Stories
Loading...

Lagharai to Ghakhi pass Road

Lagharai to Ghakhi pass Road

Fully restored
9 April, 2026 Bajaur XEN H/W BAJAUR

This activity provides a detailed overview of the operational status of the Road Lagharai to Ghakhi pass Road, recorded on 9 April, 2026. The affected site is situated within the Bajaur district, operating under the administrative jurisdiction of XEN H/W BAJAUR. The infrastructure has been primarily affected by Land Sliding, encompassing a total span of 0.27 Kilometers.

Restoration and clearance efforts were facilitated by the deployment of Tractor , which remained in active operation for a duration of 17 hours . In a formal assessment of the situation, the reporting officer noted with remarks: Fully Restore.

The affected area has been mapped using geographic coordinates. The section starts at 71.494681, 34.726606 and ends at 71.385221, 34.827039. For location reference and navigation, view the route on Google Maps.

All required restoration activities have been successfully completed, and the road is now fully operational, allowing safe and uninterrupted movement of traffic.

The following photographs provide a visual record of the site conditions before and after the activity, illustrating the extent of the affected area and the improvements achieved through the executed operations.

Before Images (1)
After Images (1)
CWD