Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
826 (OG) |
150862-Reh / Imp / BT / PCC of Boi Talkandi via Pall Mohri Sahran Sambli (R/W), Bangra Chowk to Kaner Kass Malkot U/C Plack Vill with drain, Banni Jandala to Ander Kot Drwaza via Cham U/C Plack Distt. Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 16.3 | 0.001 | 0.001 | 0.0005 | 0 | 16.3 | 53.699 | 23% |
23% September - 2018 |
3 units - (PCC components) - 2 earth work in progress, 1 structure work in progress. |
No Image |
1) Boi Talkandi road PK-45
2) Banni Jandala to Ander Kot Drwaza via Cham UC Plack PK-45 | |||||||||||||||||||
826 (OG) |
150862-Reh / Imp / BT / PCC of Boi Talkandi via Pall Mohri Sahran Sambli (R/W), Bangra Chowk to Kaner Kass Malkot U/C Plack Vill with drain, Banni Jandala to Ander Kot Drwaza via Cham U/C Plack Distt. Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 70 | 16.3 | 0.001 | 0.001 | 0.0005 | 0 | 16.3 | 53.699 | 23% |
23% July - 2018 |
3 units - (PCC components) - 2 earth work in progress, 1 structure work in progress. |
No Image |
1) Boi Talkandi road PK-45
2) Banni Jandala to Ander Kot Drwaza via Cham UC Plack PK-45 | |||||||||||||||||||
826 (OG) |
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km). |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 284 | 214.378 | 10 | 7.588 | 2.589 | 2.588 | 216.966 | 59.622 | 79% |
76% December - 2018 |
Original scope - completed (10 Km). Revised scope in progress. |
No Image |
Nowshera | |||||||||||||||||||
826 (OG) |
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km). |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 284 | 214.378 | 10 | 7.588 | 2.589 | 2.588 | 216.966 | 59.622 | 79% |
76% November - 2018 |
Original scope - completed (10 Km). Revised scope in progress. |
No Image |
Nowshera | |||||||||||||||||||
826 (OG) |
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km). |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 284 | 214.378 | 10 | 7.588 | 2.589 | 2.588 | 216.966 | 59.622 | 79% |
76% November - 2018 |
Original scope - completed (10 Km). Revised scope in progress. |
No Image |
Nowshera | |||||||||||||||||||
826 (OG) |
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km). |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 284 | 214.378 | 10 | 7.588 | 7.588 | 7.588 | 221.966 | 59.622 | 79% |
78% April - 2019 |
Original scope - completed (10 Km). Revised scope- In progress. |
No Image |
Nowshera | |||||||||||||||||||
826 (OG) |
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km). |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 284 | 214.378 | 10 | 7.588 | 5.0885 | 5.089 | 219.467 | 59.622 | 79% |
77% March - 2019 |
Original scope - completed (10 Km). Revised scope- In progress. |
No Image |
Nowshera | |||||||||||||||||||
826 (OG) |
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km). |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 284 | 214.378 | 10 | 7.588 | 5.0885 | 5.089 | 219.467 | 59.622 | 79% |
77% March - 2019 |
Original scope - completed (10 Km). Revised scope- In progress. |
No Image |
Nowshera | |||||||||||||||||||
826 (OG) |
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km). |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 284 | 214.378 | 10 | 7.588 | 5.0885 | 5.089 | 219.467 | 59.622 | 79% |
77% February - 2019 |
Original scope - completed (10 Km). Revised scope- In progress. |
No Image |
Nowshera | |||||||||||||||||||
826 (OG) |
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km). |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 284 | 214.378 | 10 | 7.588 | 2.588 | 2.588 | 216.966 | 59.622 | 79% |
76% January - 2019 |
Original scope - completed (10 Km). Revised scope in progress. |
No Image |
Nowshera | |||||||||||||||||||
826 (OG) |
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 60.356 | 10 | 6.8625 | 6.8625 | 0 | 60.356 | 49.644 | 59% |
50% December - 2019 |
Length 10 Km TST - earth work 95%, masonry work 35% completed. Revised PC-1 under process. |
No Image |
Ranyal Chichloo road (10 Km) Shangla | |||||||||||||||||||
826 (OG) |
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 60.356 | 10 | 7.5 | 0 | 0 | 60.356 | 49.644 | 59% |
50% November - 2019 |
Length 10 Km TST - earth work 95%, masonry work 35% completed. |
No Image |
Ranyal Chichloo road (10 Km) Shangla | |||||||||||||||||||
826 (OG) |
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 60.356 | 10 | 7.5 | 0 | 0 | 60.356 | 49.644 | 59% |
50% October - 2019 |
Length 10 Km TST - earth work 95%, masonry work 35% completed. |
No Image |
Ranyal Chichloo road (10 Km) Shangla | |||||||||||||||||||
826 (OG) |
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 60.356 | 10 | 10 | 2.5 | 0 | 60.356 | 49.644 | 59% |
50% September - 2019 |
Length 10 Km TST - earth work 95%, masonry work 35% completed. |
No Image |
Ranyal Chichloo road (10 Km) Shangla | |||||||||||||||||||
826 (OG) |
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 60.356 | 10 | 10 | 2.5 | 0 | 60.356 | 49.644 | 59% |
50% August - 2019 |
Length 10 Km TST - earth work 95%, masonry work 35% completed. |
No Image |
Ranyal Chichloo road (10 Km) Shangla | |||||||||||||||||||
826 (OG) |
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 60.356 | 10 | 6.8625 | 6.8625 | 3.429 | 63.785 | 49.644 | 59% |
53% May - 2020 |
Length 10 Km TST - earth work 95%, masonry work 35% completed. Revised PC-1 under process. |
No Image |
Ranyal Chichloo road (10 Km) Shangla | |||||||||||||||||||
826 (OG) |
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 60.356 | 10 | 6.8625 | 6.8625 | 0 | 60.356 | 49.644 | 59% |
50% April - 2020 |
Length 10 Km TST - earth work 95%, masonry work 35% completed. Revised PC-1 under process. |
No Image |
Ranyal Chichloo road (10 Km) Shangla | |||||||||||||||||||
826 (OG) |
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 60.356 | 10 | 6.8625 | 6.8625 | 0 | 60.356 | 49.644 | 59% |
50% March - 2020 |
Length 10 Km TST - earth work 95%, masonry work 35% completed. Revised PC-1 under process. |
No Image |
Ranyal Chichloo road (10 Km) Shangla | |||||||||||||||||||
826 (OG) |
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 60.356 | 10 | 6.8625 | 6.8625 | 0 | 60.356 | 49.644 | 59% |
50% February - 2020 |
Length 10 Km TST - earth work 95%, masonry work 35% completed. Revised PC-1 under process. |
No Image |
Ranyal Chichloo road (10 Km) Shangla | |||||||||||||||||||
826 (OG) |
140955-F/S, Design, Improvement / Widening & BT of Ranyal to Chichloo Road (10 Km), Shangla |
Shangla |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 60.356 | 10 | 6.8625 | 6.8625 | 0 | 60.356 | 49.644 | 59% |
50% January - 2020 |
Length 10 Km TST - earth work 95%, masonry work 35% completed. Revised PC-1 under process. |
No Image |
Ranyal Chichloo road (10 Km) Shangla | |||||||||||||||||||
826 (OG) |
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 176.072 | 20.983 | 152.272 | 152.272 | 55.738 | 43.641 | 64.624 | 2.817 | 98% |
37% December - 2020 |
A) Establishment of 04 Nos CHCs
1) M/B upto roof level.
2) Flooring in progress.
3) MB completed upto roof level.
4) M/B upto DPC level.
Upgradation of 11 Nos CDs to CHC level.
Work in progress on all units. |
No Image |
826 (OG) |
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 176.072 | 20.983 | 152.272 | 152.272 | 55.738 | 43.641 | 64.624 | 2.817 | 98% |
37% December - 2020 |
A) Establishment of 04 Nos CHCs
1) M/B upto roof level.
2) Flooring in progress.
3) MB completed upto roof level.
4) M/B upto DPC level.
Upgradation of 11 Nos CDs to CHC level.
Work in progress on all units. |
No Image |
826 (OG) |
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 176.072 | 20.983 | 152.272 | 152.272 | 20 | 20 | 40.983 | 2.817 | 98% |
23% October - 2020 |
A) Establishment of 04 Nos CHCs
1) M/B upto roof level.
2) Flooring in progress.
3) MB completed upto roof level.
4) M/B upto DPC level.
Upgradation of 11 Nos CDs to CHC level.
Work in progress on all units. |
No Image |
826 (OG) |
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 176.072 | 20.983 | 152.272 | 152.272 | 20 | 17.222 | 38.205 | 2.817 | 98% |
22% September - 2020 |
A) Establishment of 04 Nos CHCs
1) M/B upto roof level.
2) Flooring in progress.
3) MB completed upto roof level.
4) M/B upto DPC level.
Upgradation of 11 Nos CDs to CHC level.
Work in progress on all units. |
No Image |
826 (OG) |
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 176.072 | 20.983 | 152.272 | 152.272 | 20 | 0 | 20.983 | 2.817 | 98% |
12% August - 2020 |
A) Establishment of 04 Nos CHCs
1) M/B upto roof level.
2) Flooring in progress.
3) MB completed upto roof level.
4) M/B upto DPC level.
Upgradation of 11 Nos CDs to CHC level.
Work in progress on all units. |
No Image |
826 (OG) |
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 176.072 | 20.983 | 152.272 | 104.005 | 104.005 | 73.377 | 94.36 | 2.817 | 98% |
54% May - 2021 |
A) Establishment of 04 Nos CHCs
1) M/B upto roof level.
2) Flooring in progress.
3) MB completed upto roof level.
4) M/B upto DPC level.
Upgradation of 11 Nos CDs to CHC level.
Work in progress on all units. |
No Image |
1 Estab: of CHCs
2 Upgradation of 11 Nos CDc to CHCs level | |||||||||||||||||||
826 (OG) |
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 176.072 | 20.983 | 152.272 | 104.005 | 104.005 | 58.954 | 79.937 | 2.817 | 98% |
45% April - 2021 |
A) Establishment of 04 Nos CHCs
1) M/B upto roof level.
2) Flooring in progress.
3) MB completed upto roof level.
4) M/B upto DPC level.
Upgradation of 11 Nos CDs to CHC level.
Work in progress on all units. |
No Image |
1 Estab: of CHCs
2 Upgradation of 11 Nos CDc to CHCs level | |||||||||||||||||||
826 (OG) |
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 176.072 | 20.983 | 152.272 | 104.005 | 104.005 | 60.288 | 81.271 | 2.817 | 98% |
46% March - 2021 |
A) Establishment of 04 Nos CHCs
1) M/B upto roof level.
2) Flooring in progress.
3) MB completed upto roof level.
4) M/B upto DPC level.
Upgradation of 11 Nos CDs to CHC level.
Work in progress on all units. |
No Image |
1 Estab: of CHCs
2 Upgradation of 11 Nos CDc to CHCs level | |||||||||||||||||||
826 (OG) |
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 176.072 | 20.983 | 152.272 | 104.005 | 104.005 | 60.288 | 81.271 | 2.817 | 98% |
46% February - 2021 |
A) Establishment of 04 Nos CHCs
1) M/B upto roof level.
2) Flooring in progress.
3) MB completed upto roof level.
4) M/B upto DPC level.
Upgradation of 11 Nos CDs to CHC level.
Work in progress on all units. |
No Image |
1 Estab: of CHCs
2 Upgradation of 11 Nos CDc to CHCs level | |||||||||||||||||||
826 (OG) |
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA] |
South Waziristan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 176.072 | 20.983 | 152.272 | 55.738 | 55.738 | 55.738 | 76.721 | 2.817 | 98% |
44% January - 2021 |
A) Establishment of 04 Nos CHCs
1) M/B upto roof level.
2) Flooring in progress.
3) MB completed upto roof level.
4) M/B upto DPC level.
Upgradation of 11 Nos CDs to CHC level.
Work in progress on all units. |
No Image |
1 Estab: of CHCs
2 Upgradation of 11 Nos CDc to CHCs level | |||||||||||||||||||
826 (OG) |
191528-150392 - Establishment of 04 CHCs and Upgradation of 11 CDs to CHCs, SWA. (Umbrella) (ADP No.235/140315) [MA] |
South Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 176.072 | 23.8 | 152.272 | 0 | 0 | 0 | 23.8 | 0 |
July - 2020 |
No Image | ||