Battagram Damages Detail - Monsoon (2025)

Report Date: July 30, 2025 Infrastructure Type: Road Total Damages: 9
Reported by:
Waqas (XEN BATTAGRAM)
8
Affected Roads
9
Total Damages
4.26
Damaged Length (KM)
4
Fully Restored
5
Partially Restored
0
Not Restored
Road Damages
S# Road Name Total Length Status Damaged Length Dated
1 Battagram KuzabandaChattar Top 14 (KM) Partially restored 0.300 (KM) Jul 29, 2025
2 Battagram Paimal Road (2 Damages) 12 (KM) 1 Fully restored 0.210 (KM) Jul 17, 2025
2 Partially restored 0.300 (KM) Jul 08, 2025
3 Battagram shumlai hill 17 (KM) Fully restored 0.350 (KM) Jul 16, 2025
4 Dumrai Road 3 (KM) Fully restored 0.05 (KM) Jul 09, 2025
5 Rashang Road 5 (KM) Fully restored 0.10 (KM) Jul 09, 2025
6 Karag jabaa gantar 7 (KM) Partially restored 0.550 (KM) Jul 08, 2025
7 Sajbyar Road 8.6 (KM) Partially restored 1.9 (KM) Jul 08, 2025
8 Thakot Bana Road 29 (KM) Partially restored 0.5 (KM) Jul 08, 2025