Progressive Review for the month(s) of : January - 2021, January - 2019, January - 2020, February - 2021, February - 2019, February - 2020, March - 2021, March - 2019, March - 2020, April - 2021, April - 2019, April - 2020, May - 2021, May - 2020, July - 2018, July - 2020, August - 2019, August - 2020, September - 2020, September - 2018, September - 2019, October - 2020, October - 2019, November - 2018, November - 2019, December - 2020, December - 2018, December - 2019,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Khyber
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
December - 2020
PC-I/DCE submitted to client deptt.
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Khyber
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
December - 2020
PC-I/DCE submitted to client deptt.
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Khyber
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
October - 2020
PC-I/DCE submitted to client deptt.
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Khyber
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
September - 2020
PC-I/DCE submitted to client deptt.
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Khyber
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
May - 2021
PC-I/DCE submitted to client deptt.
No Image
Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Khyber
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
April - 2021
PC-I/DCE submitted to client deptt.
No Image
Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Khyber
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
March - 2021
PC-I/DCE submitted to client deptt.
No Image
Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Khyber
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2021
PC-I/DCE submitted to client deptt.
No Image
Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Khyber
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
January - 2021
PC-I/DCE submitted to client deptt.
No Image
Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
890
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 37.25 20 18.725 18.725 11.345495 48.595495 14.042 80% 68%
December - 2019
5km- Earth work completed. Structure work in progress.
No Image
Mansehra
890
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 37.25 20 20 5 5 42.25 14.042 80% 59%
November - 2019
5km- Earth work completed. Structure work in progress.
No Image
Mansehra
890
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 37.25 20 20 5 5 42.25 14.042 80% 59%
October - 2019
5km- Earth work completed. Structure work in progress.
No Image
Mansehra
890
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 37.25 20 20 5 3.972 41.222 14.042 80% 58%
September - 2019
5km- Earth work completed. Structure work in progress.
No Image
Mansehra
890
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 37.25 20 20 5 0 37.25 14.042 80% 52%
August - 2019
5km- Earth work completed. Structure work in progress.
No Image
Mansehra
890
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 37.25 20 18.489 18.489 18.489 55.739 14.042 80% 78%
May - 2020
5km- Earth work completed. 4-km Asphalt completed. Structure, road work in progress.
No Image
Mansehra
890
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 37.25 20 18.725 18.725 17.756 55.006 14.042 80% 77%
April - 2020
5km- Earth work completed. 4-km Asphalt completed. Structure, road work in progress.
No Image
Mansehra
890
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 37.25 20 18.725 18.725 17.756 55.006 14.042 80% 77%
March - 2020
5km- Earth work completed. 4-km Asphalt completed. Structure, road work in progress.
No Image
Mansehra
890
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 37.25 20 18.725 18.725 17.756 55.006 14.042 80% 77%
February - 2020
5km- Earth work completed. 4-km Asphalt completed. Structure, road work in progress.
No Image
Mansehra
890
(OG)
170565-Construction of Roads from a) Dhgri-Moharr (1Km), b) Ghazikot-Chameri (1Km) c) Phulra-Madserian (1Km) d) Ratta Depo-Chanyal (1Km) e) Saira-Daraband (1Km), Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 71.292 37.25 20 18.725 18.725 11.345495 48.595495 14.042 80% 68%
January - 2020
5km- Earth work completed. Structure work in progress.
No Image
Mansehra
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Mohmand
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
December - 2020
Work in progress.
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Mohmand
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
December - 2020
Work in progress.
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Mohmand
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
October - 2020
Work in progress.
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Mohmand
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
September - 2020
Work in progress.
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Mohmand
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
May - 2021
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Mohmand
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
April - 2021
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Mohmand
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
March - 2021
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Mohmand
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2021
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Mohmand
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
January - 2021
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1440 0 50 50 0 0 0 0 - -
December - 2020
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1440 0 50 50 0 0 0 0 - -
December - 2020
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1440 0 50 50 0 0 0 0 - -
October - 2020
No Image
890
(OG)
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 100 2.473 0.001 0.001 0.0005 0 2.473 0 - -
September - 2018
PC-II approved.
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1440 0 50 50 0 0 0 0 - -
September - 2020
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1440 0 50 50 0 0 0 0 - -
August - 2020
No Image
890
(OG)
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 100 2.473 0.001 0.001 0.0005 0 2.473 0 - -
July - 2018
PC-II approved.
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1440 0 50 0 0 0 0 0 -
July - 2020
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1440 0 50 50 0 0 0 0 - -
May - 2021
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1440 0 50 50 0 0 0 0 - -
April - 2021
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1440 0 50 50 0 0 0 0 - -
March - 2021
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1440 0 50 50 0 0 0 0 - -
February - 2021
No Image
890
(New)
195157-Establishment/Strengthening of Trauma centers / Accidents and Emergencies at DHQs (AIP)
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1440 0 50 50 0 0 0 0 - -
January - 2021
No Image
890
(OG)
141004-F/S, Design and Rehabilitation of Roads (a) Martung to Dedal (b) Shikolai to Anawar (3 Km) (c) Awarai to Kandona (2 Km) & (d) Fiza to Alagram (1 Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 61.221 5 4.75 2.251 2.25 63.471 121.919 35% 34%
December - 2018
Length 12 Km (4 units) - earth work, SW in progress.
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
890
(OG)
141004-F/S, Design and Rehabilitation of Roads (a) Martung to Dedal (b) Shikolai to Anawar (3 Km) (c) Awarai to Kandona (2 Km) & (d) Fiza to Alagram (1 Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 61.221 5 4.75 2.251 0 61.221 121.919 35% 33%
November - 2018
Length 12 Km (4 units) - earth work, SW in progress.
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
890
(OG)
141004-F/S, Design and Rehabilitation of Roads (a) Martung to Dedal (b) Shikolai to Anawar (3 Km) (c) Awarai to Kandona (2 Km) & (d) Fiza to Alagram (1 Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 61.221 5 4.75 2.251 0 61.221 121.919 35% 33%
November - 2018
Length 12 Km (4 units) - earth work, SW in progress.
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
890
(OG)
141004-F/S, Design and Rehabilitation of Roads (a) Martung to Dedal (b) Shikolai to Anawar (3 Km) (c) Awarai to Kandona (2 Km) & (d) Fiza to Alagram (1 Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 61.221 5 4.75 4.75 3.5 64.721 121.919 35% 34%
April - 2019
Length 12 Km (4 units) - earth work, SW in progress. (P-II) Liability Rs.65 m.
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
890
(OG)
141004-F/S, Design and Rehabilitation of Roads (a) Martung to Dedal (b) Shikolai to Anawar (3 Km) (c) Awarai to Kandona (2 Km) & (d) Fiza to Alagram (1 Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 61.221 5 4.75 3.5005 3.5 64.721 121.919 35% 34%
March - 2019
Length 12 Km (4 units) - earth work, SW in progress. (P-II) Liability Rs.65 m.
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
890
(OG)
141004-F/S, Design and Rehabilitation of Roads (a) Martung to Dedal (b) Shikolai to Anawar (3 Km) (c) Awarai to Kandona (2 Km) & (d) Fiza to Alagram (1 Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 61.221 5 4.75 3.5005 3.5 64.721 121.919 35% 34%
March - 2019
Length 12 Km (4 units) - earth work, SW in progress. (P-II) Liability Rs.65 m.
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
890
(OG)
141004-F/S, Design and Rehabilitation of Roads (a) Martung to Dedal (b) Shikolai to Anawar (3 Km) (c) Awarai to Kandona (2 Km) & (d) Fiza to Alagram (1 Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 61.221 5 4.75 3.5005 2.25 63.471 121.919 35% 34%
February - 2019
Length 12 Km (4 units) - earth work, SW in progress. (P-II) Liability Rs. 65 M
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)
890
(OG)
141004-F/S, Design and Rehabilitation of Roads (a) Martung to Dedal (b) Shikolai to Anawar (3 Km) (c) Awarai to Kandona (2 Km) & (d) Fiza to Alagram (1 Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 61.221 5 4.75 2.251 2.25 63.471 121.919 35% 34%
January - 2019
Length 12 Km (4 units) - earth work, SW in progress.
No Image
1) Fainza Alagram road (1 Km)
2) Awarai to Kadona road (2 Km)
3) Shikolai to Anawar (3 Km)
4) Martong to Dedal (6 Km)