Report Date:
August 21, 2025
Infrastructure Type:
Road
Total Damages:
4
Reported by:
Muhammad Adnan
(XEN LOWER CHITRAL)
Affected Roads
Total Damages
Damaged Length
(KM)
Fully Restored
Partially Restored
Not Restored
Road Damages Overview
S# | Road Name & Location | Total Length | Status | Damaged Length | Damage Coordinates | Date Reported |
---|---|---|---|---|---|---|
1
|
Arkari Valley
|
32
(KM) |
Fully restored |
10
(KM) |
No damage coordinates |
Aug 15, 2025
03:00 PM |
Remarks:
Work on restoration is in progress
Reported by:
XEN LOWER CHITRAL
|
||||||
2
|
Prait Road
No coordinates available
|
5
(KM) |
Partially restored |
0.5
(KM) |
No damage coordinates |
Aug 15, 2025
02:51 PM |
Remarks:
Work on restoration (Blasting) is in progress
Reported by:
XEN LOWER CHITRAL
|
||||||
3
|
Madaklasht Road
No coordinates available
|
45
(KM) |
Fully restored |
10
(KM) |
No damage coordinates |
Jul 30, 2025
11:20 AM |
Remarks:
Road has been temporarily restored. Further work in progress
Reported by:
XEN LOWER CHITRAL
|
||||||
4
|
Faizabad Hone road, Shiaqotak, Doomshor Orguch road
No coordinates available
|
7
(KM) |
Fully restored |
0.2
(KM) |
No damage coordinates |
Jun 30, 2025
09:50 AM |
Remarks:
Due to high flood level, the said retaining wall was damaged which was restored immediately. However rehabilitation of the retaining wall is required
Reported by:
XEN LOWER CHITRAL
|