Report Date:
January 27, 2026
Infrastructure Type:
Road
Total Damages:
8
Reported by:
Abbas Khan
(XEN KURRAM LOWER)
Affected Roads
Total Damages
Damaged Length
(KM)
Fully Restored
Partially Restored
Not Restored
Road Damages Overview
| S# | Road Name & Location | Total Length | Status | Damaged Length | Damage Coordinates | Date Reported |
|---|---|---|---|---|---|---|
|
1
|
Sarpakh to Sarpakh tanga road
|
4
(KM) |
Fully restored |
4
(KM) |
Jan 26, 2026
12:52 PM |
|
|
Remarks:
The road is cleared for traffic
Reported by:
XEN KURRAM LOWER
|
||||||
|
2
|
Sarpakh to Kimal Baza
|
5
(KM) |
Fully restored |
5
(KM) |
Jan 26, 2026
12:30 PM |
|
|
Remarks:
Road is cleared for traffic flow
Reported by:
XEN KURRAM LOWER
|
||||||
|
3
|
Khomasa to arwaza road
|
23
(KM) |
Fully restored |
23
(KM) |
Jan 26, 2026
12:16 PM |
|
|
Remarks:
The road is cleared for traffic flow
Reported by:
XEN KURRAM LOWER
|
||||||
|
4
|
Shashoo to tora warai via chinarak
|
37
(KM) |
Fully restored |
37
(KM) |
Jan 25, 2026
04:02 PM |
|
|
Remarks:
Complete road restored for traffic
Reported by:
XEN KURRAM LOWER
|
||||||
|
5
|
Sadda- Dogar road
|
22
(KM) |
Fully restored |
8
(KM) |
Jan 25, 2026
03:55 PM |
|
|
Remarks:
The road has been restored for traffic
Reported by:
XEN KURRAM LOWER
|
||||||
|
6
|
Makhrani to Sarpakh via gogani
|
5
(KM) |
Partially restored |
5
(KM) |
Jan 25, 2026
03:35 PM |
|
|
Remarks:
2 km cleared out of 5. The balance portion clearance is underway
Reported by:
XEN KURRAM LOWER
|
||||||
|
7
|
Sarpakh to Tauda Oba Via Gondal
|
06
(KM) |
Fully restored |
6
(KM) |
Jan 25, 2026
03:28 PM |
|
|
Remarks:
black top cleared from snow and traffic restored
Reported by:
XEN KURRAM LOWER
|
||||||
|
8
|
Avidara to Sarpakh road Center kurram
|
7
(KM) |
Partially restored |
7
(KM) |
Jan 25, 2026
03:08 PM |
|
|
Remarks:
One Tractor is continuously working in clearance of the road and partially road cleared
Reported by:
XEN KURRAM LOWER
|
||||||