News & Events

  1. Engr. Zahid Arif assumed charge as Secretary C&W on 24-06-2011.
  2. Inspection of Nowshera roads by Chief Engineer (Centre) is scheduled on 07-09-2011.
  3. AA of the schemes discussed in the DDWP meeting held on 24-08-2011 issued.
  4. Review of ADP schemes will be starting from 21-08-2011 under the Chairmanship of Director (P&M).
  5. Engr. Farooq Azam Chief CDO issued letter to all XEN offices to submit Road Inventory data by 26-08-2011.
  6. Data Entry started in MIS Modules.
  7. Digitization of remaining Districts started.

DISTRICT ROADS − ON-GOING

ADP NO. SchemeName Aamount AllocationCFY CFYExpdr cost(MM) District
316 (OG) 30845-Construction of bridge at Misribanda, Nowshera. 103.85 0.00 81.808 Nowshera
317 (OG) 30889-Extention, Improvement and B/T of road from Feza to Topal via Sarqilla Bazar, Chamo District Bunair 200.22 20.00 0.00 82.737 Buner
318 (OG) 30902-Construction of bridges at Toru Godar Ghara, Ghala Dher, Bago Banda and Mayar District Mardan 153.59 50.00 0.00 143.072 Mardan
319 (OG) 31122-Improvement and widening of roads from Matta to Fazil Banda, Bagh Dheri to Lalkoo, Berum to Shor Gut, Swat 317.59 10.51 0.00 205.016 Swat
320 (OG) 31234-Construction of bridge at Pir Sabak, Nowshera 104.85 112.57 0.00 72.863 Nowshera
321 (OG) 50209-Construction, BT & Rehabilitation of 14 Kms road in District Kohistan 172.92 20.00 0.00 136.823 Kohistan
322 (OG) 60128-Construction of Pir Sohawa Kohala Bala road District Haripur (18.5 Kms) 301.25 36.10 0.00 211.636 Haripur
323 (OG) 60323-Construction of RCC Bridge on River Swat along with approch road at Thana - Malakand 144.31 49.61 0.00 80.948 Malakand
324 (OG) 70210-Construction of Chitral Bazar Bye-pass road District Chitral (CMD) 542.67 23.37 0.00 249.5 Chitral
325 (OG) 70636-Construction & BT of Chakesar Dandai Road (27 Kms) District Shangla 339.94 146.50 0.00 155.3 Shangla
326 (OG) 70738-Feasibility/ Construction of Bridge of Maroor road  Pattan, Kohistan 12.30 58.83 0.00 7.03 Kohistan
327 (OG) 70759-Reconstruction of road alongwith bridge approach road Batkhela to Badwan (4.5-Kms) Malakand 344.00 5.27 0.00 225.045 Malakand
328 (OG) 70768-Construction of Bridge ovef stream of village Batamoori, Battagram 29.30 174.00 0.00 16.277 Battagram
329 (OG) 70769-Construction RCC Bridge over stream of village Battagram for GGHS village Battagram District Battagram 26.68 13.02 0.00 19.6 Battagram
330 (OG) 80574-Construction & BT of road from Bagi Qamar to Village Kundal Phase-III (56 Kms) DI.Khan 939.83 7.08 0.00 616.45 D.I.Khan
331 (OG) 80668-Construction of alternate road Lachi to Hangu - Thall - Parachinar road (41.80 Kms) 655.05 157.34 0.00 125.688 Provincial
332 (OG) 80669-Widening/Black topping of remaining portion of Dalazak Road from Yousaf Abad Bridge to Bacha Khan Road Peshawar (3 Kms) 91.59 80.00 0.00 58 Peshawar
333 (OG) 90016-Construction of remaining 12 Km Siraj Khel road District Karak 115.80 33.59 0.00 60 Karak
334 (OG) 90023-Construction/ Improvement & B/T of road from Malandri foothill to Masoom Baba top in District Mardan (9-Km) 244.52 55.80 0.00 162 Mardan
335 (OG) 90028-Construction of Sarbanda road (1.5 Km) District Dir Lower 15.00 82.52 0.00 0 Dir Lower
336 (OG) 90069-Improvement & Widening of Pabbi Cherat Road, District Nowshera 300.04 10.00 0.00 256.52 Nowshera
337 (OG) 90226-Construction of RCC bridge in village Baghicha Sufaid Sung PF-7 District Peshawar 39.76 60.54 0.00 14.576 Peshawar
338 (OG) 90424-Improvement & Widening of Pajaggi Chagharmatti Road (Balance Portion) District Peshawar 314.41 25.18 0.00 130 Peshawar
339 (OG) 90471-Repair, rehabilitation and improvement of Mardan Bakhshali road, Mardan 70.56 70.00 0.00 27.593 Mardan
340 (OG) 100005-F/S and reconstruction of bridge on Nurangi at Kalo Khan Swabi 29.90 42.97 0.00 15.57 Swabi
341 (OG) 100006-Construction of suspension bridge bans over river Kunhar Mansehra 9.84 14.33 0.00 2.483 Mansehra
342 (OG) 100007-Rehabilitation of suspension bridge Soach Mansehra 9.71 3.35 0.00 4 Mansehra
343 (OG) 100011-Widening of Orakzai main road 20 Km District Kohat President Directive 200.89 5.71 0.00 40 Kohat
344 (OG) 100042-Improvement and Rehabilitation of Mardan Katlang road upto Chihar (14 Km) District Mardan 389.44 50.00 0.00 6 Mardan
345 (OG) 100048-Rehabilitation of 17 KMs Roads in PK-48 District Abbottabad 117.00 100.00 0.00 0 Abbottabad
346 (OG) 100382-Construction of Sairay Kalkot to Thall Kumrat road, 10 Kms, Dir Upper 144.07 40.81 0.00 0 Dir Upper
347 (OG) 100460-Improvement & widening of road from Utmanzai Branch to Mir Aad Pul via Sarki Shakh No.5 (115 Kms) Sub Head: 3.5 Kms Phase-I, District Charsadda 49.97 22.14 0.00 45.875 Charsadda
348 (OG) 110305-Rehabilitation of Kotla Mohsin Khan /Dheri Baghbanan road  taking off from Nothia/Landi Arbab chowk 1.3 km District Peshawar 17.50 29.97 0.00 7.5 Peshawar
10.00
349 (New) 100053-Construction of road from Odigram to Lal Qilla Maidan (10 Km) Dir Lower 100.00 0.00 0 Dir Lower
350 (New) 100054-Improvement & Widening of Ama Khel Mulazai Road (5 Km) District Tank 100.00 20.00 0.00 0 Tank
351 (New) 100055-Rehabilitation of Saiful Malook Road (8.55 Km) District Mansehra 80.00 40.00 0.00 0 Mansehra
352 (New) 100381-Construction of Topi Utla road including Bada Bridge District Swabi 575.00 20.00 0.00 0 Swabi
353 (New) 110200-Construction of kota bypass road district Swabi 25.00 60.00 0.00 0 Swabi
354 (New) 110621-Feasibility study/ realignment of Chitral Garam Chashma Road. 0.50 25.00 0.00 0 Chitral