 | 0 | 0 | 0 | 0 | 3.443 | - |
- March - 2018 |
Work order issued. |
No Image |
Construction of Mosque in Judicial Colony Nowshera road Mardan | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3.443 | 0 | 0 | 0 | 0 | 0 | 0 | 3.443 | - |
- February - 2018 |
Tender called on 20/01/2018, approval under process. |
No Image |
Construction of Mosque in Judicial Colony Nowshera road Mardan | |||||||||||||||||||
823 (New) |
170188-Missing facilities and improvement of infrastructure of existing judicial complexes in Khyber Pakhtunkhwa. |
Mardan |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 3.443 | 0 | 0 | 0 | 0 | 0 | 0 | 3.443 | - |
- January - 2018 |
Tender called on 20/01/2018. |
No Image |
Construction of Mosque in Judicial Colony Nowshera road Mardan | |||||||||||||||||||
Pages : 1 2 3 |