Report Date:
January 27, 2026
Infrastructure Type:
Road
Total Damages:
3
Reported by:
Zahid Mehmood
(XEN South Waziristan (U))
Affected Roads
Total Damages
Damaged Length
(KM)
Fully Restored
Partially Restored
Not Restored
Road Damages Overview
| S# | Road Name & Location | Total Length | Status | Damaged Length | Damage Coordinates | Date Reported |
|---|---|---|---|---|---|---|
|
1
|
Baddar Road
|
20
(KM) |
Fully restored |
18
(KM) |
Jan 25, 2026
04:00 PM |
|
|
Remarks:
road is cleared
Reported by:
XEN South Waziristan (U)
|
||||||
|
2
|
Sam to Karama Road
|
20
(KM) |
Fully restored |
15
(KM) |
Jan 25, 2026
03:51 PM |
|
|
Remarks:
road is cleared
Reported by:
XEN South Waziristan (U)
|
||||||
|
3
|
Main Sararogha Makin Shakai Road
|
30
(KM) |
Fully restored |
25
(KM) |
Jan 25, 2026
03:30 PM |
|
|
Remarks:
road is cleared
Reported by:
XEN South Waziristan (U)
|
||||||