Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.378 | 54.013 | 0 | 0 | 0 | 0 | 54.013 | 0 | - |
100% December - 2019 |
Completed & H/O (3 units). |
No Image |
1) Bachelor hostel (6 suits), C&W Colony Sikandarabad
2) Cat-II residence, Sujabdarabad (1 No)
3) Cat-II residence, Sikandarabad (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.378 | 54.013 | 0 | 0 | 0 | 0 | 54.013 | 0 | - |
100% November - 2019 |
Completed & H/O (3 units). |
No Image |
1) Bachelor hostel (6 suits), C&W Colony Sikandarabad
2) Cat-II residence, Sujabdarabad (1 No)
3) Cat-II residence, Sikandarabad (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.378 | 54.013 | 0 | 0 | 0 | 0 | 54.013 | 0 | - |
100% October - 2019 |
Completed & H/O (3 units). |
No Image |
1) Bachelor hostel (6 suits), C&W Colony Sikandarabad
2) Cat-II residence, Sujabdarabad (1 No)
3) Cat-II residence, Sikandarabad (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.378 | 54.013 | 0 | 0 | 0 | 0 | 54.013 | 0 | - |
100% September - 2019 |
Completed & H/O (3 units). |
No Image |
1) Bachelor hostel (6 suits), C&W Colony Sikandarabad
2) Cat-II residence, Sujabdarabad (1 No)
3) Cat-II residence, Sikandarabad (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.378 | 54.013 | 0 | 0 | 0 | 0 | 54.013 | 0 | - |
100% August - 2019 |
Completed & H/O (3 units). |
No Image |
1) Bachelor hostel (6 suits), C&W Colony Sikandarabad
2) Cat-II residence, Sujabdarabad (1 No)
3) Cat-II residence, Sikandarabad (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.378 | 54.013 | 0 | 0 | 0 | 0 | 54.013 | 0 | - |
100% May - 2020 |
Completed & H/O (3 units). |
No Image |
1) Bachelor hostel (6 suits), C&W Colony Sikandarabad
2) Cat-II residence, Sujabdarabad (1 No)
3) Cat-II residence, Sikandarabad (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.378 | 54.013 | 0 | 0 | 0 | 0 | 54.013 | 0 | - |
100% April - 2020 |
Completed & H/O (3 units). |
No Image |
1) Bachelor hostel (6 suits), C&W Colony Sikandarabad
2) Cat-II residence, Sujabdarabad (1 No)
3) Cat-II residence, Sikandarabad (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.378 | 54.013 | 0 | 0 | 0 | 0 | 54.013 | 0 | - |
100% March - 2020 |
Completed & H/O (3 units). |
No Image |
1) Bachelor hostel (6 suits), C&W Colony Sikandarabad
2) Cat-II residence, Sujabdarabad (1 No)
3) Cat-II residence, Sikandarabad (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.378 | 54.013 | 0 | 0 | 0 | 0 | 54.013 | 0 | - |
100% February - 2020 |
Completed & H/O (3 units). |
No Image |
1) Bachelor hostel (6 suits), C&W Colony Sikandarabad
2) Cat-II residence, Sujabdarabad (1 No)
3) Cat-II residence, Sikandarabad (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53.378 | 54.013 | 0 | 0 | 0 | 0 | 54.013 | 0 | - |
100% January - 2020 |
Completed & H/O (3 units). |
No Image |
1) Bachelor hostel (6 suits), C&W Colony Sikandarabad
2) Cat-II residence, Sujabdarabad (1 No)
3) Cat-II residence, Sikandarabad (1 No) | |||||||||||||||||||
98 (OG) |
191082-070103-Opening of 5- CVDs, 5- CVCs, 6 - AICs and Upgradation of 2 CVDs to CVHs Status, Bajaur . [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 183.14 | 165.64 | 0 | 0 | 0 | 0 | 165.64 | 0 | - |
- December - 2020 |
No Image | |
98 (OG) |
191082-070103-Opening of 5- CVDs, 5- CVCs, 6 - AICs and Upgradation of 2 CVDs to CVHs Status, Bajaur . [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 183.14 | 165.64 | 0 | 0 | 0 | 0 | 165.64 | 0 | - |
- December - 2020 |
No Image | |
98 (OG) |
191082-070103-Opening of 5- CVDs, 5- CVCs, 6 - AICs and Upgradation of 2 CVDs to CVHs Status, Bajaur . [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 183.14 | 165.64 | 0 | 0 | 0 | 0 | 165.64 | 0 | - |
- October - 2020 |
No Image | |
98 (OG) |
191082-070103-Opening of 5- CVDs, 5- CVCs, 6 - AICs and Upgradation of 2 CVDs to CVHs Status, Bajaur . [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 183.14 | 165.64 | 0 | 0 | 0 | 0 | 165.64 | 0 | - |
- September - 2020 |
No Image | |
98 (OG) |
191082-070103-Opening of 5- CVDs, 5- CVCs, 6 - AICs and Upgradation of 2 CVDs to CVHs Status, Bajaur . [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 183.14 | 165.64 | 0 | 0 | 0 | 0 | 165.64 | 0 | - |
- August - 2020 |
No Image | |
98 (OG) |
191082-070103-Opening of 5- CVDs, 5- CVCs, 6 - AICs and Upgradation of 2 CVDs to CVHs Status, Bajaur . [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 183.14 | 165.64 | 0 | 0 | 0 | 0 | 165.64 | 0 | - |
July - 2020 |
No Image | |
98 (OG) |
191082-070103-Opening of 5- CVDs, 5- CVCs, 6 - AICs and Upgradation of 2 CVDs to CVHs Status, Bajaur . [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 183.14 | 165.64 | 0 | 0 | 0 | 0 | 165.64 | 0 | - |
- May - 2021 |
No Image | |
98 (OG) |
191082-070103-Opening of 5- CVDs, 5- CVCs, 6 - AICs and Upgradation of 2 CVDs to CVHs Status, Bajaur . [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 183.14 | 165.64 | 0 | 0 | 0 | 0 | 165.64 | 0 | - |
- April - 2021 |
No Image | |
98 (OG) |
191082-070103-Opening of 5- CVDs, 5- CVCs, 6 - AICs and Upgradation of 2 CVDs to CVHs Status, Bajaur . [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 183.14 | 165.64 | 0 | 0 | 0 | 0 | 165.64 | 0 | - |
- March - 2021 |
No Image | |
98 (OG) |
191082-070103-Opening of 5- CVDs, 5- CVCs, 6 - AICs and Upgradation of 2 CVDs to CVHs Status, Bajaur . [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 183.14 | 165.64 | 0 | 0 | 0 | 0 | 165.64 | 0 | - |
- February - 2021 |
No Image | |
98 (OG) |
191082-070103-Opening of 5- CVDs, 5- CVCs, 6 - AICs and Upgradation of 2 CVDs to CVHs Status, Bajaur . [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 183.14 | 165.64 | 0 | 0 | 0 | 0 | 165.64 | 0 | - |
- January - 2021 |
No Image | |
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.375 | 62.309 | 0 | 0 | 0 | 0 | 62.309 | 0.066 | - |
100% December - 2019 |
Completed & H/O. |
No Image |
1) Category-III residence, Bannu | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.375 | 62.309 | 0 | 0 | 0 | 0 | 62.309 | 0.066 | - |
100% November - 2019 |
Completed & H/O. |
No Image |
1) Category-III residence, Bannu | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.375 | 62.309 | 0 | 0 | 0 | 0 | 62.309 | 0.066 | - |
100% October - 2019 |
Completed & H/O. |
No Image |
1) Category-III residence, Bannu | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.375 | 62.309 | 0 | 0 | 0 | 0 | 62.309 | 0.066 | - |
100% September - 2019 |
Completed & H/O. |
No Image |
1) Category-III residence, Bannu | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.375 | 62.309 | 0 | 0 | 0 | 0 | 62.309 | 0.066 | - |
100% August - 2019 |
Completed & H/O. |
No Image |
1) Category-III residence, Bannu | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.375 | 62.309 | 0 | 0 | 0 | 0 | 62.309 | 0.066 | - |
100% May - 2020 |
Completed & H/O. |
No Image |
1) Category-III residence, Bannu | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.375 | 62.309 | 0 | 0 | 0 | 0 | 62.309 | 0.066 | - |
100% April - 2020 |
Completed & H/O. |
No Image |
1) Category-III residence, Bannu | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.375 | 62.309 | 0 | 0 | 0 | 0 | 62.309 | 0.066 | - |
100% March - 2020 |
Completed & H/O. |
No Image |
1) Category-III residence, Bannu | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.375 | 62.309 | 0 | 0 | 0 | 0 | 62.309 | 0.066 | - |
100% February - 2020 |
Completed & H/O. |
No Image |
1) Category-III residence, Bannu | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 62.375 | 62.309 | 0 | 0 | 0 | 0 | 62.309 | 0.066 | - |
100% January - 2020 |
Completed & H/O. |
No Image |
1) Category-III residence, Bannu | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.391 | 27.5 | 0 | 0 | 0 | 0 | 27.5 | 3.891 | - |
88% December - 2019 |
Main building - flooring completed, BW and joinery in progress.
Deamnd Rs. 2.5 m for complteion |
No Image |
Construction of Bachelor Hostel (6 suits) in District Buner PK-79 | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.391 | 27.5 | 0 | 0 | 0 | 0 | 27.5 | 3.891 | - |
88% November - 2019 |
Main building - flooring, BW and joinery in progress.
Deamnd Rs. 2.5 m for complteion |
No Image |
Construction of Bachelor Hostel (6 suits) in District Buner PK-79 | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.391 | 27.5 | 0 | 0 | 0 | 0 | 27.5 | 3.891 | - |
88% October - 2019 |
Main building - flooring, BW and joinery in progress.
Deamnd Rs. 2.5 m for complteion |
No Image |
Construction of Bachelor Hostel (6 suits) in District Buner PK-79 | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.391 | 27.5 | 0 | 0 | 0 | 0 | 27.5 | 3.891 | - |
88% September - 2019 |
Main building - flooring, BW and joinery in progress. |
No Image |
Construction of Bachelor Hostel (6 suits) in District Buner PK-79 | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.391 | 27.5 | 0 | 0 | 0 | 0 | 27.5 | 3.891 | - |
88% August - 2019 |
Main building - flooring, BW and joinery in progress. |
No Image |
Construction of Bachelor Hostel (6 suits) in District Buner PK-79 | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.391 | 27.5 | 3.623 | 3.623 | 3.623 | 0 | 27.5 | 0.268 | 99% |
88% May - 2020 |
Main building - flooring completed, BW and joinery in progress.
Deamnd Rs. 3 m for complteion |
No Image |
Construction of Bachelor Hostel (6 suits) in District Buner PK-79 | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.391 | 27.5 | 3.623 | 3.623 | 3.623 | 0 | 27.5 | 0.268 | 99% |
88% April - 2020 |
Main building - flooring completed, BW and joinery in progress.
Deamnd Rs. 3 m for complteion |
No Image |
Construction of Bachelor Hostel (6 suits) in District Buner PK-79 | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.391 | 27.5 | 3.623 | 3.623 | 3.623 | 0 | 27.5 | 0.268 | 99% |
88% March - 2020 |
Main building - flooring completed, BW and joinery in progress.
Deamnd Rs. 3 m for complteion |
No Image |
Construction of Bachelor Hostel (6 suits) in District Buner PK-79 | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.391 | 27.5 | 3.623 | 3.623 | 3.623 | 0 | 27.5 | 0.268 | 99% |
88% February - 2020 |
Main building - flooring completed, BW and joinery in progress.
Deamnd Rs. 3 m for complteion |
No Image |
Construction of Bachelor Hostel (6 suits) in District Buner PK-79 | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.391 | 27.5 | 0 | 0 | 0 | 0 | 27.5 | 3.891 | - |
88% January - 2020 |
Main building - flooring completed, BW and joinery in progress.
Deamnd Rs. 3 m for complteion |
No Image |
Construction of Bachelor Hostel (6 suits) in District Buner PK-79 | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.447 | 37.776 | 0 | 0 | 0 | 0 | 37.776 | 0 | - |
100% December - 2019 |
Completed. |
No Image |
1) Bachelor Hostel (6 units)
2) Cat-III Residence (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.447 | 37.776 | 0 | 0 | 0 | 0 | 37.776 | 0 | - |
100% November - 2019 |
Completed. |
No Image |
1) Bachelor Hostel (6 units)
2) Cat-III Residence (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.447 | 37.776 | 0 | 0 | 0 | 0 | 37.776 | 0 | - |
100% October - 2019 |
Completed. |
No Image |
1) Bachelor Hostel (6 units)
2) Cat-III Residence (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.447 | 37.776 | 0 | 0 | 0 | 0 | 37.776 | 0 | - |
100% September - 2019 |
Completed. |
No Image |
1) Bachelor Hostel (6 units)
2) Cat-III Residence (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.447 | 37.776 | 0 | 0 | 0 | 0 | 37.776 | 0 | - |
100% August - 2019 |
Completed. |
No Image |
1) Bachelor Hostel (6 units)
2) Cat-III Residence (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.447 | 37.776 | 0 | 0 | 0 | 0 | 37.776 | 0 | - |
100% May - 2020 |
Completed. |
No Image |
1) Bachelor Hostel (6 units)
2) Cat-III Residence (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.447 | 37.776 | 0 | 0 | 0 | 0 | 37.776 | 0 | - |
100% April - 2020 |
Completed. |
No Image |
1) Bachelor Hostel (6 units)
2) Cat-III Residence (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.447 | 37.776 | 0 | 0 | 0 | 0 | 37.776 | 0 | - |
100% March - 2020 |
Completed. |
No Image |
1) Bachelor Hostel (6 units)
2) Cat-III Residence (1 No) | |||||||||||||||||||
98 (OG) |
120626-Construction of Residences & Bachelor Hostel in all District headquarters for Government Servants in Khyber Pakhtunkhwa. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 37.447 | 37.776 | 0 | 0 | 0 | 0 | 37.776 | 0 | - |
100% February - 2020 |
Completed. |
No Image |
1) Bachelor Hostel (6 units)
2) Cat-III Residence (1 No) | |||||||||||||||||||