Progressive Review for the month(s) of : January - 2021, January - 2019, January - 2020, February - 2021, February - 2019, February - 2020, March - 2021, March - 2019, March - 2020, April - 2021, April - 2019, April - 2020, May - 2021, May - 2020, July - 2018, July - 2020, August - 2019, August - 2020, September - 2020, September - 2018, September - 2019, October - 2020, October - 2019, November - 2018, November - 2019, December - 2020, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
826
(OG)
150862-Reh / Imp / BT / PCC of Boi Talkandi via Pall Mohri Sahran Sambli (R/W), Bangra Chowk to Kaner Kass Malkot U/C Plack Vill with drain, Banni Jandala to Ander Kot Drwaza via Cham U/C Plack Distt. Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 70 16.3 0.001 0.001 0.0005 0 16.3 53.699 23% 23%
September - 2018
3 units - (PCC components) - 2 earth work in progress, 1 structure work in progress.
No Image
1) Boi Talkandi road PK-45
2) Banni Jandala to Ander Kot Drwaza via Cham UC Plack PK-45
826
(OG)
150862-Reh / Imp / BT / PCC of Boi Talkandi via Pall Mohri Sahran Sambli (R/W), Bangra Chowk to Kaner Kass Malkot U/C Plack Vill with drain, Banni Jandala to Ander Kot Drwaza via Cham U/C Plack Distt. Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 70 16.3 0.001 0.001 0.0005 0 16.3 53.699 23% 23%
July - 2018
3 units - (PCC components) - 2 earth work in progress, 1 structure work in progress.
No Image
1) Boi Talkandi road PK-45
2) Banni Jandala to Ander Kot Drwaza via Cham UC Plack PK-45
826
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km).
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 214.378 10 7.588 2.589 2.588 216.966 59.622 79% 76%
December - 2018
Original scope - completed (10 Km). Revised scope in progress.
No Image
Nowshera
826
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km).
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 214.378 10 7.588 2.589 2.588 216.966 59.622 79% 76%
November - 2018
Original scope - completed (10 Km). Revised scope in progress.
No Image
Nowshera
826
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km).
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 214.378 10 7.588 2.589 2.588 216.966 59.622 79% 76%
November - 2018
Original scope - completed (10 Km). Revised scope in progress.
No Image
Nowshera
826
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km).
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 214.378 10 7.588 7.588 7.588 221.966 59.622 79% 78%
April - 2019
Original scope - completed (10 Km). Revised scope- In progress.
No Image
Nowshera
826
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km).
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 214.378 10 7.588 5.0885 5.089 219.467 59.622 79% 77%
March - 2019
Original scope - completed (10 Km). Revised scope- In progress.
No Image
Nowshera
826
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km).
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 214.378 10 7.588 5.0885 5.089 219.467 59.622 79% 77%
March - 2019
Original scope - completed (10 Km). Revised scope- In progress.
No Image
Nowshera
826
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km).
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 214.378 10 7.588 5.0885 5.089 219.467 59.622 79% 77%
February - 2019
Original scope - completed (10 Km). Revised scope- In progress.
No Image
Nowshera
826
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km).
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 284 214.378 10 7.588 2.588 2.588 216.966 59.622 79% 76%
January - 2019
Original scope - completed (10 Km). Revised scope in progress.
No Image
Nowshera
826
(OG)
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla
Shangla
30-11--1 30-11--1 - 30-11--1 - 120 60.356 10 6.8625 6.8625 0 60.356 49.644 59% 50%
December - 2019
Length 10 Km TST - earth work 95%, masonry work 35% completed. Revised PC-1 under process.
No Image
Ranyal Chichloo road (10 Km) Shangla
826
(OG)
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla
Shangla
30-11--1 30-11--1 - 30-11--1 - 120 60.356 10 7.5 0 0 60.356 49.644 59% 50%
November - 2019
Length 10 Km TST - earth work 95%, masonry work 35% completed.
No Image
Ranyal Chichloo road (10 Km) Shangla
826
(OG)
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla
Shangla
30-11--1 30-11--1 - 30-11--1 - 120 60.356 10 7.5 0 0 60.356 49.644 59% 50%
October - 2019
Length 10 Km TST - earth work 95%, masonry work 35% completed.
No Image
Ranyal Chichloo road (10 Km) Shangla
826
(OG)
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla
Shangla
30-11--1 30-11--1 - 30-11--1 - 120 60.356 10 10 2.5 0 60.356 49.644 59% 50%
September - 2019
Length 10 Km TST - earth work 95%, masonry work 35% completed.
No Image
Ranyal Chichloo road (10 Km) Shangla
826
(OG)
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla
Shangla
30-11--1 30-11--1 - 30-11--1 - 120 60.356 10 10 2.5 0 60.356 49.644 59% 50%
August - 2019
Length 10 Km TST - earth work 95%, masonry work 35% completed.
No Image
Ranyal Chichloo road (10 Km) Shangla
826
(OG)
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla
Shangla
30-11--1 30-11--1 - 30-11--1 - 120 60.356 10 6.8625 6.8625 3.429 63.785 49.644 59% 53%
May - 2020
Length 10 Km TST - earth work 95%, masonry work 35% completed. Revised PC-1 under process.
No Image
Ranyal Chichloo road (10 Km) Shangla
826
(OG)
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla
Shangla
30-11--1 30-11--1 - 30-11--1 - 120 60.356 10 6.8625 6.8625 0 60.356 49.644 59% 50%
April - 2020
Length 10 Km TST - earth work 95%, masonry work 35% completed. Revised PC-1 under process.
No Image
Ranyal Chichloo road (10 Km) Shangla
826
(OG)
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla
Shangla
30-11--1 30-11--1 - 30-11--1 - 120 60.356 10 6.8625 6.8625 0 60.356 49.644 59% 50%
March - 2020
Length 10 Km TST - earth work 95%, masonry work 35% completed. Revised PC-1 under process.
No Image
Ranyal Chichloo road (10 Km) Shangla
826
(OG)
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla
Shangla
30-11--1 30-11--1 - 30-11--1 - 120 60.356 10 6.8625 6.8625 0 60.356 49.644 59% 50%
February - 2020
Length 10 Km TST - earth work 95%, masonry work 35% completed. Revised PC-1 under process.
No Image
Ranyal Chichloo road (10 Km) Shangla
826
(OG)
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla
Shangla
30-11--1 30-11--1 - 30-11--1 - 120 60.356 10 6.8625 6.8625 0 60.356 49.644 59% 50%
January - 2020
Length 10 Km TST - earth work 95%, masonry work 35% completed. Revised PC-1 under process.
No Image
Ranyal Chichloo road (10 Km) Shangla
826
(OG)
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 176.072 20.983 152.272 152.272 55.738 43.641 64.624 2.817 98% 37%
December - 2020
A) Establishment of 04 Nos CHCs 1) M/B upto roof level. 2) Flooring in progress. 3) MB completed upto roof level. 4) M/B upto DPC level. Upgradation of 11 Nos CDs to CHC level. Work in progress on all units.
No Image
826
(OG)
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 176.072 20.983 152.272 152.272 55.738 43.641 64.624 2.817 98% 37%
December - 2020
A) Establishment of 04 Nos CHCs 1) M/B upto roof level. 2) Flooring in progress. 3) MB completed upto roof level. 4) M/B upto DPC level. Upgradation of 11 Nos CDs to CHC level. Work in progress on all units.
No Image
826
(OG)
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 176.072 20.983 152.272 152.272 20 20 40.983 2.817 98% 23%
October - 2020
A) Establishment of 04 Nos CHCs 1) M/B upto roof level. 2) Flooring in progress. 3) MB completed upto roof level. 4) M/B upto DPC level. Upgradation of 11 Nos CDs to CHC level. Work in progress on all units.
No Image
826
(OG)
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 176.072 20.983 152.272 152.272 20 17.222 38.205 2.817 98% 22%
September - 2020
A) Establishment of 04 Nos CHCs 1) M/B upto roof level. 2) Flooring in progress. 3) MB completed upto roof level. 4) M/B upto DPC level. Upgradation of 11 Nos CDs to CHC level. Work in progress on all units.
No Image
826
(OG)
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 176.072 20.983 152.272 152.272 20 0 20.983 2.817 98% 12%
August - 2020
A) Establishment of 04 Nos CHCs 1) M/B upto roof level. 2) Flooring in progress. 3) MB completed upto roof level. 4) M/B upto DPC level. Upgradation of 11 Nos CDs to CHC level. Work in progress on all units.
No Image
826
(OG)
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 176.072 20.983 152.272 104.005 104.005 73.377 94.36 2.817 98% 54%
May - 2021
A) Establishment of 04 Nos CHCs 1) M/B upto roof level. 2) Flooring in progress. 3) MB completed upto roof level. 4) M/B upto DPC level. Upgradation of 11 Nos CDs to CHC level. Work in progress on all units.
No Image
1 Estab: of CHCs
2 Upgradation of 11 Nos CDc to CHCs level
826
(OG)
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 176.072 20.983 152.272 104.005 104.005 58.954 79.937 2.817 98% 45%
April - 2021
A) Establishment of 04 Nos CHCs 1) M/B upto roof level. 2) Flooring in progress. 3) MB completed upto roof level. 4) M/B upto DPC level. Upgradation of 11 Nos CDs to CHC level. Work in progress on all units.
No Image
1 Estab: of CHCs
2 Upgradation of 11 Nos CDc to CHCs level
826
(OG)
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 176.072 20.983 152.272 104.005 104.005 60.288 81.271 2.817 98% 46%
March - 2021
A) Establishment of 04 Nos CHCs 1) M/B upto roof level. 2) Flooring in progress. 3) MB completed upto roof level. 4) M/B upto DPC level. Upgradation of 11 Nos CDs to CHC level. Work in progress on all units.
No Image
1 Estab: of CHCs
2 Upgradation of 11 Nos CDc to CHCs level
826
(OG)
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 176.072 20.983 152.272 104.005 104.005 60.288 81.271 2.817 98% 46%
February - 2021
A) Establishment of 04 Nos CHCs 1) M/B upto roof level. 2) Flooring in progress. 3) MB completed upto roof level. 4) M/B upto DPC level. Upgradation of 11 Nos CDs to CHC level. Work in progress on all units.
No Image
1 Estab: of CHCs
2 Upgradation of 11 Nos CDc to CHCs level
826
(OG)
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 176.072 20.983 152.272 55.738 55.738 55.738 76.721 2.817 98% 44%
January - 2021
A) Establishment of 04 Nos CHCs 1) M/B upto roof level. 2) Flooring in progress. 3) MB completed upto roof level. 4) M/B upto DPC level. Upgradation of 11 Nos CDs to CHC level. Work in progress on all units.
No Image
1 Estab: of CHCs
2 Upgradation of 11 Nos CDc to CHCs level
826
(OG)
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA]
South Wazirstan
30-11--1 30-11--1 - 30-11--1 - 176.072 23.8 152.272 0 0 0 23.8 0