Report Date:
January 27, 2026
Infrastructure Type:
Road
Total Damages:
38
Reported by:
Najm Ud Din
(XEN DIR UPPER)
Affected Roads
Total Damages
Damaged Length
(KM)
Fully Restored
Partially Restored
Not Restored
Road Damages Overview
| S# | Road Name & Location | Total Length | Status | Damaged Length | Damage Coordinates | Date Reported |
|---|---|---|---|---|---|---|
|
1
|
Pataw Nagril Road
|
12
(KM) |
Not restored |
12
(KM) |
Jan 26, 2026
01:12 PM |
|
|
2
|
kadikhel dara Road
|
8
(KM) |
Partially restored |
5
(KM) |
Jan 26, 2026
01:00 PM |
|
|
3
|
badalai main road
|
10
(KM) |
Partially restored |
3
(KM) |
Jan 26, 2026
12:57 PM |
|
|
4
|
Osori dara road
|
10
(KM) |
Partially restored |
4
(KM) |
Jan 26, 2026
12:52 PM |
|
|
5
|
bandai serai road
|
8
(KM) |
Partially restored |
2
(KM) |
Jan 26, 2026
12:44 PM |
|
|
6
|
Karo dara (left side) Road
No coordinates available
|
26
(KM) |
Not restored |
3
(KM) |
Jan 26, 2026
12:33 PM |
|
|
7
|
Samang Sheringle Road
|
6
(KM) |
Fully restored |
5
(KM) |
Jan 26, 2026
11:54 AM |
|
|
Remarks:
opened for traffic
Reported by:
XEN DIR UPPER
|
||||||
|
8
|
Aligasar Usheri
|
5
(KM) |
Fully restored |
5
(KM) |
Jan 26, 2026
11:48 AM |
|
|
Remarks:
opened for traffic
Reported by:
XEN DIR UPPER
|
||||||
|
9
|
Doon Achar Road
|
8
(KM) |
Partially restored |
8
(KM) |
Jan 26, 2026
11:41 AM |
|
|
Remarks:
work is in progress
Reported by:
XEN DIR UPPER
|
||||||
|
10
|
Sadiq Banda Panakot
|
3
(KM) |
Not restored |
3
(KM) |
Jan 26, 2026
11:21 AM |
|
|
Remarks:
Machinery will be mobilized. The Operating hours & Approximate cost may increase with time. As the road is closed, therefore no picture is available, and will be uploaded later.
Reported by:
XEN DIR UPPER
|
||||||
|
11
|
Barkand Road
No coordinates available
|
12
(KM) |
Fully restored |
7
(KM) |
Jan 26, 2026
11:15 AM |
|
|
Remarks:
opened for traffic
Reported by:
XEN DIR UPPER
|
||||||
|
12
|
Kilot Road Doag dara
|
6
(KM) |
Partially restored |
6
(KM) |
Jan 26, 2026
11:02 AM |
|
|
Remarks:
work is in progress will be cleared soon
Reported by:
XEN DIR UPPER
|
||||||
|
13
|
Goryal Sheringle Road
|
8
(KM) |
Fully restored |
8
(KM) |
Jan 26, 2026
10:54 AM |
|
|
Remarks:
Road opened for traffic
Reported by:
XEN DIR UPPER
|
||||||
|
14
|
Usheri Dara Main Road upto Gorkohi
|
32
(KM) |
Fully restored |
32
(KM) |
Jan 26, 2026
10:43 AM |
|
|
Remarks:
Main Road opened for traffic
Reported by:
XEN DIR UPPER
|
||||||
|
15
|
Bin dara Jaba bala Road
|
10
(KM) |
Partially restored |
10
(KM) |
Jan 26, 2026
10:41 AM |
|
|
Remarks:
Work is still under progress. The Operating hours & Approximate cost may increase with time. The pictures are without coordinates due to internet issue.
Reported by:
XEN DIR UPPER
|
||||||
|
16
|
Doag Dara Main Road and its links
|
45
(KM) |
Partially restored |
35
(KM) |
Jan 26, 2026
10:35 AM |
|
|
Remarks:
Main road will be cleared today and links will be cleared in two days
Reported by:
XEN DIR UPPER
|
||||||
|
17
|
Hayagai Road
No coordinates available
|
26
(KM) |
Not restored |
12
(KM) |
Jan 26, 2026
10:34 AM |
|
|
Remarks:
Work is still under progress. The Operating hours & Approximate cost may increase with time. The picture is of road leading to Hayagy. Actual Pictures will be shared later
Reported by:
XEN DIR UPPER
|
||||||
|
18
|
Badgoi Road
|
42
(KM) |
Not restored |
42
(KM) |
Jan 26, 2026
10:27 AM |
|
|
Remarks:
Badgoi road will be cleared in may june 2026 because badgoi top is closed upo june 206
Reported by:
XEN DIR UPPER
|
||||||
|
19
|
Jandrai Lamoti Road
|
12
(KM) |
Partially restored |
12
(KM) |
Jan 26, 2026
10:18 AM |
|
|
Remarks:
work is in progress will be cleared soon
Reported by:
XEN DIR UPPER
|
||||||
|
20
|
Gwaldi Dara Main Road
|
25
(KM) |
Partially restored |
25
(KM) |
Jan 26, 2026
10:12 AM |
|
|
Remarks:
Work is in progress will be cleared soon
Reported by:
XEN DIR UPPER
|
||||||
|
21
|
Ganshal Road
|
17
(KM) |
Partially restored |
17
(KM) |
Jan 26, 2026
10:05 AM |
|
|
Remarks:
work is in progress will be cleared soon
Reported by:
XEN DIR UPPER
|
||||||
|
22
|
Sonai Dara Road
|
5
(KM) |
Partially restored |
5
(KM) |
Jan 25, 2026
07:09 PM |
|
|
Remarks:
Work is still under progress. Only 1.8km portion remains to clear. The Operating hours & Approximate cost may increase with time.
Reported by:
XEN DIR UPPER
|
||||||
|
23
|
Hattan Dara Road
|
12
(KM) |
Fully restored |
8
(KM) |
Jan 25, 2026
07:03 PM |
|
|
Remarks:
Work is still under progress. Only 1km portion remains to clear. The Operating hours & Approximate cost may increase with time.
Reported by:
XEN DIR UPPER
|
||||||
|
24
|
Shingara Road
No coordinates available
|
15
(KM) |
Partially restored |
5
(KM) |
Jan 25, 2026
06:43 PM |
|
|
Remarks:
Work is still under progress. The Operating hours & Approximate cost may increase with time.
Reported by:
XEN DIR UPPER
|
||||||
|
25
|
Daskor Badali Maskari Road Wari
No coordinates available
|
12
(KM) |
Partially restored |
5
(KM) |
Jan 25, 2026
02:45 PM |
|
|
26
|
kakad Tangi Road Wari
No coordinates available
|
7
(KM) |
Fully restored |
3
(KM) |
Jan 25, 2026
02:39 PM |
|
|
27
|
sultankhel dara Mulvi Road
|
11.8
(KM) |
Fully restored |
1.5
(KM) |
Jan 25, 2026
01:33 PM |
|
|
28
|
sundal to arimanzai Road
|
5.96
(KM) |
Partially restored |
2
(KM) |
Jan 25, 2026
01:10 PM |
|
|
29
|
wari jilar road
|
15
(KM) |
Fully restored |
6
(KM) |
Jan 25, 2026
12:04 PM |
|
|
30
|
Gal pashta Road wari
No coordinates available
|
5
(KM) |
Fully restored |
3
(KM) |
Jan 25, 2026
11:27 AM |
|
|
31
|
Matar Shawkand Road
No coordinates available
|
8
(KM) |
Partially restored |
4
(KM) |
Jan 25, 2026
11:05 AM |
|
|
32
|
Nihag Dara Phase I Road
No coordinates available
|
27
(KM) |
Fully restored |
8
(KM) |
Jan 25, 2026
10:41 AM |
|
|
33
|
Dobando Road
|
10
(KM) |
Partially restored |
5
(KM) |
Jan 25, 2026
08:42 AM |
|
|
Remarks:
One tractor has been mobilized and road is partially clear for one side flow. Work is still under progress. The Operating hours & Approximate cost may increase.
Reported by:
XEN DIR UPPER
|
||||||
|
34
|
Shahikot Road
|
3
(KM) |
Partially restored |
3
(KM) |
Jan 24, 2026
09:18 PM |
|
|
Remarks:
One tractor has been mobilized and road is partially clear. for one side floor. Work is still under progress.
Reported by:
XEN DIR UPPER
|
||||||
|
35
|
Bijligar Chinar Muhalal Road
|
1.5
(KM) |
Fully restored |
1.5
(KM) |
Jan 24, 2026
09:06 PM |
|
|
Remarks:
One tractor has been mobilized and road is almost clear. Work is still under progress. Pictures during working hours is attached.
Reported by:
XEN DIR UPPER
|
||||||
|
36
|
Kair Dara Road
No coordinates available
|
18
(KM) |
Partially restored |
15
(KM) |
Jan 24, 2026
07:35 PM |
|
|
Remarks:
Snow height increases from start to the end of road. Two tractors have been mobilized and the road is almost clear. Kair Dara consists of Nalu Road, Shamorgar Road, Muto Road, Kair Khass Road
Reported by:
XEN DIR UPPER
|
||||||
|
37
|
Nasrat Dara Road
|
10
(KM) |
Partially restored |
10
(KM) |
Jan 24, 2026
07:24 PM |
|
|
Remarks:
Snow height increases from start to the end of road. Three tractors have been mobilized, and road is clear for one side traffic., each has worked for 25 hours till now. still the road is not clear completely. Complete cost of Clearing Nasrat Dara Roads is Rs.1.00 Million. This cost is for clearnce first spell of snow.
Reported by:
XEN DIR UPPER
|
||||||
|
38
|
Seyasan Dara Road
|
12
(KM) |
Partially restored |
12
(KM) |
Jan 24, 2026
01:09 PM |
|
|
Remarks:
Road is block due to heavy snowfall work is in progress
Reported by:
XEN DIR UPPER
|
||||||