Report Date:
January 27, 2026
Infrastructure Type:
Road
Total Damages:
1
Reported by:
Engr. Sohail Idrees
(Managing Director PKHA)
Affected Roads
Total Damages
Damaged Length
(KM)
Fully Restored
Partially Restored
Not Restored
Road Damages Overview
| S# | Road Name & Location | Total Length | Status | Damaged Length | Damage Coordinates | Date Reported |
|---|---|---|---|---|---|---|
|
1
|
Beer to Kalangir on Haripur -Chappar Road Section of Provincial Highway S-12
|
17
(KM) |
Partially restored |
0.067
(KM) |
Jan 25, 2026
10:30 AM |
|
|
Remarks:
Tractor was also used for 4 hours to clear the land slide.
Reported by:
Managing Director PKHA
|
||||||