Report Date:
August 21, 2025
Infrastructure Type:
Road
Total Damages:
46
Reported by:
Engr. Waqas
(XEN H/W SWABI)
Engr. Sohail Idrees
(Managing Director PKHA)
Affected Roads
Total Damages
Damaged Length
(KM)
Fully Restored
Partially Restored
Not Restored
Road Damages Overview
S# | Road Name & Location | Total Length | Status | Damaged Length | Damage Coordinates | Date Reported |
---|---|---|---|---|---|---|
1
|
Kammah road Jalbai
|
2.30
(KM) |
Not restored |
0.04
(KM) |
Aug 21, 2025
01:24 PM |
|
Remarks:
Nil
Reported by:
XEN H/W SWABI
|
||||||
2
|
Bakyano Road pabaini
No coordinates available
|
3.00
(KM) |
Not restored |
1
(KM) |
No damage coordinates |
Aug 21, 2025
01:23 PM |
Remarks:
The subject Causway damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
3
|
Pabini Meenai Road
|
1.50
(KM) |
Partially restored |
0.5
(KM) |
Aug 21, 2025
01:18 PM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
4
|
Saleem Khan Loya Lar
No coordinates available
|
2.00
(KM) |
Not restored |
0.5
(KM) |
Aug 21, 2025
01:09 PM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
5
|
Umarabad Qaziabad Link Road
|
1.78
(KM) |
Not restored |
0.2
(KM) |
Aug 21, 2025
12:55 PM |
|
Remarks:
Nil
Reported by:
XEN H/W SWABI
|
||||||
6
|
Jhanda Pajmand Road along with Culverts
|
1.00
(KM) |
Not restored |
0.5
(KM) |
Aug 21, 2025
12:51 PM |
|
Remarks:
The subject Causway damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
7
|
Baghe Haram Lar Tordher
|
1
(KM) |
Not restored |
0.1
(KM) |
Aug 21, 2025
12:48 PM |
|
8
|
FAQIR KHEL TO LANGARKOT LAR JALBAI
|
1.5
(KM) |
Not restored |
0.6
(KM) |
Aug 21, 2025
12:25 PM |
|
Remarks:
Nil
Reported by:
XEN H/W SWABI
|
||||||
9
|
Tordher Alladher Bypass Road
|
10
(KM) |
Not restored |
1.8
(KM) |
Aug 21, 2025
12:01 PM |
|
10
|
Kotha Sogandih Road
|
1.6
(KM) |
Not restored |
0.75
(KM) |
Aug 21, 2025
11:57 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
11
|
Gandaf village Road
|
1.5
(KM) |
Not restored |
1.3
(KM) |
Aug 21, 2025
11:54 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
12
|
Lahore Ground Road
|
1
(KM) |
Not restored |
0.2
(KM) |
Aug 21, 2025
11:53 AM |
|
13
|
Dewal Village Road
|
2.5
(KM) |
Not restored |
1.5
(KM) |
Aug 21, 2025
11:51 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
14
|
Pola road
|
3.5
(KM) |
Not restored |
2.5
(KM) |
Aug 21, 2025
11:48 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
15
|
Mazghund To nogram
|
7
(KM) |
Partially restored |
6
(KM) |
Aug 21, 2025
11:43 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
16
|
Sokhta Lar Zaida
|
2
(KM) |
Not restored |
0.1
(KM) |
Aug 21, 2025
11:42 AM |
|
17
|
Amrai Pyan
|
2
(KM) |
Not restored |
1.5
(KM) |
Aug 21, 2025
11:39 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
18
|
Meenai Shakarai Road
|
1.5
(KM) |
Not restored |
1.5
(KM) |
Aug 21, 2025
11:36 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
19
|
Takail Gajai Road
|
3
(KM) |
Not restored |
3
(KM) |
Aug 21, 2025
11:32 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
20
|
Panawal Road
|
3
(KM) |
Fully restored |
2
(KM) |
Aug 21, 2025
11:29 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
21
|
Chak sokilay road
|
2.5
(KM) |
Fully restored |
1.3
(KM) |
Aug 21, 2025
11:26 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
22
|
Dewal to Katgram road Gero Road
|
13
(KM) |
Not restored |
13
(KM) |
Aug 21, 2025
11:24 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
23
|
Deval garai road
|
4.5
(KM) |
Not restored |
2.5
(KM) |
Aug 21, 2025
11:21 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
24
|
Bada to shnai road
|
8.5
(KM) |
Partially restored |
8.5
(KM) |
Aug 21, 2025
11:18 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
25
|
Mangal chai sarkoi payan road
|
5.1
(KM) |
Partially restored |
4.5
(KM) |
Aug 21, 2025
11:14 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
26
|
Topi Matoona Road
|
2.2
(KM) |
Not restored |
0.75
(KM) |
Aug 21, 2025
11:10 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
27
|
Moterway Road Nobat Abad cheeno Side
|
2.3
(KM) |
Not restored |
1.2
(KM) |
Aug 21, 2025
11:06 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
28
|
Cheenu Lar
|
1.19
(KM) |
Not restored |
1.1
(KM) |
Aug 21, 2025
11:03 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
29
|
Utla Village/Dam Road
|
4
(KM) |
Partially restored |
2
(KM) |
Aug 21, 2025
10:54 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
30
|
Dagai Road i/c village Road
|
3
(KM) |
Not restored |
2.8
(KM) |
Aug 21, 2025
10:47 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
31
|
Sathketar treet bagan Road
|
4
(KM) |
Not restored |
3.6
(KM) |
Aug 21, 2025
10:46 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
32
|
Pikrarry to Gabai
|
5
(KM) |
Partially restored |
2.6
(KM) |
Aug 21, 2025
10:43 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
33
|
Malak Abad Road
|
3.6
(KM) |
Not restored |
1
(KM) |
No damage coordinates |
Aug 21, 2025
10:40 AM |
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
34
|
Takail To Malak Abad
|
5
(KM) |
Partially restored |
5
(KM) |
No damage coordinates |
Aug 21, 2025
10:37 AM |
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
35
|
Takail Sandawa
|
4.5
(KM) |
Partially restored |
3
(KM) |
Aug 21, 2025
10:34 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
36
|
Besak Road
|
5
(KM) |
Partially restored |
2.5
(KM) |
Aug 21, 2025
10:28 AM |
|
Remarks:
The subject Road damged due heavy Flood and cloud Brust.
Reported by:
XEN H/W SWABI
|
||||||
37
|
Kalu dher Turlandi road
|
2
(KM) |
Not restored |
0.4
(KM) |
Aug 21, 2025
07:19 AM |
|
38
|
Bangzara Road KSK
|
2
(KM) |
Not restored |
0.7
(KM) |
Aug 20, 2025
01:38 PM |
|
39
|
Naranji high school Road
|
0.8
(KM) |
Not restored |
0.1
(KM) |
Aug 20, 2025
01:04 PM |
|
40
|
Jalbai main road
|
2.5
(KM) |
Not restored |
0.6
(KM) |
Aug 20, 2025
12:30 PM |
|
41
|
Bada Dalorie Road
|
16.00
(KM) |
Partially restored |
7.5
(KM) |
Aug 20, 2025
12:11 PM |
|
Remarks:
The subject Road are damged in different portion at Bada Dalore to mangle due heavy Flood and cloud Brust
Reported by:
XEN H/W SWABI
|
||||||
42
|
Malak Cham Lar
|
1.5
(KM) |
Not restored |
0.4
(KM) |
Aug 20, 2025
11:53 AM |
|
Remarks:
The Road and pathway protection wall along the nullah at length of 30 meters has been fully damaged
Reported by:
XEN H/W SWABI
|
||||||
43
|
Faqeer abad road Jalbai
|
0.40
(KM) |
Not restored |
0.4
(KM) |
Aug 20, 2025
11:26 AM |
|
Remarks:
Nil
Reported by:
XEN H/W SWABI
|
||||||
44
|
Jalsai to Chota Lahor
|
2.23
(KM) |
Not restored |
0.1
(KM) |
Aug 20, 2025
10:46 AM |
|
Remarks:
The approaches, slab culverts, asphalt and side walls have been damaged
Reported by:
XEN H/W SWABI
|
||||||
45
|
Swabi - Topi Section of P-Hway (S-1) 19 km
No coordinates available
|
19
(KM) |
Fully restored |
4
(KM) |
Aug 19, 2025
12:40 AM |
|
Remarks:
Damage & Silting up of Drains, Damage to Protection work of Bada Bridge
Reported by:
Managing Director PKHA
|
||||||
46
|
Topi - Gadoon - Beer Gali (46km)
|
46
(KM) |
Partially restored |
1.5
(KM) |
Aug 19, 2025
12:21 AM |
|
Remarks:
R/walls, landslides and shoulders are washed away at various sections from km 12 to 44. Sub-structure and protection of besak bridge is damaged.
Reported by:
Managing Director PKHA
|