Report Date:
July 27, 2025
Infrastructure Type:
Road
Total Damages:
3
Reported by:
Engr. Sohail Idrees
(Managing Director PKHA)
Affected Roads
Total Damages
Damaged Length
(KM)
Fully Restored
Partially Restored
Not Restored
Road Damages
S# | Road Name | Total Length | Status | Damaged Length | Dated |
---|---|---|---|---|---|
1 | Sararogha to Makeen (2 Damages) | 33 (KM) | 1 Partially restored | .37 (KM) | Jul 24, 2025 |
2 Partially restored | .50 (KM) | Jul 24, 2025 | |||
Remarks: this portion in hilly terrain and one side is hill and the other side of road is river ,
Reported by:
Managing Director PKHA
|
|||||
2 | Khergi to Sararogha | 44 (KM) | Not restored | .171 (KM) | Jul 08, 2025 |
Remarks: the Retaining wall is completely damaged ,it is very important to restore timely other wise the road will partially or fully washed out .
Reported by:
Managing Director PKHA
|