Chitral Upper Damages Detail - Monsoon (2025)

Report Date: July 27, 2025 Infrastructure Type: Road Total Damages: 7
Reported by:
Engr. Zia Ur Rehman (XEN UPPER CHITRAL)
2
Affected Roads
7
Total Damages
3.07
Damaged Length (KM)
0
Fully Restored
6
Partially Restored
1
Not Restored
Road Damages
S# Road Name Total Length Status Damaged Length Dated
1 Mastuj Broghil Pass Road (6 Damages) 149 (KM) 1 Partially restored 0.3 (KM) Jul 22, 2025
2 Partially restored 0.06 (KM) Jul 09, 2025
3 Partially restored 1 (KM) Jul 09, 2025
4 Partially restored 0.36 (KM) Jul 02, 2025
Remarks: PARTIALLY RESTORED
Reported by: XEN UPPER CHITRAL
5 Partially restored 0.45 (KM) Jul 02, 2025
Remarks: PARTIALLY RESTORED
Reported by: XEN UPPER CHITRAL
6 Partially restored 0.30 (KM) Jul 02, 2025
Remarks: PARTIALLY RESTORED
Reported by: XEN UPPER CHITRAL
2 Awi meragram Road 10 (KM) Not restored 0.6 (KM) Jul 02, 2025
Remarks: In 2022, the flood washed away the road. This department then acquired land from locals and shifted the road's alignment to reopen it for traffic. now in 2025 another flood hit the area and again washed away the road. this time the locals are not providing lands for the restoration of road and they are demanding the previous year's and this year's land amount to be paid.
Reported by: XEN UPPER CHITRAL