Report Date:
July 27, 2025
Infrastructure Type:
Road
Total Damages:
8
Reported by:
Engr. Sohail Idrees
(Managing Director PKHA)
,
Muhammad Zahid
(XEN H/W HARIPUR)
Affected Roads
Total Damages
Damaged Length
(KM)
Fully Restored
Partially Restored
Not Restored
Road Damages
S# | Road Name | Total Length | Status | Damaged Length | Dated |
---|---|---|---|---|---|
1 | S-12 Haripur Chppar Chandur Shara-e-Tanawal to | 72 (KM) | Partially restored | 0.030 (KM) | Jul 06, 2025 |
Remarks: Vented Causeway has been damaged and the wingwall downstream needs to be restored. The Cause Way has been opened manually by labour.
Reported by:
Managing Director PKHA
|
|||||
2 | Tarnawa to Kohala Bala | 35 (KM) | Partially restored | 14 (KM) | Jul 06, 2025 |
Remarks: The amount is for clearance of debris, sli[ps,ersosion and leveling of Kacha Road only. The boulders on site have been removed Primaly with help of locals,
Reported by:
Managing Director PKHA
|
|||||
3 | Ghazi-Serikot-Panian Road (S-1) | 40 (KM) | Not restored | 0.038 (KM) | Jul 06, 2025 |
Remarks: The restoration should be done at the earliest to avoid any damage to the remaining road structure.
Reported by:
Managing Director PKHA
|
|||||
4 | Haripur Sarai Nimat Khan road | 14 (KM) | Partially restored | 14 (KM) | Jul 02, 2025 |
Remarks: Retaining structure damaged.
Reported by:
XEN H/W HARIPUR
|
|||||
5 | Karrach Road | 4 (KM) | Partially restored | 4 (KM) | Jul 02, 2025 |
Remarks: Retaining structure damaged & road is partially opened for traffic.
Reported by:
XEN H/W HARIPUR
|
|||||
6 | Talhad Road. | 3 (KM) | Partially restored | 3 (KM) | Jul 02, 2025 |
Remarks: Retaining structure damaged on said road. An amount of Rs. 5.000 (M) is restoration of damaged structure.
Reported by:
XEN H/W HARIPUR
|
|||||
7 | Nartopa Road | 12 (KM) | Partially restored | 12 (KM) | Jul 02, 2025 |
Remarks: Retaining wall along road side damaged due to heavy rain fall. An amount of Rs. 2.500 (M) required for restoration of damaged structure.
Reported by:
XEN H/W HARIPUR
|
|||||
8 | Sahki Khenian road | 7 (KM) | Partially restored | 03 (KM) | Jul 02, 2025 |
Remarks: Landslide occurred at the site due to heavy rainfall. The debris has been partially cleared and the road has been restored for traffic
Reported by:
XEN H/W HARIPUR
|