Stories
Loading...

Torghar Damages Detail - Monsoon (2025)

Report Date: July 27, 2025 Infrastructure Type: Road Total Damages: 10
Reported by:
Hilal Hussain Shah (XEN TORGHAR)
10
Affected Roads
10
Total Damages
26
Damaged Length (KM)
1
Fully Restored
9
Partially Restored
0
Not Restored
Road Damages
S# Road Name Total Length Status Damaged Length Dated
1 Bartooni Road 7.9 (KM) Partially restored 1 (KM) Jul 02, 2025
2 Mera Mada Khail to Gooder Road 10 (KM) Partially restored 0 (KM) Jul 02, 2025
3 Tilli Kandao to Tilli Baba Ziarat Road 5.5 (KM) Partially restored 0 (KM) Jul 02, 2025
4 Gavi Moratta Road 19 (KM) Partially restored 0 (KM) Jul 02, 2025
5 Thakot Darband Road 64 (KM) Partially restored 8 (KM) Jul 02, 2025
6 Pakbun Road 16 (KM) Fully restored 1 (KM) Jul 02, 2025
7 Judbah to Shattal Jatka Road 20.8 (KM) Partially restored 0 (KM) Jul 02, 2025
8 Judbah to Gitto Road 16 (KM) Partially restored 6 (KM) Jul 02, 2025
9 Shagai to Kalish Road 11.9 (KM) Partially restored 1 (KM) Jul 02, 2025
10 Zeezari Shingle Dar Road 10 (KM) Partially restored 9 (KM) Jul 02, 2025