Bhunja Freedabad Road

Bhunja Freedabad Road

Partially restored
25 January, 2026 Mansehra XEN H/W MANSEHRA

This activity provides a detailed overview of the operational status of the Road Bhunja Freedabad Road, recorded on 25 January, 2026. The affected site is situated within the Mansehra district, operating under the administrative jurisdiction of XEN H/W MANSEHRA. The infrastructure has been primarily affected by Snow Clearance, Land Sliding, encompassing a total span of 9 Kilometers.

Environmental conditions at the site indicated an average recorded snow depth of 2.00 inches. Restoration and clearance efforts were facilitated by the deployment of Excavator , which remained in active operation for a duration of 72 hours .

The affected area has been mapped using geographic coordinates. The section starts at 73.516608, 34.654496 and ends at 73.523794, 34.625244. For location reference and navigation, view the route on Google Maps.

The road is now partially accessible; however, motorists are advised to proceed with caution as restoration work continues to achieve full safety and normal traffic flow.

The following photographs provide a visual record of the site conditions before and after the activity, illustrating the extent of the affected area and the improvements achieved through the executed operations.

Before Images (1)
After Images (1)